Key takeaways
- Fort Worth inspects underground conduit (205) and in-slab grounding (240) before anything is covered.
- Rough-in is three inspections: 210 for panels and wiring, 255 for wall conduit and box grounding, 215 for everything above the ceiling.
- A temporary release (250/285) can come before the final; the electrical final (200/285) is for permanent power.
- The 200 final checklist includes arc-flash warning labels, grounding and bonding, and a field test letter on large 480-volt services.
- Requests made before 6:30 a.m. are scheduled that day; later requests go to the next business day.
A Fort Worth electrical inspection is called at each point where work is about to be hidden, and the city gives each one a number. The underground and slab work is seen before backfill and concrete, the rough wiring before walls and ceilings close, and the finished system before the city releases power. Knowing the numbers lets a builder schedule trades around them instead of waiting on them. This guide walks through the sequence in the order the City of Fort Worth's own inspection guide lists it, with the checks that apply at each stop.
What are the Fort Worth electrical inspections, in order?
The city's guide lists them by number. Underground work comes first with 205 and 240, then rough-in with 210, 255 and 215 before wall and ceiling membranes go up. A temporary release, 250/285, may come before finals, and the electrical final, 200/285, is the inspection for permanent power.
- 205, Electrical Underground: conduit or duct banks, before backfill.
- 240, Electrical Slab: in-slab grounding, before the pour.
- 210, Electrical Rough: panels and wiring in wall and ceiling areas.
- 255, Electrical Wall: metal conduit and box grounding.
- 215, Electrical Ceiling: wiring and fixtures above the ceiling.
- 250/285, temporary release: the system checked for temporary power before the final.
- 200/285, electrical final: the system checked for permanent power.
The numbers go on the inspection request, so the request names exactly what the inspector is coming to see. A job can call the same number more than once over its life, one for each area that is ready to close. A build-out with no new conduit below the floor has no underground or slab work to show, and its sequence starts at rough-in.
Source: the city's What Inspections Do I Need? guide, linked from the Fort Worth inspections page.
When does the 205 underground inspection happen?
After the trenches or ditches are dug and bedded and the conduit is in, and before any backfill goes in. The city's guide sets that timing for the underground electrical inspection. The 240 slab inspection covers in-slab grounding, so it is called before the concrete covers the grounding conductors.
Oncor has an inspection of its own at the same stage on commercial jobs. Its Electric Service Guidelines say the service lateral conduit must meet the 24 inch NEC burial depth to the top of the conduit, and that for commercial and industrial installations an inspection before cover-up is mandatory. That is the utility's check on the raceway it will pull its conductors through, separate from the city's 205. Both belong on the schedule before the backhoe comes back.
Source: Oncor's Electric Service Guidelines, February 2025.
What do the 210, 255 and 215 rough inspections cover?
Rough-in is checked after the roof, framing, fire blocking, fire stopping, draft stopping and bracing are in place and the wiring to be concealed is complete, before wall or ceiling membranes. Inspection 210 covers panels and wiring in walls and ceilings, 255 covers metal conduit and box grounding, and 215 covers wiring and fixtures above the ceiling.
Splitting rough-in into three numbers helps on commercial work, where walls and ceilings rarely close on the same day. The walls in a tenant suite can be inspected and boarded while the ceiling grid is still open above them. The 215 ceiling inspection then catches the fixtures, the whips and the wiring that rides above the grid, before the tiles go in. We call each one as its area is ready, so drywall and ceiling crews are not held for the whole floor.
What is the 250/285 temporary release?
It is an inspection of the electrical system before the final, for temporary power to the building. The city says electrical temporary releases may be requested before finals. Fort Worth's Electrical Permit Application carries an Electrical Release box, marked yes or no, so the release is planned on the permit from the start.
The same form says a Temporary Power Letter is by separate permit only. The city's Temporary Power Letter for Clean and Show must be approved by an electrical inspector, and it warns that signing it does not authorize occupancy of the structure. Temporary power lets the trades test equipment and finish work. It is not a certificate of occupancy, and nobody should move in on it.
Sources: the city's Electrical Permit Application and its Temporary Power Letter for Clean and Show.
What does the 200 electrical final check?
The final checks every part of the system installed after the rough was approved, for permanent power. The city's checklist starts with approved plans and the permit card on site, then covers arc-flash warning labels on service equipment, grounding and bonding of service equipment, and fixtures that match the COMcheck list.
The checklist also says that on 480 volt services with a main breaker of 1000 amps or more, the city verifies "GFCI protection" is in place and field tested as the NEC requires, with a copy of the test letter given to the inspector. In NEC terms that is ground-fault protection of equipment on the service, set out in Article 230. The arc-flash labels come from Section 110.16 of the NEC. We install the labels the code calls for; any arc flash study behind them is engineering work done by a qualified engineer.
Source: the city's 200 Electrical Final checklist.
Where does the temporary pole fit in the sequence?
It comes first, before most of the numbered inspections. Fort Worth's Electrical Permit Application lists the temporary pole as a permit item. Oncor's guidelines say the customer provides and installs the pole, and that a retail electric provider must be chosen before the temporary meter is installed and energized.
Oncor's pole specification is short: at least 4 by 4 inches by 16 feet unspliced, or a treated pole with a 5 inch minimum diameter at the top, tall enough for the service drop to meet its clearance. The pole is marked with the address in numbers at least 3 inches high, and Oncor owns and installs the service drop.
The pole goes up where the service drop can reach it and the trades can reach the pole, and it stays until the permanent service is released and energized. On commercial jobs the same idea scales up: Oncor's checklist asks for a marked site plan showing where the temporary point of delivery will be, so the pole location is settled with Oncor before it is set.
The builder's side of the temporary pole, with Oncor's ESI ID steps, is in our guide to Oncor temporary power for DFW home builders.
How do you request an inspection in Fort Worth?
Through Accela Citizen Access or the city's inspection request phone line. Requests received before 6:30 a.m. are scheduled for that day, and requests at or after 6:30 a.m. go to the next business day. The city asks that the inspection contact be filled out in the online profile for every scheduled inspection.
Oncor does not stand in for the city at any of these steps. Its guidelines say it does not assume any duty of inspecting the customer's lines, switches or equipment, and it will not connect until it is notified that the proper authority approved the installation. The city's inspections are the ones that lead to power, so a failed one moves the meter date with it. Fort Worth enforces the 2026 NEC on work started from September 1, 2026, and each inspection is judged to that edition.
How the permit itself is applied for is in our guide to how commercial electrical permits work in Fort Worth. We schedule these inspections on Fort Worth tenant build-outs; see also the Fort Worth commercial electrician hub and our commercial electrical services. Source for the 2026 NEC date: the city's building and energy codes page.