Key takeaways
- The electrical scope of a tenant build-out covers power, lighting, panels, feeders and any service change, drawn before plans go up.
- Plans go to the city through ProjectDox, and trade permits are bought only after the building permit has been sold.
- Walls and ceilings wait on cover inspections; the city aims to inspect within three working days of a request.
- After the final and the city's utility release, CenterPoint says meters are usually set within 3 to 5 business days of the requested start date.
A tenant build-out turns a shell or a former tenant's space into a space that fits the new lease, and the electrical scope is often the part that sets the schedule. In Houston the steps run in an order the city and CenterPoint Energy set, and most of the dates on a build-out depend on that order rather than on how fast any trade works. This guide lists what the electrical scope covers and walks through each Houston step in sequence, with the official pages behind them, so a tenant, landlord or general contractor can see what waits on what.
What is in the electrical scope of a tenant build-out?
The electrical scope covers everything that feeds and serves the new layout: lighting and its controls, receptacles and dedicated circuits, panels and feeders, equipment connections for mechanical and kitchen gear, and any change to the service or meter. It also covers demolition of the old wiring that no longer fits the plan.
- Demolition and make-safe of circuits the new layout removes.
- Lighting layout, fixtures, controls and exit and emergency lighting.
- Receptacles, dedicated circuits and data or low voltage pathways where the contract includes them.
- Panels, feeders and panel schedules for every new or changed panel.
- Connections for HVAC, water heaters, kitchen equipment and signs.
- Any service or meter change that needs CenterPoint.
For the room by room items to verify before walls close, see the Houston tenant build-out electrical checklist.
Which drawings does the electrical scope need before plan review?
Houston's code asks for plans, calculations and diagrams with each permit application, and the building official may require them to be prepared by a master electrician of record or sealed by a Texas professional engineer. For a build-out that usually means lighting and power plans, panel schedules and load calculations for the space.
The same section of the code lets the building official waive plan submission when review is not needed for the work, but a commercial build-out should be drawn as if review will happen. The load calculation is worth doing early either way, because it answers whether the existing service can carry the new layout or whether CenterPoint will need to be involved.
The tenant's equipment list belongs with the drawings from the start. Kitchen lines, medical or lab equipment, server racks and signs each need their own circuits, and their nameplate data drives the panel schedules and the load calculation. An equipment list that arrives after plan review usually means revised drawings and a second round of comments.
Where do the plans go, and what comes back?
Commercial plans are uploaded through ProjectDox, and permits are applied for and bought in iPermits. The Houston Permitting Center assigns discipline reviews from the project's scope of work, and Electrical is one of those disciplines, so a build-out with electrical work gets an electrical review alongside the building review.
Comments from any discipline come back to the applicant to answer, and the electrical comments come to the electrical contractor through the general contractor or the designer. Answering them quickly is the one part of plan review the project team controls, so name the person responsible for electrical responses before the plans go up.
The city lays out the process in its Commercial Permitting 101 presentation, and the plan rules are in Section 302.2 of the City of Houston Electrical Code.
Why does the building permit come before the electrical permit?
The Houston Permitting Center says licensed contractors can purchase trade permits after the building permit has been sold. On a tenant build-out the general contractor's building permit is the gate, and the electrical permit follows it, bought by a TDLR-licensed master electrician registered with the city.
Temporary power follows the same gate. The city says temporary utilities may be obtained after all permits are purchased, including a Temporary Cut In permit. So a build-out that needs construction power cannot get it ahead of the permits, and the schedule should show the building permit, then the trade permits, then any temporary power, in that order.
When do the cover inspections happen?
Cover inspections happen before anything hides the wiring. The city lists ditch or slab cover, wall cover and ceiling cover inspections, and its code says no wiring meant to be concealed may be concealed until inspected and approved. Drywall and ceiling grid each wait on the inspection for their area.
- Ditch or slab cover: underground conduit, before backfill or a pour.
- Rough-in, then wall cover: wiring in the walls, before drywall.
- Ceiling cover: wiring above the ceiling, before grid tiles or hard lid.
- Temporary cut-in, when temporary power is needed to check wiring.
On a build-out this is where trades overlap most. The electrical rough-in finishes in one area while another area is still being framed, and the drywall crew wants to start where the inspection has not happened yet. Splitting the space into areas, and calling each cover inspection as its area is ready, keeps the walls moving.
The inspection list is on the city's Electrical Inspections page.
How long does the city take to inspect?
Section 305.2 of the Houston code says Electrical Inspections shall endeavor to inspect work within three working days following receipt of an inspection request. That is the city's stated aim, not a guarantee, so a sound build-out schedule books each inspection as soon as its stage is ready.
The licensed electrical contractor schedules every inspection, online or through the city's IVR line, and both the master and contractor registrations must be in good standing to do it. Those are the only inspection timing facts the city publishes, so we do not put a date on an inspection beyond the request and the city's aim.
What happens between the final and the CenterPoint meter?
When the work is complete, a final inspection is made, and nothing may be connected until the building official approves it. Electrical Inspections then performs the utility release. CenterPoint connects once approval or a permit number reaches its Permit Desk, and says meters are usually set within 3 to 5 business days of the requested start date.
If the space needs a new meter or new utility equipment, the CenterPoint request should go in well before the final. Projects that need CenterPoint construction go through its online Electric Service Request, and CenterPoint says a local service consultant reaches out within two business days. CenterPoint's meter window also carries its own words: weather and workload permitting.
CenterPoint's steps are on its service connect page. Since September 1, 2026, permit applications are reviewed to the 2026 National Electrical Code.
How should a tenant build-out schedule be built?
Build it backward from the date the tenant needs power, using the fixed order: CenterPoint meter, utility release, final, ceiling cover, wall cover, rough-in, trade permit, building permit, plan review. Each step waits on the one before it, so the earliest real date is set by that chain, not by crew size.
Two items deserve their own lines on the schedule because they sit outside the building: the CenterPoint request and any long lead electrical gear such as a new panel or transformer. Starting both while plans are still in review keeps them from becoming the last thing the opening date waits on.