Key takeaways
- NWS Austin/San Antonio records that San Antonio International Airport stayed below freezing for 4 days 12 hours during Uri, one hour short of the 1951 record.
- CPS Energy reported a peak of 45,000 customers out in the February 2023 ice storm, and more than 250,000 customers initially lost power in the late August 2026 storm.
- CPS Energy's Service Standards bar a customer generator from running in parallel with its lines unless Distribution Planning approves, and require an interlocked transfer scheme.
- CPS Energy's DG Manual calls for break before make transfer on non-paralleling generators and limits closed transition to one second of parallel operation.
- Most business generators are optional standby under NEC Article 702, and the price of a system is set at the free site visit.
Standby power for a San Antonio business has been tested hard in the last five years. Winter Storm Uri cut power across Texas in February 2021 because supply ran short. An ice storm brought lines down in February 2023. A severe storm at the end of August 2026 initially left more than 250,000 CPS Energy customers without power. A building with its own generator and transfer switch kept its chosen circuits running through each one. This guide sets out what the National Weather Service, CPS Energy, the City and ERCOT recorded, which code articles govern a commercial system, and what CPS Energy asks before a generator is wired into a building it serves.
What did the National Weather Service record about Winter Storm Uri?
The National Weather Service office for Austin and San Antonio calls February 10 to 18, 2021 an unprecedented and historical eight-day period of winter weather across South-Central Texas. San Antonio International Airport stayed below freezing for 4 days 12 hours, one hour short of the record set in late January and early February 1951.
Snow came in the second round, with 2 to 3 inches recorded in San Antonio. The weather service summary names the impacts across the state plainly: failed power grids, burst water pipes, and limited road and air travel. For a business, the length of the freeze mattered as much as the cold. Four and a half days below freezing is long enough for pipes, coolers and stock to fail inside a building with no heat and no power, even where the wires outside were never touched.
Source: NWS Austin/San Antonio, February 2021 weather event summary.
How did Winter Storm Uri reach CPS Energy customers?
Through rotating outages ordered when generation failed. CPS Energy's report to its board says ERCOT initiated load shed of up to 20,000 megawatts across the state to avoid a total grid collapse, and that the loss of power, and then water, to large portions of the area created numerous hardships across the community.
CPS Energy's question and answer sheet of February 19, 2021 said power had been restored to almost all of its customers, and that about 500 customers were experiencing equipment-related issues and remained without power. The same sheet explains that rotating outages were necessary to avoid a catastrophic event involving the entire grid. After the storm, CPS Energy told its board it enhanced its automated rotating outage program, raised its load shed limit to its share of 20,000 MW, and expanded the number of interruptible circuits.
The City's Community Emergency Preparedness Committee reviewed the storm in a report dated June 24, 2021. Citing an ERCOT report, the committee found that CPS Energy provided 6.79% of the total load shed ordered by ERCOT, about 1,358 MW, at the peak late on February 15, 2021. Those are the committee's findings, in a report that is also critical of how CPS Energy managed outages across its interruptible circuits.
ERCOT's own documents describe the supply side. Its March 24, 2021 statement to a U.S. House committee says that at its worst the storm took out 48.6% of the generation available to ERCOT. Its generator outage report puts unavailable capacity at its highest, 52,037 MW, at about 8:00 AM on February 16, 2021. No feeder in San Antonio had to fail for a business to go dark.
Sources: CPS Energy's Winter Weather Prep Report and February 2021 outage questions, the City's Community Emergency Preparedness Committee report, ERCOT's March 2021 statement to Congress and its generator outages by cause report.
Which storms since Uri have cut power in San Antonio?
Two stand out in CPS Energy's own reports. An ice storm entered its service area early on February 1, 2023, and a severe storm moved through the San Antonio area over a weekend at the end of August 2026. Both brought lines down, unlike Uri, so restoration depended on crews rather than on grid supply.
For the 2023 ice storm, CPS Energy reported that as of 8:30 a.m. on February 1 more than 111 outages were affecting about 26,000 of its customers. Its update the next day said that at the peak of the storm 45,000 customers experienced an outage, and that the storm caused nearly 200 downed lines.
The August 2026 storm was larger. CPS Energy's September 3, 2026 release says more than 250,000 customers initially lost power, with winds of up to 65 miles per hour and around 2,481 lightning strikes. The utility logged more than 1,000 downed-wire calls and over 60 pole replacements, and reported that it had restored all storm-related outages as of September 1. A standby plan here covers summer wind as well as February ice.
Sources: CPS Energy's February 1, 2023 ice storm release, its February 2, 2023 update and its September 2026 storm restoration release.
What is a commercial standby system?
It is a generator, a transfer switch and the wiring that moves chosen loads onto the generator when CPS Energy's supply fails. The switch senses the outage, starts the generator and shifts the loads, then returns them to the utility once power is back and holding steady. Nothing else in the building has to change.
Sizing starts with a list, not with the service rating. We walk the building with the owner and write down what has to keep running: walk-in coolers, servers and phones, alarm and access control panels, egress lighting, and in a freeze the heat that protects water lines and sprinkler risers. Each load's running and starting draw goes into the study, and the generator is chosen to carry the total with room for motor starts. Those circuits either move to a dedicated standby panel or stay where they are, with the switch at the service and load controls that drop whatever the generator cannot carry. Fuel is settled in the same study, either the building's natural gas service or stored fuel sized to the outage the owner plans for.
Which NEC articles govern standby power?
Three articles, chosen by the reason the power is needed. Article 700 covers emergency systems that protect life, such as egress lighting. Article 701 covers legally required standby, where a government rule demands backup. Article 702 covers optional standby, which the owner chooses to protect the business. Most business generators fall under Article 702.
The duties differ by article. An emergency system under 700 must restore power within 10 seconds and keep its wiring apart from ordinary circuits. A legally required system under 701 has up to 60 seconds. An optional system under 702 leaves the choice of loads to the owner, provided the generator can carry what its transfer equipment can connect. San Antonio adopts the National Electrical Code with its own local amendments, and Texas adopted the 2026 NEC as the state electrical code effective September 1, 2026. One of the City's amendments, on closed transition transfer, is covered below.
State code source: TDLR's 2026 NEC adoption notice.
What does CPS Energy require of a customer generator?
That it never runs in parallel with CPS Energy's lines unless Distribution Planning specifically approves it. CPS Energy's Electric Service Standards also require the customer to submit the transfer scheme, control schematics and operating logic for review, and the scheme must be interlocked so utility and emergency power never parallel during normal, test or maintenance conditions.
The same standards bar customer equipment, generators included, from being connected to CPS Energy meters or inside meter sockets and metering enclosures, except where CPS Energy has contracted for and approved it. The generator ties into the building's own distribution through its transfer switch, never through the meter.
CPS Energy's Distributed Generation Manual, its May 1, 2024 ninth edition, adds the switching rule. For a generator that does not parallel the grid, the transfer scheme must operate as break before make, both when load moves to emergency power and when it returns to normal. Drawings for whole-building backup go to the DG Team through CPS Energy's DG Review Portal, and they must be signed and sealed by a licensed engineer when the system is over 600 amps at 150 volts to ground or less, or 400 amps at 150 volts to ground or greater.
Sources: CPS Energy's Electric Service Standards (Articles 306.1 and 1809.4) and its Distributed Generation Manual.
Can a standby system use closed transition transfer in San Antonio?
Only within a one-second limit and with CPS Energy's approval. The DG Manual says a closed transition scheme may parallel with CPS Energy's distribution system for no more than one second while load moves from emergency power back to normal. The City's code carries the same one-second rule in its amendment to NEC 701.4(D)(2).
Closed transition matters to loads that cannot take even a blink on the return to utility power, such as some process controls and data equipment. The City's amendment adds that such systems must be approved by CPS Energy's Distributed Generation section. Most business standby systems are built open transition instead: the switch breaks from one source before it makes to the other, so the two never run together. Where an owner wants closed transition, the design goes to CPS Energy for review before the switch is ordered.
Source: the City's Chapter 10 building-related codes, Article VI amendments.
How is a standby system permitted and priced in San Antonio?
The City's Development Services Department permits the electrical work through the BuildSA portal, and its inspectors see the wiring before it is covered and again at final. Wattsmith registers with the City before a permit is bought, as the City requires. The price of the system is set at the free site visit.
At the visit we walk the building with the owner, list the loads to keep, look at the service and where a generator and switch can sit, and confirm the fuel on hand. The written estimate then names the generator size, the transfer equipment, the wiring and the permit work. Wattsmith Electric is a veteran-owned contractor working under Texas electrical contractor license TECL 41806. Once a system is in, it should run under load, with the switch carrying the building, before each summer storm season and again before the first freeze.
We install systems like these as commercial standby generators. A new building that needs power before its finals is covered in temporary power in San Antonio, and the step that turns on a new service in the Release to CPS. For the rest of our work see commercial electrical services. Permit source: the City's Commercial Project Application Guide.