Key takeaways
- The lease work letter decides who pays for the suite's service, panel, meter and distribution; read it before pricing anything.
- The first question is how much power the suite needs and whether the building's service has it to give.
- In Fort Worth the building permit is issued before the electrical permit can be applied for, and plans over 5,000 square feet are engineer sealed.
- Walls and ceilings are inspected separately (210, 255, 215), so the suite can close in stages.
- Power comes after the city's release; a new suite meter needs its ESI ID and a retail provider before Oncor sets it.
Tenant build-out electrical work in Fort Worth starts with a document most electricians never see first: the lease. The work letter attached to it says what the landlord delivers and what the tenant builds, and the electrical scope splits along that line. A suite might come with a panel and a meter or with a capped conduit in a gray shell. This guide looks at the build-out from the tenant's and the landlord's side: who usually carries which part, how the suite's power is sized, and how the City of Fort Worth's permit order and inspections line up with the move-in date.
What electrical work does the landlord usually provide in a build-out?
Whatever the lease work letter names, and nothing more. A typical shell delivery brings power to the suite: a meter position, a feeder or a conduit stubbed in, and sometimes a tenant panel. Common areas, the building service and the house panels stay the landlord's. Any line the letter leaves out falls to the tenant.
Landlords also set rules that reach the tenant's electrician: approved contractors, insurance certificates naming the landlord, hours for loud work, and how roof and electrical room access is handled. A second generation suite brings its own question: what was left behind. Old panels, abandoned circuits and fixtures from the last tenant may need to come out or be proven safe before new work starts, and the work letter should say whose cost that is.
What does the tenant's electrical scope usually include?
Everything inside the suite past the landlord's delivery point. That is usually the suite panel or its feeder, branch circuits for receptacles and equipment, lighting and its controls, exit and emergency lighting, data and low voltage pathways, and the dedicated circuits a tenant's equipment calls for. Signage power and rooftop equipment often land here too.
The tenant's own equipment list drives the scope more than the floor plan does. A dental office, a restaurant and a call center can share a suite size and need very different power. Kitchen equipment, imaging, server racks and specialty HVAC each have nameplate loads and circuit requirements, so the tenant's equipment schedule belongs in the electrical bid from the start. Exit and emergency lighting follows NEC Article 700, and its wiring is kept apart from the general circuits.
How is the suite's power sized?
With a load calculation for the tenant's actual use, compared with what the building can deliver to the suite. The calculation follows NEC Article 220: lighting, receptacles, equipment and HVAC, with demand factors where the code allows. If the suite needs more than the landlord's delivery, the gap is settled before the lease is signed.
Closing that gap can mean a larger feeder from the building's switchboard, a spare section of the switchboard put to use, or more capacity from the utility. On an Oncor service, Oncor's Commercial and Industrial Load Requirements form has a box for adding load to an electrically energized service, and a request that needs Oncor construction starts online. Utility work can take months, so a tenant whose suite needs it should know before the lease fixes a move-in date. Most Fort Worth addresses are on Oncor; some edge areas are co-op territory.
Sources: Oncor's Commercial and Industrial Load Requirements form, its new construction page, and the PUC's FAQ on municipal utilities and co-ops.
Does a Fort Worth tenant suite get its own Oncor meter?
Often, when the suite is billed separately. A new meter on an Oncor service follows Oncor's steps: when the location is ready, Oncor provides an ESI ID, the tenant chooses a retail provider, and the meter is installed on the start date chosen with that provider. The tenant's retailer then bills the suite's delivery and energy.
Some buildings submeter suites from a master service instead, and the landlord bills the tenant under the lease. Which arrangement applies is a lease question with an electrical answer: a separately metered suite needs a meter position and a tenant panel fed from it, while a submetered suite needs the landlord's submeter. The PUC notes that it regulates delivery utility rates, not the retail provider's price, which the tenant chooses.
Sources: Oncor's new construction page and the PUC's guide to understanding your bill.
In what order does Fort Worth permit a tenant build-out?
Building permit first, then the electrical permit. Fort Worth takes applications through Accela Citizen Access and says the building permit must be issued before a trade permit can be applied for. The electrical drawings are reviewed with the building set, so the electrical scope has to be settled before submittal.
For the tenant and landlord, that means the electrical design sits on the lease schedule's critical path. The city's stated standard for first review comments on a complete commercial application is 7 business days, and a set with questions goes another round. For buildings over 5,000 square feet, the city says state law requires the electrical plans to be sealed by a Texas Professional Engineer. The contractor who pulls the electrical permit must be registered with the city before the permit is issued. We register with the city before a permit is bought, as the city requires.
Sources: the city's commercial permits page, commercial building plans page, review timeframes page, contractor registration page and the 2025 Commercial Development Guide, page 34. Each permit step in detail is in our guide to how commercial electrical permits work in Fort Worth.
How do the inspections fit the suite's construction schedule?
They set when walls and ceilings may close. Fort Worth inspects rough-in in three parts: 210 for panels and wiring in walls and ceilings, 255 for metal conduit and box grounding, and 215 for wiring and fixtures above the ceiling. Each is called before the membranes that would hide that work go up.
In a suite that lets the drywall crew start on inspected walls while the ceiling grid stays open. The general contractor's schedule should show each inspection as a step with its own date, because a failed one holds the trade behind it. At the end, the 200 Electrical Final checks that installed fixtures match the COMcheck list and that arc-flash warning labels are on the service equipment. We install the labels; any arc flash study behind them is engineering work done by a qualified engineer.
Sources: the city's What Inspections Do I Need? guide and 200 Electrical Final checklist. The full numbered sequence is in our guide to the Fort Worth electrical inspections sequence.
When can the tenant turn the power on and move in?
After the city's electrical release, and for a new meter, after Oncor sets it. Fort Worth's electrical final is the inspection for permanent power, and Oncor's tariff says it will not connect until the proper authority approves the installation. A temporary release can come earlier for testing and finishing, but it is not occupancy.
The certificate of occupancy is a separate building approval, and the tenant's opening date depends on it as much as on the power. A realistic schedule leaves room between the electrical final and opening day for the meter set, equipment start up and any punch list. Fort Worth enforces the 2026 NEC on work started from September 1, 2026, so a suite started now is built and inspected to that edition. The price of the electrical scope is set after the free written estimate.
We do this work as Fort Worth tenant build-outs. Before choosing anyone for the scope, our guide to vetting a Fort Worth electrical company lists checks you can run yourself. See also the Fort Worth commercial electrician hub and our commercial electrical services. Sources: Oncor's Tariff for Retail Delivery Service, Section 5.4.2, and the city's building and energy codes page.