Key takeaways
- The generator is sized from the loads you choose to keep running, measured and calculated, not from the size of the service.
- On an Oncor service the transfer switch goes on the load side of the meter base, never in series with the meter.
- Whether the job falls under NEC Article 700, 701 or 702 decides how the wiring is separated and how fast power must return.
- Fort Worth takes the electrical permit through Accela Citizen Access and inspects buried conduit, rough wiring and the final in numbered steps.
- The price is set at the free site visit, in writing, after the load list and the location are settled.
Commercial generator installation in Fort Worth is a construction job with a fixed order: decide what must stay on, size the generator to it, choose where the unit and the transfer switch go, get the city permit, build, pass the inspections, and test the system under load before the city releases it. Each step depends on the one before. This guide follows the installation itself, from the first walk through the building to the day the transfer switch moves the loads for the first time, with the Oncor and City of Fort Worth rules that apply along the way.
Why does a Fort Worth business plan a generator installation around the weather?
Because North Texas loses power in every season. The National Weather Service office in Fort Worth records DFW Airport at or below freezing for 139 straight hours in February 2021, and 88 hours in the ice and sleet of early 2023. The installation is finished before the next event, not ordered during one.
Spring brings a different risk. In late May 2024, Oncor reported more than 650,000 customer outages from a storm that moved through DFW. The NWS also records 2.4 inches of snow at DFW Airport in January 2026 and, in reports it marks preliminary, hail up to softball size in late April 2026. A generator that sits on a pad through all of that has to be planned for heat, ice and hail alike.
Sources: NWS Fort Worth summaries of February 2021, January and February 2023, January 2026 and April 2026, and Oncor's May 29, 2024 restoration update.
How is a commercial generator sized?
From the loads the business chooses to keep, measured where possible and calculated where not. We list each load, read its nameplate, record what it actually draws, and add the starting current of motors and compressors. The generator must carry the running total and survive the largest motor starting while everything else runs.
The load calculation follows NEC Article 220, the same method used to size a service, applied to the list. Two choices change the answer more than anything else. Whole building coverage puts the transfer switch at the service and sizes the unit for the building's demand. Selected loads move to a separate standby panel, and the generator is sized for that panel alone. Load shedding controls can sit between the two, dropping lower priority circuits when the generator nears its limit and adding them back when it has room.
Where does the transfer switch go on an Oncor service?
On the load side of the meter base. Oncor's Electric Service Guidelines say a customer generator transfer switch is installed on the load side of the meter base, and that under no circumstances is it built into or placed in series with the meter and the base. The meter and its base stay as Oncor expects them.
Inside that rule there are still choices. A service rated transfer switch can sit right after the meter and act as the building's main disconnect. A switch downstream of the main breaker feeds only the standby panel. The choice depends on the load list, the space on the wall and the length of the feeder run from the generator pad. Most Fort Worth addresses are served by Oncor; some edge areas are co-op territory, and there the co-op's own interconnection rules apply.
Sources: Oncor's Electric Service Guidelines, February 2025, and the PUC's FAQ on municipal utilities and co-ops.
Which NEC article governs the installation: 700, 701 or 702?
The reason for the power decides it. Article 700 covers emergency systems that protect life, such as egress lighting. Article 701 covers standby that a government agency requires. Article 702 covers optional standby the owner chooses to protect the business. Many installations hold more than one, and each is wired to its own article.
For the installer the difference shows up in the wiring. An emergency system keeps its wiring apart from every other circuit and needs its own transfer switch, so egress lighting never shares a raceway with the walk-in cooler. Required standby and emergency systems have time limits for power to return; optional standby does not, but the generator must be able to carry whatever load the transfer equipment connects to it. We confirm which article applies before the drawings are final, because it changes how many switches and panels the job needs.
What goes into choosing the generator location?
Clearances, exhaust, fuel, noise, access and the feeder run. The unit needs the working space and the distance from openings that its maker's instructions set, a pad that drains, room for a technician to service it, and a path for the conductors back to the transfer switch that is as short as the site allows.
Fuel shapes the location too. A natural gas unit needs a gas service with enough volume for the generator at full load; a diesel unit carries its own tank and needs a plan for refueling during a long outage. Gas line and gas connection are not included. That is a licensed plumber's work and we quote it separately. A buried feeder from the pad to the building is common, and that conduit is inspected in the open trench before backfill, so the pad and the trench are laid out together.
What does the Fort Worth permit and inspection process look like for a generator?
The electrical permit is applied for through Accela Citizen Access. Where the job also needs a building permit, Fort Worth issues it first, because the city says the building permit must be issued before a trade permit can be applied for. The city enforces the 2026 NEC on work started from September 1, 2026.
Fort Worth's commercial plans page asks electrical plans to show disconnect and panel locations and one-line diagrams, which on a generator job means the unit, the transfer switch and the standby panel all appear on the drawing. Buried feeder conduit is inspected as 205, Electrical Underground, after the trench is bedded and the conduit is in, before backfill. The panels and wiring are inspected as 210, Electrical Rough. The 200 Electrical Final checklist includes arc-flash warning labels on service equipment and grounding and bonding of service equipment. We install the labels; any arc flash study behind them is engineering work done by a qualified engineer.
Sources: the city's permits page, commercial permits page, commercial building plans page, What Inspections Do I Need? guide, 200 Electrical Final checklist and building and energy codes page.
How is a new generator tested before it is handed over?
By cutting utility power to the transfer switch and watching the system do its job. The generator starts, the switch transfers, the chosen loads run on generator power, and when utility power returns the switch moves back and the unit cools down and stops. Every step is checked and written down.
The test happens after the city's final, and power to new service equipment comes after the city's electrical release; Oncor's tariff says it will not connect until the proper authority approves the installation. We then walk the owner through the controls, the exercise schedule and what the status lights mean, and leave the test record with the building. A maintenance agreement keeps the exercise runs and checks on a calendar, so the first real outage is not the first time anyone has looked at the unit in a year.
Source: Oncor's Tariff for Retail Delivery Service, Section 5.4.2. What the storms of the last few years recorded, and why standby matters for a DFW business, is in our guide to DFW storm standby power for businesses.
How is the price of a commercial generator installation set?
At the free site visit. The price comes from the load list, the generator that list calls for, the transfer switch and panel arrangement, the length of the feeder run, the pad and the permit work. Once those are settled on site, you get the price in writing before any work starts.
We install these as Fort Worth commercial standby generators. If the same service will also feed chargers, see our guide to EV charging for Fort Worth businesses. For our other work in the city, see the Fort Worth commercial electrician hub, and for everything we do across Texas, our commercial electrical services.