Key takeaways
- Install day is usually one day: pad, unit, transfer switch, wiring, the plumber's gas line, then start-up.
- The power is off for part of the day while the switch goes in at the meter.
- Before we leave, we cut utility power on purpose and you watch the Generac carry the house.
Generac installation day is the day the planning turns into a machine in your side yard. As a Generac Aligned Contractor, we sell and install Generac home standby and commercial generators. Here is how the day runs, so nothing on it is a surprise. The steps before it are in our home standby generator installation timeline.
What happens first thing in the morning?
The crew walks the plan with you: where the unit sits, where the transfer switch goes, the route of the wiring and the gas line. Then the pad goes down on level ground at the spot agreed on the visit, back from windows, doors and vents as Generac and your city require.
When does the power go off?
When the transfer switch goes in. A whole house switch usually sits at the meter, so the meter is pulled and the house is without utility power while it is wired. We tell you the window ahead of time. Keep the refrigerator closed and phones charged.
Who runs the gas line?
A licensed plumber. Gas piping in Texas is plumbing work. The gas line is included in your price, and we schedule the plumber around the electrical work. More in who runs the gas line for a Generac.
What does start-up involve?
- Checking the oil, the battery and the connections before the first start.
- Starting the unit and letting it warm up.
- Running it under load to confirm it carries what it was sized for.
- Cutting utility power on purpose to watch the switch move the house over, then back.
- Setting the exercise schedule.
What do I need to do on the day?
- Clear the path to the side yard and the meter, and keep pets inside.
- Make sure we can reach the panel indoors.
- Be home for the walk-through at the start and the start-up at the end.
- Have your phone ready for the app setup.
How do I watch it from my phone?
Generac calls its system Mobile Link. We set it up with you at start-up so you can see the unit's status and get alerts. Our guide on Generac Mobile Link setup and alerts covers it.
How long does the crew stay?
Most installs finish in a day. A long wiring run, a panel that needs work before the switch goes in, or rock where the pad goes can push it into a second day. We tell you on the visit if your house is likely to be one of those, so the day does not surprise anyone.
What should I expect it to sound like?
Generac publishes the sound level for each model at 23 feet under normal load and during its quieter low-speed exercise. Those figures are on each model page, such as the Generac 22kW generator. During start-up you hear it at full speed under load, which is the loudest it gets.
What if there is an inspection?
Where the city requires a permit, the inspection is on its own date, sometimes the same day and sometimes after. If there is a correction, we make it and call for the re-inspection on the same permit.
To start, book a free Generac sizing visit, or see the Generac generators page and the Generac generator cost guide. Installation details are on Generac generator installation.