Commercial Generator Installation in Dallas: Sizing, Switch and Permit

November 1, 2026Last updated 6 min readWattsmith Electric · TECL 41806

Key takeaways

  • A generator is sized from the loads it must carry, measured or calculated, not from the size of the building.
  • NEC Article 700 covers emergency systems, 701 legally required standby and 702 optional standby, and each sets its own wiring rules.
  • Oncor's Electric Service Guidelines put the transfer switch on the load side of the meter base, never in series with the meter.
  • Dallas lists generators among the projects its building code review covers, and the electrical work goes in under a city permit.
  • The price is set at the free site visit, from the loads, the transfer switch and the fuel supply.

Commercial generator installation in Dallas comes down to four decisions made in order: which loads must stay on, how large a generator carries them, where the transfer switch goes on the Oncor service, and which code article and permit the system falls under. The weather makes the case for it. Winter Storm Uri in 2021, the ice of 2023 and the storm that crossed DFW in May 2024 all left businesses dark for hours or days. This guide covers sizing, the transfer switch, NEC Articles 700, 701 and 702, the City of Dallas permit, and what happens after a storm.

Why do Dallas businesses install standby generators?

Because North Texas loses power in more than one season. In February 2021 the National Weather Service recorded 139 straight hours at or below freezing at DFW Airport. In early 2023 it recorded ice up to half an inch across North and Central Texas. In May 2024 Oncor reported a storm causing more than 650,000 customer outages.

The 2021 storm was statewide. ERCOT's chief executive told Congress that at its worst the storm took out 48.6% of the generation available to ERCOT, and that without the controlled outages power could have been out for 90% of Texans for weeks. The 2024 storm was local and physical: Oncor said wide swaths of lines in the hardest-hit areas had to be rebuilt, with poles and transformers replaced first. A building on a rebuilt line waits for that work, and a generator is what keeps it open meanwhile.

Sources: NWS Fort Worth on February 2021 and January and February 2023, ERCOT's March 24, 2021 statement and Oncor's May 29, 2024 restoration update. Our guide to DFW storm standby power has the longer record.

How is a commercial generator sized?

From the loads it must carry. We list every load the business wants on during an outage, from refrigeration and servers to lighting, pumps and HVAC, then measure what they draw or calculate it the way NEC Article 220 does. Motors get extra attention, because the current to start them runs well above the current to run them.

The list usually splits into must-run and nice-to-have. A restaurant may keep its walk-in coolers, a few circuits of lighting and the point-of-sale system, and let the dining room HVAC wait. A warehouse may need its dock doors and racking lights but not every office. Each choice moves the size, and the size moves the fuel, the pad, the transfer switch and the conductors. A generator sized to the whole building when the business only needs part of it buys capacity that never runs.

Runtime is the other half of sizing. A natural gas unit draws from the utility line for as long as gas flows, while a diesel unit runs as long as its tank lasts, so the fuel choice sets how long the building can go without help. The 2021 freeze lasted days, not hours, which is why the question of how long belongs beside the question of how much.

Which NEC article applies: 700, 701 or 702?

It depends on why the system is there. Article 700 covers emergency systems that code requires for life safety, such as egress lighting. Article 701 covers legally required standby, where a code or authority requires power for other purposes. Article 702 covers optional standby, which a business chooses to protect its own operations.

Most business generators are optional standby under Article 702. The distinction is not a label: Articles 700 and 701 set tighter rules on how the wiring is kept apart from other circuits, how fast the transfer happens and how the system is tested. A building that has both needs both designs, often with separate transfer switches. The drawings should say which article each circuit falls under, because the plan reviewer and the inspector will check it against that article.

Where does the transfer switch go on an Oncor service?

On the load side of the meter base. Oncor's Electric Service Guidelines say a customer generator transfer switch is to be installed on the load side of the meter base, and that under no circumstances may it be built into the meter base or placed in series with the meter and the base.

That rule keeps the generator from feeding back into Oncor's lines while crews work on them. The switch can be automatic or manual, and it can switch the whole service or a separate standby panel fed with only the chosen loads. On a large service the transfer switch may sit at the main switchgear; on a smaller one it often feeds a dedicated panel. Either way it sits after the meter, on the customer's side, and Oncor's meter base is left as Oncor built it.

Source: Oncor's Electric Service Guidelines, February 2025 edition.

What permit does a commercial generator need in Dallas?

A City of Dallas electrical permit, applied for through DallasNow. Dallas says electrical work on commercial property requires a registered electrical contractor and a permit, and its development guide lists generators among the projects reviewed by Building Code review. Electrical plan review checks the one-line diagram and load calculations against the NEC.

Inspections are scheduled through DallasNow at least 24 hours ahead, with the approved plans on site. Oncor's tariff says it will not connect any customer installation until it hears that the proper authority approved it, so the city's sign-off comes before anything ties into the service. The generator's pad, fuel line and enclosure often involve other trades and their own reviews. We register with the City of Dallas before a permit is bought, as the city requires.

Sources: the city's Electrical Permit Application Checklist, the 2025 to 2026 Development Guide, pages 35, 36 and 59, and Oncor's Tariff for Retail Delivery Service, Section 5.4.2.

What happens when a storm damages the electrical service?

An electrician fixes the damage before Oncor restores power. Oncor said after the May 2024 storm that a damaged or pulled-off meter base or weatherhead must be repaired by an electrician first, and that city inspections may also be required. Dallas's storm page says Oncor may require a permit and inspection before releasing power.

Dallas has an Emergency Release Policy for these cases. Vehicle, storm, fire and meter damage can warrant a power release before inspection, requested by a licensed contractor registered with the city, who then obtains the permit and requests the inspection. The city says some services are too large or complicated for this allowance and that it rests with the inspector. TDLR reminded the public after the 2024 storms that electrical work must go through a TDLR-licensed contractor. A generator keeps the business open while that sequence runs.

Sources: the city's Emergency Electrical Release Policy, its storm damage page and TDLR's May 22, 2024 notice.

How is the price of a generator installation set?

At the free site visit. We walk the building, list the loads you want carried, check the service and the space for the generator and the transfer switch, and ask about the fuel. The price comes from those choices: the generator size, the switch, the conductors, the pad and the permit work, written out line by line.

The written scope also names what is not ours. Pads are often poured by a concrete contractor and gas lines run by a plumber, and the scope says which pieces sit with other trades. Your choices move the number: a separate standby panel with a few loads and a whole-building transfer are priced differently, and both are spelled out so you can see why.

We install Dallas commercial standby generators, and our property manager electrical checklist for Dallas covers testing a system once it is in. See also the Dallas commercial electrician hub and our commercial electrical services. The price is set at the free site visit.

FAQ

Common questions

Straight answers. If you do not see yours, call us and ask.

Where does the transfer switch go on an Oncor service in Dallas?

On the load side of the meter base. Oncor's Electric Service Guidelines say it is never built into the meter base or placed in series with the meter.

Does a commercial generator need a permit in Dallas?

Yes. Electrical work on commercial property in Dallas requires a registered electrical contractor and a permit, and the city's development guide lists generators among the projects its building code review covers.

What does commercial generator installation cost in Dallas?

The price is set at the free site visit, from the loads you choose, the transfer switch, the fuel supply and the permit work, and you get it in writing.

Ready to get it handled?

Flat-rate pricing quoted up front. Licensed and insured. A Wattsmith electrician calls you back within 15 minutes during business hours.

  • Licensed and Insured
  • BBB Accredited
  • Flat-Rate Pricing
  • Background-Checked
Call NowGet a Quote