Oncor's request and project manager
When the change needs Oncor construction such as poles, wire or a transformer, it begins with Oncor's online request, and Oncor says a Project Manager calls or emails within two business days. Its Commercial and Industrial Load Requirements form has a box for adding load to an energized service, along with the voltage, motor, HVAC and lighting loads.
- Online request to Oncor
- Load form marked for added load
- Site plan showing Oncor's equipment