Key takeaways
- A commercial business owner or builder calls CenterPoint at 713-207-2222 to have an ESI ID created, and files an online Electric Service Request when CenterPoint has to build.
- CenterPoint's tariff lists six items every construction request must carry, and says CenterPoint does not guarantee construction timelines.
- CenterPoint connects only after the city's approval reaches its Permit Desk; meters are usually set 3 to 5 business days from the requested date.
- Temporary construction service is paid for before CenterPoint builds it.
New commercial electric service in Houston means working with CenterPoint Energy and the city at the same time. CenterPoint owns the poles, wires, transformers and meters. The city inspects everything on the building's side. Neither moves the other's schedule, and CenterPoint will not connect until the city says the installation is approved. This guide sets out CenterPoint's steps for a new commercial service, from the ESI ID to the meter, using CenterPoint's own service connect page and its Tariff for Retail Delivery Service, so a Houston owner or builder knows what to file and when.
Who delivers electricity to a Houston business?
CenterPoint Energy Houston Electric delivers the power across its Houston service area, while each business buys electricity from a retail electric provider of its choice. CenterPoint's delivery charges go to that provider, which CenterPoint's tariff calls the Competitive Retailer, and the provider passes them through on the bill the business pays.
For a new service, that split tells you who to call. The retail provider sells the energy, but it does not build service, set meters or approve a connection. Every step in this guide is between the customer, the customer's electrician, CenterPoint and the City of Houston.
How do you get an ESI ID from CenterPoint?
CenterPoint's service connect page tells a commercial business owner or commercial builder to call 713-207-2222 to have an Electric Service Identifier, the ESI ID, created. The ESI ID is the number that identifies the service point, and the retail provider and CenterPoint both use it from then on.
Get the ESI ID early. It is one of the items a construction request asks for when it exists, and having it ready keeps the request from going back and forth. CenterPoint lists separate routes for home builders and for multi-unit builders; a commercial project uses the phone number above.
When does a project need an Electric Service Request?
A project needs an online Electric Service Request, or ESR, when it needs CenterPoint Energy construction, such as new poles, wire or transformers. CenterPoint's portal center describes the ESR portal as the place to submit and track requests for new or modified electric service. A local service consultant then reaches out within two business days.
A larger service, a new building on a vacant pad, or a move from single phase to three phase will usually mean CenterPoint work on its side of the meter. Whether a particular job needs construction is CenterPoint's call, made with its consultant. The same portal center also lists the Joint Trench portal for underground residential projects, the MUG Project portal for major underground projects, and a Transfer Switch portal.
The ESR and the other portals are on CenterPoint's portal center, and the phone and online routes are on its service connect page.
What must a CenterPoint construction request include?
CenterPoint's tariff says every construction service request must include six items: the customer contact name, the contact phone number, the ESI ID if one exists, the service address with directions and access instructions, the construction services requested, and the date the customer wants the work done. CenterPoint then contacts the designated person within two business days.
- Retail customer contact name.
- Retail customer contact phone number.
- ESI ID, if it exists and is available.
- Service address, including city and zip code, directions to the location, and access instructions when needed.
- The construction services requested.
- The requested date for CenterPoint to perform or provide the construction service.
A complete request is the quickest way through this step. The contact named should be someone who answers the phone and can make decisions about the site, because CenterPoint's consultant will call that person. When we handle the electrical side of a new service, we help the owner put the request together so the address, access and date match the project schedule.
How long does CenterPoint construction take?
CenterPoint does not promise a construction timeline. Its tariff says it will make reasonable provisions to provide construction service but does not guarantee the timeliness of starting or finishing it. The practical answer for an owner is to file the request as early as the project allows and to keep the requested date realistic.
That is why we tell owners to start the CenterPoint request well before the building's electrical work is done. CenterPoint's construction and the electrical contractor's installation can run side by side. What cannot be overlapped is the end: CenterPoint's connection waits on the city, and the meter follows the connection.
The request rules are in Section 5.3 of CenterPoint's Tariff for Retail Delivery Service.
Why does CenterPoint wait for the city before connecting?
CenterPoint will interconnect its facilities only when notification of approval, or a permit number, from the proper authority is received at the CenterPoint Energy Permit Desk. In Houston that approval is the city's utility release, which the Electrical Inspections section performs after the installation passes inspection. Without it, CenterPoint does not connect.
The tariff says the same in Section 5.4.2: CenterPoint will not connect its delivery system to the customer's installation until it receives notification that the proper authority has approved it. The city's code matches from the other direction. Premises wiring may not be connected to a source of energy until approved by the building official. CenterPoint's page also puts the duty on the customer to obtain the permits a local ordinance requires.
The city's permit and inspection order is covered in how commercial electrical permits work in Houston, and the release is listed among the duties of the city's Electrical Inspections section.
How soon is the meter set after the city's release?
CenterPoint says meters are usually installed within 3 to 5 business days of the requested start date, weather and workload permitting. The meter comes after the city's approval reaches the Permit Desk, so an owner planning an opening date should count from the release, not from the end of the electrical work.
The words usually and permitting matter. After a storm, or in a busy construction season, the window can move. Build a few days of slack between the expected release and the opening, and keep the requested start date in CenterPoint's system current if the schedule shifts.
Who pays for temporary construction service?
The customer, in advance. CenterPoint's tariff says the customer or the entity asking for temporary service shall pay CenterPoint before it constructs temporary delivery facilities, under the tariff's rate chapter. On the city's side, temporary power is its own Temporary Cut-In permit, bought only after all of the project's permits are purchased.
Temporary service is often worth it on a long job, because it lets trades work and lets the electrician test circuits before the permanent service is ready. The amount CenterPoint charges is set by its tariff and its consultant, not by us, and our own work is priced after the free written estimate.
The city's Temporary Cut-In permit page lists plan review and inspection as required.
What does the electrical contractor handle in a new service?
The electrical contractor builds everything on the customer's side: the service entrance, switchgear or panels, meter equipment and feeders, under a Houston electrical permit with plan review. The installation also follows CenterPoint's rule book for customers and electricians, its Service Standards, which sit under the tariff. Then the contractor calls inspections and follows the release through.
On our side that means the gear is set, wired, tested and labeled before CenterPoint's crew arrives. Services follow NEC Article 230, and switchboards and panelboards get the arc flash warning labels NEC 110.16 calls for. We install those labels; a detailed arc flash study is an engineer's work. We work Houston from San Antonio and plan the trips so the gear is ready on the day CenterPoint can connect.
See our commercial service upgrades and switchgear Houston page, the Houston commercial electrician hub, and our commercial electrical services across Texas.