How Commercial Electrical Permits Work in Dallas, From DallasNow to the Power Release

November 1, 2026Last updated 7 min readWattsmith Electric · TECL 41806

Key takeaways

  • Electrical work on commercial property in Dallas needs a registered electrical contractor and a permit, and every application now goes through DallasNow.
  • Electrical plan review checks one-line diagrams, load calculations, conductor sizing, overcurrent protection and grounding, with an initial review goal of 15 days.
  • A temporary utility release lets part of the job be energized before the final, but only after a passed service inspection and the inspector's approval.
  • Oncor connects only after the city approves the installation, and only Oncor employees may connect Oncor's service conductors.

A commercial electrical permit in Dallas runs through one system, DallasNow, and ends with a step many owners have never heard named: the city's release of power to Oncor. Between the two sit the electrical plan review, the inspections and, on many jobs, a temporary utility release so the trades can work under lights. This guide sets out each step from the City of Dallas's own documents, so a property manager or general contractor planning a Dallas build-out knows what is waiting on whom.

Who can pull a commercial electrical permit in Dallas?

The city's electrical permit checklist says electrical work on commercial property requires a registered electrical contractor and a permit. Chapter 56 adds that no one may engage in the business of electrical contracting without city registration, and that a qualified electrician of proper classification must be on site supervising the permitted work.

So the permit belongs to the electrical contractor, bought in its own name under its own city registration. A building owner or general contractor does not buy it for the electrician. The state rule sits underneath: TDLR says anyone who performs electrical work in Texas must be licensed. Our Texas electrical contractor license is TECL 41806, and we register with the City of Dallas before any Dallas permit is bought, as the city requires.

The registration rules have their own guide, Dallas electrical contractor registration. The permit rule is on the city's Electrical Permit Application Checklist, and TDLR's licensing rule is in its electricians FAQ.

What is DallasNow, and what goes through it?

DallasNow is the City of Dallas land management system, launched May 5, 2025 to replace the decades-old Posse platform. It brings permitting, planning, platting, zoning, engineering and inspections into one system, and the city's development guide says all development applications, permitting included, are now submitted through it. Multi-page PDF documents can be uploaded there.

For the electrical contractor that means one place for the permit application, the plan sheets and, later, the inspection requests. Some older city forms still name Posse; the process they describe now runs in DallasNow. Upload the electrical sheets as complete PDF sets rather than loose pages, so the reviewer reads the one-line, the panel schedules and the layout together.

The city describes the system on its DallasNow page and in the 2025 to 2026 City of Dallas Development Guide.

What do Dallas electrical plans have to show?

When electrical plans go in with the permit, the city's checklist lists seven items: a diagram of the electrical service, conductor and pipe sizes, the grounding electrode system diagram and conductor sizes, overcurrent protection for the service conductors, the service location at the structure, the number and location of services, and the floor plan power and lighting layout.

There is one shortcut. Where electrical plans were already included in the master permit set submitted for plan review, the checklist says no further plan submittal is required for electrical validation on that master permit. On a tenant build-out with a full set of construction documents, that means the electrical sheets travel with the building permit and are not sent a second time.

What does the Dallas electrical plan review check?

Dallas's development guide says electrical plan reviewers examine drawings, one-line diagrams, load calculations and equipment specifications to verify conductor sizing, overcurrent protection, grounding and system coordination against the NEC and local ordinances. It asks for a full one-line diagram for the service and distribution, the calculated load for the service and every panelboard, and panel schedules.

The same guide lists Electrical Code as one of the technical reviews that are part of a Dallas building permit application, so on a commercial job the electrical sheets are read alongside the building review, not after it. A reviewer who cannot find a load calculation or a panel schedule asks for it, and every question adds a round of comments.

  • A full one-line diagram for the service and premises wiring distribution.
  • The calculated load for the service and for each panelboard.
  • Panel schedules for every new or changed panel.
  • The grounding electrode system diagram with conductor sizes.
  • The floor plan power and lighting layout.

How long does Dallas electrical plan review take?

The development guide gives an initial review performance goal of 15 days for electrical reviews. It does not say whether those are business or calendar days, and a goal is not a promise. Treat the 15 days as the first look only; comments sent back start another round once the corrected sheets go in.

The surest way to hold plan review to one round is a complete set: every panel scheduled, every load counted, and the service diagram matching the one-line. When we take on a Dallas job, we check the electrical sheets against the list above before the set goes in, and where the job calls for an engineer's seal, the engineer of record provides it.

How are Dallas electrical inspections scheduled?

The development guide says to schedule inspections through DallasNow when the work is ready and 24 hours in advance, and the city also takes requests through its IVR phone system. It adds that approved plans must be on site for the inspector. On an electrical permit, the request comes from the electrical contractor doing the work.

Plan each request around the stage that is actually finished. Have the approved plans on site, keep the work area open and reachable, and call the inspection only when the stage is complete, because a visit the inspector cannot pass costs another day of notice and pushes every trade waiting behind it.

What is a temporary utility release in Dallas?

It is the city's approval to energize part of an installation before the final, so trades can work and equipment can be tested. Dallas calls authorizing power a release. For a temporary one, the electrical contractor signs a Request for Temporary Utilities form and must show a valid reason for the release of power.

  • The electrical room must be dried in.
  • The panel must have a lock, or the electrical room door must lock.
  • A notarized letter from the general contractor and the electrical contractor says only the journeyman overseeing the job holds the key.
  • The service inspection must pass.
  • The equipment tied to the release is inspected, and its wiring must be 100 percent complete.
  • No equipment or lighting is energized before the inspector approves it.

The request form also carries two promises. The owner agrees that the building or suite will not be occupied before all final inspections are approved and a Certificate of Occupancy is obtained where one is required, and that the utility will be disconnected a set number of days after the release, or sooner if the terms are broken. The form leaves the number of days blank, so confirm it with the inspector.

The city's Temporary Utility Release Form Interpretation lists the electrical items, and the Request for Temporary Utilities form carries the occupancy and disconnection terms.

When does Oncor connect a Dallas commercial service?

Only after the city approves the installation. Oncor's tariff says it will not interconnect with a customer's electrical installation until it receives notification of approval from the proper authority, and in Dallas that approval is the city's release of power. Chapter 56 adds that only authorized Oncor employees may connect Oncor's service conductors to the customer's.

Chapter 56 draws the line in one more place: when Oncor installs underground service lateral conductors to a commercial building, that installation, conduit included, needs no inspection or approval by the City of Dallas. The electrician's work ends at the service entrance conductors, Oncor's begins there, and the city inspects only the customer's side. If the space needs new or larger service, the Oncor request should be in long before the final.

Oncor's steps are in our guide to Oncor new commercial electric service. The connection rules are in Chapter 56 of the Dallas City Code and Section 5.4.2 of Oncor's Tariff for Retail Delivery Service.

Can Dallas release power before an inspection after damage?

Sometimes. Dallas's Emergency Release Policy lists vehicle damage, storm damage, fire damage and meter damage as emergencies that may warrant a power release before inspection. A licensed contractor registered with the City of Dallas must make the request, the structure must be occupied or vacant because of the outage, and a permit and inspection follow.

The policy says plainly that the list is not complete and that no release without inspection is guaranteed: some services are too large or complicated for the allowance, and the inspector decides. The city's storm damage page adds that Oncor may require an electrical permit and inspection before releasing power in any case. For a business with a damaged service, the first call is to a registered electrical contractor who can request the release and pull the permit.

Read the city's Emergency Electrical Release Policy and its storm damage repair page. Our emergency commercial electrician Dallas page covers what we do when a business loses its service.

How should a building owner plan around the Dallas permit order?

Plan the electrical schedule around the city's gates, not the trades' availability. Confirm the contractor's Dallas registration before the bid is accepted, get complete electrical sheets into the DallasNow submittal, allow for the review goal and a round of comments, and file the Oncor request well before the final so the release is not waiting on the utility.

  • Confirm the electrical contractor's City of Dallas registration and insurance are current.
  • Put the one-line diagram, load calculations and panel schedules in the plan set.
  • Expect the first electrical review comments on the city's 15 day goal, and plan for a second round.
  • Ask for a temporary utility release only when the electrical room is dried in and lockable.
  • Keep approved plans on site for every inspection.
  • Start the Oncor request as soon as the service size is known.

We work Dallas from San Antonio and plan each trip around the stage the space is ready for, so a visit ends with an inspection requested rather than a crew waiting on one.

For suites and storefronts, see our tenant build-out electrician Dallas page, and for the code itself, the Dallas Electrical Code guide. The Dallas commercial electrician hub lists all our Dallas work, and our commercial electrical services page covers the rest of Texas.

FAQ

Common questions

Straight answers. If you do not see yours, call us and ask.

Can a general contractor buy the electrical permit in Dallas?

No. The city says electrical work on commercial property requires a registered electrical contractor and a permit, and the permit system will not issue a permit to an unregistered contractor.

How long is the Dallas electrical plan review?

The development guide gives an initial review performance goal of 15 days for electrical reviews, without saying business or calendar days. Comments start another round.

What does the city's release of power mean?

It is the city's approval that lets Oncor connect or energize the installation. Oncor will not interconnect until it is notified that the proper authority has approved the work.

Ready to get it handled?

Flat-rate pricing quoted up front. Licensed and insured. A Wattsmith electrician calls you back within 15 minutes during business hours.

  • Licensed and Insured
  • BBB Accredited
  • Flat-Rate Pricing
  • Background-Checked
Call NowGet a Quote