Temporary Power in San Antonio: the TML and TOPS Permits

November 1, 2026Last updated 6 min readWattsmith Electric · TECL 41806

Key takeaways

  • A TML (temporary meter loop) permit lets the contractor install a panel and get a temporary meter for construction power.
  • CPS Energy energizes a temporary service only after the City has released the permits, and never on a meter loop attached to a portable building.
  • A TOPS (temporary on permanent set) energizes the permanent service before the certificate of occupancy, under the conditions in Section 10-53 of the City's code.
  • On a commercial combination permit, the TOPS inspections sit on the building permit; the electrical contractor must not pull a separate TOPS permit.
  • A TOPS release never allows anyone to occupy the building.

Temporary power on a San Antonio commercial job comes in two forms, and the City treats each one differently. A TML, or temporary meter loop, is the construction pole that feeds tools and trailers while the building goes up. A TOPS, or temporary on permanent set, energizes the building's permanent service before every final inspection has passed, so equipment can be started and tested. Both depend on CPS Energy, which energizes nothing until the City has released the permits. This guide covers what each one allows, how CPS Energy wants the pole built, and the limits the City puts on a TOPS.

What is a TML in San Antonio?

A TML is the City's temporary meter loop permit for construction power. The Development Services Department says it allows the contractor to install an electrical panel and get a temporary meter to be used for construction power. The electrical contractor should make sure the TML and TOPS permits are linked to the main building permit.

In practice the TML is a pole with a meter base, a disconnect and a small panel of breakers and receptacles, set where the site plan allows and where CPS Energy can reach it with an overhead drop or an underground feed. It serves the trades through the build and comes down once permanent power is on. The City's commercial inspection checklist lists a TML inspection as optional in Stage 2, beside the concrete encased electrode and slab rough-in inspections, so a job calls it only when a construction meter is actually wanted.

Sources: the City's utility release page and its commercial inspection checklist.

How does CPS Energy want a temporary meter pole built?

CPS Energy supplies construction power only where the customer installs an approved structure with a meter loop. Its Electric Service Standards require a stand-alone temporary meter structure, and Article 1602 sets the build: a wooden mast of at least 4 inches by 4 inches, set at least 2 feet in the ground and supported by three braces and stakes.

The standards add two limits that catch sites out. CPS Energy will not supply service to any meter loop located on or attached to a portable structure or building, so the meter cannot ride on a jobsite trailer. Where a three-phase temporary service is requested, the customer installs a meter pole that meets the standards' Section 1400 for overhead services. Heavy equipment on a commercial site, such as a tower crane or a hoist, often needs that three-phase feed, so the choice is made before the pole is ordered.

Source: CPS Energy's Electric Service Standards, Section 1600.

When will CPS Energy energize temporary service?

Only after the City has released the permits. CPS Energy's Service Standards say that before it energizes a temporary service, the customer must satisfy the permitting requirements of the authority having jurisdiction, and that authority must release those permits. In San Antonio that authority is the City's Development Services Department, working through BuildSA.

For a commercial TML, the City's release follows the inspection on its own. Its CPS release checklist, revision 10/25, lists the commercial TML as a systematic release: when the Electrical TML inspection is closed with a status of Pass or Conditionally Approved, the release goes out without a staff step. On CPS Energy's side, the project is registered on its Construction and Renovation Web Portal, where a contractor can request temporary service and track the project through to permanent service. CPS Energy says it typically processes a registration within 24 to 48 hours, and an owner authorizes a contractor to register with its Web Authorization Form.

Sources: the City's CPS Release Requirements for commercial work and CPS Energy's New Commercial Construction step by step document.

What is a TOPS permit?

TOPS stands for temporary on permanent set. The City's code defines it as an electrical permit that allows use of an existing or new distribution or service before a certificate of occupancy is obtained, and adds that connection to a service also requires CPS Energy's approval. It is how a building gets real power before its finals.

The City's utility release page puts it simply: if a structure needs temporary electrical service before final approval on all inspections, the team applies for a TOPS. That lets the mechanical contractor start rooftop units and the electrical crew check the permanent gear under load while finish work continues. Information Bulletin 104a, revised February 8, 2023, sets out the requirements for a TOPS release to CPS on new construction.

What must be finished before a TOPS on a commercial building?

Section 10-53 of the City's code sets the conditions. The electrical service must be complete with all grounding. The building permit needs a complete foundation inspection and at least a partial frame inspection. Every trade permit needs at least a partial rough-in, including a partial plumbing top out, and the sewer permit needs an approved final.

Those conditions make a TOPS a late step in the build, not a shortcut around inspections. The service equipment has to be set, terminated and bonded, with its grounding electrode system complete. On our jobs we plan the TOPS date backward from that list: the service gear and grounding are scheduled to finish ahead of it, and the rough-in inspections are called early enough that partial approvals are in place across the trades when the request goes in.

Source: the City's Chapter 10 building-related codes, Section 10-53.

Does a commercial combination permit need a separate TOPS permit?

No. Information Bulletin 104a says TOPS inspections are part of the combination building permit for a commercial building with a new meter for a new building, or an upgrade to an existing building under a remodel permit. Once TOPS is paid on that permit, only the electrical Licensed Professional may schedule the TOPS inspections.

The bulletin is blunt about the mistake to avoid: the electrical contractor must not pull a separate TOPS permit online. Doing so means paying for TOPS twice and two sets of inspections, and it hinders and delays the approval to CPS Energy for the release. The City's commercial guide explains the structure behind this. On a combination permit, the trade inspections are issued on the building permit, and trade contractors are added to it as Licensed Professionals so they can view the project and schedule the inspections for their work.

A standalone TOPS permit does exist for cases outside that structure. The bulletin's example is a second meter for a fire pump serving the sprinkler system of a new building, released so fire contractors and fire inspectors can test it. That application is made online by the Texas licensed master electrician registered with the City and linked to the main building permit.

Sources: Information Bulletin 104a and the City's Commercial Project Application Guide.

Can a business occupy a building on TOPS power?

No. Information Bulletin 104a says a TOPS release to CPS must never be used to let business owners occupy a building, and the City's code says the TOPS permit and the utility connection do not allow the owner or occupants to occupy it until a certificate of occupancy is issued. Power on is not permission to open.

A TOPS is for start-up, testing and finish work. Stocking shelves, moving staff in or opening to customers waits for the final inspections and the certificate of occupancy. The code also limits permits for temporary structures, equipment or systems to no more than 180 days, with extensions the Building Official may grant for demonstrated cause. Once the finals pass, the permanent release follows the path described in our post on the Release to CPS.

How does Wattsmith plan temporary power on a commercial job?

We settle it when the site plan is fixed. The pole location, single-phase or three-phase service, and the date the permanent service should go live on TOPS all go into the schedule. Wattsmith registers with the City before a permit is bought, as the City requires, and is added to the building permit as the electrical Licensed Professional.

Our written estimate lists the temporary pole and its inspection, the permanent service work and the TOPS inspections as separate lines, so the general contractor can see when each is due. Wattsmith Electric is a veteran-owned contractor working under Texas electrical contractor license TECL 41806, and tenant build-outs and new commercial buildings are the core of what we wire here. The price is set after the free written estimate.

We handle this as part of commercial tenant build-outs. The permanent release is laid out in the Release to CPS for commercial buildings, and backup power for the finished building in standby power for San Antonio business. For all of our work see commercial electrical services.

FAQ

Common questions

Straight answers. If you do not see yours, call us and ask.

What is the difference between a TML and a TOPS in San Antonio?

A TML is a temporary meter loop, a construction pole with a temporary meter. A TOPS energizes the building's permanent service before the certificate of occupancy, once the conditions in Section 10-53 of the City's code are met.

Should the electrician pull a separate TOPS permit on a commercial building?

Not on a combination permit. Information Bulletin 104a says the TOPS inspections are part of the building permit, and a separate TOPS permit means paying twice, two sets of inspections and a delayed release to CPS Energy.

Can a temporary meter go on a construction trailer?

No. CPS Energy's Service Standards say it will not supply service to any meter loop located on or attached to a portable structure or building. The meter goes on a stand-alone temporary pole.

Related help

Where to go from here

Ready to get it handled?

Flat-rate pricing quoted up front. Licensed and insured. A Wattsmith electrician calls you back within 15 minutes during business hours.

  • Licensed and Insured
  • BBB Accredited
  • Flat-Rate Pricing
  • Background-Checked
Call NowGet a Quote