Skip to content
Wattsmith Electric

Commercial

DFW Storm Standby Power for Businesses: What Oncor and the NWS Record

November 1, 2026Last updated 7 min readWattsmith Electric · TECL 41806

Key takeaways

  • Oncor reported more than 650,000 customer outages from the storm that crossed DFW in late May 2024.
  • A storm-damaged meter base must be fixed by an electrician before Oncor restores power, and a city inspection may come first.
  • North Texas storms run all year: ice in February 2021 and 2023, snow and sleet in January 2026, hail in April 2026, tornadoes in December 2015.
  • Most business generators are optional standby under NEC Article 702; Articles 700 and 701 cover life safety and legally required systems.
  • Oncor's guidelines put the transfer switch on the load side of the meter base, and the work goes in under a city electrical permit.

Standby power for a business in Dallas and Fort Worth is planned for weather that comes in every season. A spring storm in 2024 left hundreds of thousands of Oncor customers dark, Winter Storm Uri cut power across Texas in 2021, and ice, snow and hail have followed since. A business that keeps running through those days has a generator, a transfer switch and a short list of loads already wired to stay on. This guide covers what Oncor, ERCOT and the National Weather Service recorded, how a commercial standby system is built, and what Oncor and the city ask for first.

What did the May 2024 storm do to Oncor's system?

Oncor said a storm system that moved through DFW and into the eastern part of its service area caused significant damage and more than 650,000 customer outages. On May 29, 2024 it reported power back for more than 340,000 customers less than 24 hours after the storm, and more than 400,000 by 4 p.m. that day.

The damage went past downed wires. Oncor said that in heavily damaged areas, wide swaths of power lines and distribution equipment had to be rebuilt, with damaged poles and transformers replaced before new lines could go up. More than 7,500 personnel, mutual assistance crews from other utilities among them, worked 16 hour shifts around the clock. Even at that pace, a building at the end of a rebuilt line waits longer than most.

Source: Oncor's May 29, 2024 restoration update.

Why can a damaged meter base keep a business dark after the lines are back?

Because the meter base and the weatherhead belong to the customer, not to Oncor. In the same update Oncor said that where a storm damaged or pulled off a meter base or weatherhead, the customer must have an electrician fix it before Oncor can restore power, and that city inspections may also be required before the service is energized.

Cities have a path for this. The City of Dallas Emergency Release Policy lists storm damage among the emergencies that can warrant a power release before inspection, requested by a licensed contractor registered with the city, who then pulls the electrical permit and asks for the inspection. The policy says some services are too large or complicated for that allowance, at the inspector's discretion. In Fort Worth the city's word for the approval is also a release. A standby system wired on the load side of the meter can carry its loads while that work and inspection happen, so it covers this gap as well as the outage itself.

Source: the City of Dallas Emergency Electrical Release Policy and its storm damage page.

Which North Texas storms should a standby plan account for?

Cold and hail as much as wind. The National Weather Service office in Fort Worth records DFW Airport at or below freezing for 139 straight hours in February 2021, falling to minus 2 degrees on February 16. Its summaries also cover the 2023 ice storm, the January 2026 winter storm and the April 2026 hail outbreak.

  • January 30 to February 1, 2023: ice and sleet across North and Central Texas, with several reports of half an inch of ice, and DFW Airport at or below freezing for 88 hours.
  • January 23 to 26, 2026: sleet, snow and freezing rain, with 2.4 inches of snow recorded at DFW Airport on January 24 and 25.
  • April 27 and 28, 2026: supercells across the middle of the Metroplex with hail up to teacup size, then hail up to softball size and an EF3 tornado in northeast Mineral Wells. The NWS marks these reports preliminary.
  • December 26, 2015: 12 confirmed tornadoes, including an EF4 through Sunnyvale, Garland and Rowlett in Dallas County.

Sources: NWS Fort Worth summaries of February 2021, January and February 2023, January 2026, April 2026 and December 26, 2015.

What did ERCOT say happened during Winter Storm Uri?

ERCOT told Congress that at its worst, the February 2021 storm took out 48.6% of the generation available to the Texas grid. It said that without the controlled outages, power could have been out for 90% of Texans for weeks. The shortage was in the power plants, so no line crew could bring a building back early.

ERCOT's generator outage report puts the most unavailable capacity at 52,037 MW, about 8:00 AM on February 16, 2021. Its release of February 15 reported about 10,500 MW of customer load shed at the highest point to that time, enough to serve about two million homes. That figure is from early in the event, as of that release, not the final peak. A grid shortfall cuts power in rotation across the state, so a standby system matters as much in a freeze as after a windstorm.

Sources: ERCOT's statement to the U.S. House Energy and Commerce Committee, March 24, 2021, its generator outages by cause report, updated April 27, 2021, and its February 15, 2021 release.

What is a commercial standby system?

It is a permanently installed generator, an automatic transfer switch that moves chosen loads from the utility to the generator when power fails, and the wiring that keeps those loads apart from the rest of the building. When utility power returns, the switch transfers back and the generator cools down and stops.

The generator is sized from the loads the business chooses to keep, not from the size of the service. Refrigeration, servers and phones, security and alarm power, enough lighting to move safely, and a restroom usually come first. In a North Texas freeze the list also needs heat for the core of the building and anything that keeps pipes and sprinkler lines from freezing. The circuits on the list move to their own standby panel, or the transfer switch sits at the service with load shedding that drops what the generator cannot carry.

Which NEC article applies: 700, 701 or 702?

It depends on why the power is needed. Article 700 covers emergency systems required for life safety, such as egress lighting. Article 701 covers legally required standby, which a government agency requires. Article 702 covers optional standby, which the owner chooses to protect the business. Most business generators fall under Article 702.

The articles set different rules. An emergency system under Article 700 must restore power within 10 seconds and keeps its wiring separate from other circuits. Legally required standby under Article 701 has a 60 second limit. Optional standby under Article 702 leaves the owner the most room, as long as the generator can carry the load the transfer equipment connects. One building can hold both an Article 700 branch for egress lighting and a separate Article 702 system for the rest.

Where does Oncor want the transfer switch?

On the load side of the meter base. Oncor's Electric Service Guidelines say a customer generator transfer switch is to be installed on the load side of the meter base, and that under no circumstances may it be built into or placed in series with the meter and the base. The meter stays Oncor's, untouched.

The transfer switch is also what keeps a generator from sending power back onto the utility's lines while crews work on them. Oncor's guidelines say it will not connect a customer installation until the proper authority approves it, so the city inspection and release come before any change at the service. Most of Dallas and Fort Worth is served by Oncor; some edge areas are co-op territory, and there the co-op's own rules apply.

Source: Oncor's Electric Service Guidelines, February 2025.

Is a city permit required for commercial standby power?

Yes. A commercial generator, its transfer switch and the wiring are electrical work under a city electrical permit. In Fort Worth that permit is applied for through Accela Citizen Access, and the city enforces the 2026 NEC on work started from September 1, 2026. Dallas lists generators among the projects its Building Code review covers.

Where a job also needs a Fort Worth building permit, the city issues it before the trade permits. Wiring is inspected before it is covered, and the city releases the system after its final. We then test it under load, with the transfer switch moving the building to the generator, before the spring storm season and again before the first freeze. The price of a standby system is set at the free site visit.

We install these systems as Fort Worth commercial standby generators and Dallas commercial standby generators. The permit steps are in our guide to how commercial electrical permits work in Fort Worth. See also the Fort Worth commercial electrician hub and our commercial electrical services. Sources: the city's permits page and commercial permits page.

FAQ

Common questions

Straight answers. If you do not see yours, call us and ask.

How many Oncor customers lost power in the May 2024 storm?

Oncor reported more than 650,000 customer outages from the storm that moved through DFW, and power back for more than 400,000 customers by 4 p.m. on May 29, 2024.

Where does the transfer switch go on an Oncor service?

On the load side of the meter base. Oncor's Electric Service Guidelines say it is never built into or placed in series with the meter and the base.

What does a commercial standby system cost in Dallas or Fort Worth?

The price is set at the free site visit, from the loads you choose, the transfer switch and the fuel supply, and you get it in writing.

Ready to get it handled?

Flat-rate pricing quoted up front. Licensed and insured. A Wattsmith electrician calls you back within 15 minutes during business hours.

  • Licensed and Insured
  • BBB Accredited
  • Flat-Rate Pricing
  • Background-Checked
Call NowGet a Quote