Key takeaways
- A project that needs Oncor construction, such as new poles, wire or transformers, starts with an online request, and a Project Manager makes contact within two business days.
- Oncor's Commercial and Industrial Load Requirements form, a site plan and an easement for Oncor facilities come before design is finished.
- Oncor's tariff calls for an estimated completion date and cost within ten business days of a detailed request.
- Oncor connects only after the city approves the installation, and the ESI ID and a retail provider come before the meter is set.
Oncor new commercial electric service means working with Oncor and the city at the same time. Oncor builds and owns the delivery side: the poles, wire and transformers that bring power to the property. The City of Dallas or Fort Worth inspects everything on the building's side. Neither sets the other's schedule, and Oncor will not connect until the city approves the installation. This guide sets out Oncor's steps for a new commercial service, from the online request to the meter, using Oncor's own pages, forms and tariff.
Who delivers electricity to businesses in Dallas and Fort Worth?
Oncor Electric Delivery serves the Dallas, Plano and Irving and the Fort Worth and Arlington metro areas, more than 400 communities in 98 counties. Each business buys its electricity from a retail provider of its choice. Oncor's delivery charges are billed to that provider, which Oncor's tariff calls the Competitive Retailer, and it passes them through.
The Public Utility Commission of Texas regulates the rates delivery utilities charge in competitive areas, but it does not set the final price retail providers charge. For a new service, the split tells you who to call: the retailer sells energy, while Oncor builds service, sets meters and connects. Most of Dallas and Fort Worth is served by Oncor; some edge areas are co-op territory. Fort Worth's own development guide lists CoServ, Johnson County Electric Co-Op and Tri-County Electric Cooperative among its utility contacts, and the PUC says co-ops and municipal utilities choose whether to join retail choice.
Oncor describes its territory on its economic development page. The PUC explains the split on understanding your electric bill and its municipal utilities and co-ops FAQ.
How do you start an Oncor new commercial service request?
Oncor's new construction page says to submit an online request if the project needs Oncor construction, for example new poles, wire or transformers. It covers a new business, a new warehouse or a new retail building at a location without electrical service, and the request site routes commercial and industrial projects separately from other types.
A larger service, a building on a vacant pad, or a move to three phase will usually mean Oncor work on its side of the meter. Whether a given job needs construction is Oncor's call, made with its Project Manager. When the online steps raise a question, Oncor names its New Construction Management Center, at 888.222.8045, as the place to call.
The request starts on Oncor's commercial request form, reached from its new construction page.
What happens after the request is submitted?
Oncor asks the requester to create a Construction Portal account with the same email used on the request form, to see the project's status and updates throughout. A Project Manager is assigned to the request, and Oncor says to expect a phone call or email from that person within two business days of submitting it.
The tariff sets the same contact window and lists six items every construction service request must include: the customer contact name, the contact phone number, the ESI ID if one exists, the service address with directions and access instructions, the construction services requested, and the date the customer wants the work done. A complete request is the quickest way through. Name a contact who answers the phone and can decide things about the site, because the Project Manager will call that person.
What does Oncor's commercial and industrial load form ask for?
The Commercial and Industrial Load Requirements form asks for the general and electrical contractors, requested dates for temporary and permanent service, the meters and amps, the voltage, and the HVAC, motor and lighting loads. It also asks whether the load is new or added to a service that is already energized, and it goes back to the Project Manager.
- A copy of the plat, with water and sewer prints.
- A site plan showing the proposed transformer, meter and other Oncor equipment locations.
- A survey or plat if the Project Manager asks for one.
- An easement for the onsite Oncor facilities, by final plat or by a separate instrument.
- One load form for each voltage and phase type on the job.
That last item catches people. Oncor's Customer Checklist gives the example of trailer power, construction power and crane power at three different voltages needing three separate load forms. The checklist also asks for civil and electrical plans: the plat, the site plan, a riser diagram and the electric panel schedule. These are the same load numbers the city's plan review checks, so we fill in the Oncor form from the load calculation in the permit set.
The form is Oncor's Commercial and Industrial Load Requirements, and the plan list is in its Customer Checklist.
When does Oncor give an estimate of cost and completion?
Oncor's tariff says that, unless Oncor and the customer agree otherwise, Oncor gives the requester an estimated completion date and an estimated cost for all charges within ten business days of receiving a detailed request. For non-residential extensions that need construction, the work should be completed within the time Oncor estimates.
The words that matter are detailed request. The estimate clock depends on Oncor having the load form, the site plan and the other items above. The load form adds that a Contribution in Aid of Construction is payable to Oncor before any construction is scheduled, and that permits, easements and surveying add design time. Oncor's checklist warns that long lead time equipment can take months to be delivered, which is why the request should go in as soon as the service size is known.
What must be done before Oncor schedules construction?
Oncor's Customer Checklist says it cannot schedule construction until the contracts and payments are received, the original easement documents are executed and received, all civil construction by the customer is approved by an Oncor inspector, and the site is within about 3 inches of final grade. Each item is the customer's to finish.
Underground work has its own rule. Oncor's Electric Service Guidelines say service lateral conduit must meet the 24 inch NEC burial depth to the top of the conduit, and on commercial and industrial installations an inspection before cover up is mandatory. The Guidelines, February 2025 edition, apply to construction starting on or after that month, and the customer is responsible for having the latest revision.
The burial and inspection rules are in Oncor's Electric Service Guidelines. The estimate timing is Section 5.7.3 of Oncor's Tariff for Retail Delivery Service, listed on its tariffs and rate schedules page.
Why does Oncor wait for the city before connecting?
Because its tariff says so. Where an ordinance requires a permit or inspection, the customer must obtain them, and Oncor will not interconnect until it receives notification that the proper authority approved the installation. In Dallas and Fort Worth that approval is called a release, and Oncor's own Guidelines say Oncor does not inspect the customer's equipment.
Dallas's Chapter 56 also says only authorized Oncor employees may connect Oncor's service conductors to the customer's service entrance conductors. So the end of a job runs in a fixed order: the city's final inspection, the city's release, then Oncor's connection. In Fort Worth, the numbered electrical final for permanent power plays the same part.
The city side is in how commercial electrical permits work in Dallas. For new or larger service, see our Dallas service upgrades and switchgear page or the Fort Worth service upgrades and switchgear page.
When is the ESI ID issued, and why does it matter?
Oncor says that when the location is ready for service, the Project Manager provides an ESI ID. The customer then chooses a retail provider and rate plan, with Oncor pointing to powertochoose.org, and meters are installed based on the start date chosen with that provider. Construction or property access problems can move the meter date.
The ESI ID is the number that identifies the service point, and the retailer and Oncor both use it from then on. Have the retail provider chosen before the release is expected, so the meter order is waiting when the city's approval reaches Oncor rather than the other way round.
How does temporary construction power fit in?
Temporary service starts with a call to Oncor at 1.888.222.8045, and the Guidelines say the customer must choose a retail electric provider before a temporary meter is energized. The tariff adds that temporary delivery facilities are paid for before Oncor builds them, and the city still has to release the temporary installation first.
On an overhead temporary service, the customer provides and installs the pole, at least 4 by 4 inches by 16 feet unspliced or a treated pole at least 5 inches across the top, tall enough for the service drop clearances and marked with the address in numbers at least 3 inches high. Oncor owns and installs the service drop. Oncor's checklist asks for a marked up site plan showing where the temporary point of delivery will be.
What should an owner have ready before calling Oncor?
Have the service size, the voltage and phase, the loads by type, the site plan with proposed equipment locations, the plat, and the dates wanted for temporary and permanent service. Know who will sign the easement and who will pay, because Oncor will not schedule construction without contracts, payment and executed easement documents.
- The confirmed utility for the address: Oncor, or a co-op at the edge of the metro.
- A load calculation that matches the one in the city permit set.
- A site plan marking transformer, meter and Oncor equipment locations.
- A contact who can answer for the site and the schedule.
- A plan for temporary power, if the trades need it.
When the bill arrives, the demand line is its own subject: see Oncor demand charges and LED retrofits. The Dallas commercial electrician hub lists all our Dallas work, and our commercial electrical services page covers the rest of Texas.