Key takeaways
- AEP Texas delivers power to the majority of Corpus Christi; Nueces Electric Cooperative serves parts of Nueces County, so confirm the utility for the address first.
- A new business requests permanent service on AEP Texas's online form, and every construction request must carry the six items the tariff lists.
- AEP Texas contacts the person named within two business days but does not guarantee construction timelines.
- AEP Texas connects only after the proper authority approves the installation, and inside city limits a new meter where none existed needs a city inspection.
Getting new commercial service from AEP Texas in Corpus Christi means two parties work the same job from opposite sides of the meter. AEP Texas builds and connects the delivery side. The City of Corpus Christi permits and inspects the building's side. AEP Texas will not connect until the City approves, and the City will not approve until the installation passes. This guide lays out the AEP Texas steps for a new business service, using the company's own web forms, its Tariff for Retail Delivery Service and its meter guide.
Does AEP Texas serve every Corpus Christi business?
No. The City says AEP Texas provides power to the majority of Corpus Christi, and that Nueces Electric Cooperative provides electricity to parts of Nueces County. The City itself does not supply electricity. AEP Texas's tariff lists Nueces County and Corpus Christi in the area it serves, but confirm the utility for each address.
That check is the first step on any new service, because the forms, rules and contacts in this guide are AEP Texas's. A site served by the cooperative follows the cooperative's process instead. The deed, a neighboring business's bill or the utility's own service map will usually settle it in a few minutes.
The City's utility list is on its recover from disasters page, and AEP Texas's service area is in Section 2.2 of its Tariff for Retail Delivery Service.
Who sells the electricity if AEP Texas delivers it?
A retail electric provider the business chooses. AEP Texas's tariff says it bills its delivery charges to the customer's selected competitive retailer, and its guide says Texas Choice is applied for by contacting a retail electric provider well ahead of the date service is needed. The PUC explains the choice for customers inside ERCOT.
The PUC's wording is that customers in the ERCOT region who are not served by an electric cooperative or a municipally owned utility can choose their provider. A business served by Nueces Electric Cooperative falls outside that sentence. For an AEP Texas site, the provider sells the energy, while every construction and connection step below runs between the owner, the electrician, AEP Texas and the City.
The PUC's explanation is on its choosing an electric plan page.
How do you request new commercial service from AEP Texas?
Through the Permanent Service for a New Business form on AEP Texas's Builders and Contractors pages. The form is for a newly constructed business facility and asks for the customer name, site address, driving directions, mailing address, phone and project details. The same pages hold the temporary service form, the generator page and the meter guide.
AEP Texas describes these as online forms, not a separate builder portal. For a construction job that needs power before the permanent service is ready, the Temporary Service form requests an ESI ID for electrical service during construction, and the tariff says temporary delivery facilities are paid for before AEP Texas builds them. The meter guide shows the temporary pole details.
The forms are on AEP Texas's Builders and Contractors page, including the new business service form and the temporary service form.
What must an AEP Texas construction request include?
AEP Texas's tariff lists six items for every construction service request: the customer contact name, the contact phone number, the ESI ID if one exists, the service address with city, zip code, directions and access instructions, the construction services wanted, and the date requested. AEP Texas then contacts the named person within two business days.
- Retail customer contact name.
- Retail customer contact phone number.
- The ESI ID, if it exists and is available.
- Service address with city and zip code, directions, and access instructions when needed.
- The construction services requested.
- The date requested for AEP Texas to perform or provide them.
Name a contact who answers the phone and can decide things about the site, because that is who AEP Texas will call. The ESI ID matters twice: AEP Texas asks for it here, and the City's trade permit form says electrical service releases need the ESID number. When we handle the electrical side, we help the owner put one consistent set of details into both.
How long does AEP Texas take to build new service?
AEP Texas does not promise a timeline. Its tariff says the company will make reasonable provisions to provide construction service but does not guarantee its timeliness. No AEP Texas page found gives a number of days for new commercial service, so the honest plan is to file early and keep the requested date realistic.
AEP Texas's build and the electrician's installation can run side by side. The step that cannot overlap is the end of the job, because the connection waits on the City's approval. For that reason we tell owners to send the new business form as soon as the service size and location are settled, not when the gear is set.
When does AEP Texas connect the service?
Only after the proper authority approves the electrical installation. Section 5.4.2 of the AEP Texas tariff says that where an ordinance requires a permit or certificate of inspection, the company will not connect until it receives notice of approval. In Corpus Christi that approval is the City's service release, performed by a City inspector.
AEP Texas's permit and inspection entry for Corpus Christi says that inside city limits a non-residential premises needs a city inspection where there was no previous meter, and for upgrades or repairs to an existing meter enclosure. A premises outside city limits that receives city water and sewer also needs a city permit and inspection, so check before assuming a site is exempt.
The entry is on AEP Texas's permit and inspection requirements page, with Corpus Christi chosen from the list. The City's side is covered in how commercial electrical permits work in Corpus Christi.
Which AEP guide covers the electrician's side of the meter?
AEP's Guide for Electric Service and Meter Installations (2026), linked from AEP Texas's builders page as the Meter and Service Guide. It says the customer is responsible for obtaining the inspections the local authority requires, and that the customer must notify the company before altering service entrance equipment so facilities of proper capacity can be provided.
The guide covers several AEP companies and says it is written for residential buildings and small commercial establishments. For larger commercial or industrial jobs, it says the engineer, architect or electrical contractor should contact the company for detailed service requirements. On a bigger service we make that call early, before the gear is ordered.
Read AEP's Guide for Electric Service and Meter Installations (2026) for the meter and service rules.
What does the electrical contractor handle in a new service?
Everything on the customer's side of the point of delivery: the service entrance, switchgear or panelboards, meter equipment and feeders, built under a City of Corpus Christi electrical permit to the meter guide's rules. Then the contractor calls the inspections, schedules the service release in the INFOR Portal with the ESID, and follows it through.
On our side that means the gear is set, wired, tested and labeled before AEP Texas's crew arrives. Services follow NEC Article 230, and switchboards and panelboards get the arc flash warning labels NEC 110.16 calls for. We install those labels; a detailed arc flash study is an engineer's work. We work Corpus Christi from San Antonio, and every job is priced after the free written estimate.
See our commercial service upgrade Corpus Christi page, the Corpus Christi electrical company hub, and our commercial electrical services across Texas. Billing on the new service is covered in AEP Texas demand charges.