Key takeaways
- ERCOT told Congress that at its worst, Winter Storm Uri took out 48.6% of the generation available to the Texas grid in February 2021.
- A statewide generation shortfall cuts power by rotating controlled outages, so no repair crew on your street can bring it back early.
- Winter loads differ from summer ones: freeze protection, heat for the core of the building and the systems that keep pipes and sprinklers safe come first.
- Fuel is the winter question: a gas unit's supply and a diesel unit's tank size and refill plan both belong in the design.
- Test under load before the first freeze, with the transfer switch moving the building to the generator.
Winter storm backup power asks different questions from hurricane planning, and Winter Storm Uri in February 2021 is the reason. Uri did not knock down poles across Houston the way Beryl did. It took generation off the Texas grid until the grid operator had to cut load across the state. This guide uses ERCOT's own reports to explain what happened, why a statewide shortfall is different from a local line down, and what that means for the fuel, the load list and the testing of a standby system at a Houston business.
What happened to the Texas grid during Winter Storm Uri?
During the week of February 15, 2021, Texas needed more electricity than its power plants could supply. ERCOT, which runs the grid for most of the state, told Congress that at its worst the storm took out 48.6% of the generation available to ERCOT. The shortage was in the power plants, not the wires.
ERCOT's report on generator outages puts the largest amount of unavailable capacity at 52,037 MW, at about 8:00 AM on February 16, 2021. That is the measure of how much generation was missing at the worst moment. With that much supply gone and demand high from the cold, the grid had to shed load or risk losing far more.
Sources: ERCOT's statement to the U.S. House Energy and Commerce Committee, March 24, 2021, and its report on generator outages by cause, updated April 27, 2021.
How much load did ERCOT shed during Uri?
ERCOT's release of February 15, 2021 reported about 10,500 MW of customer load shed at the highest point to that time, enough to serve about two million homes. That figure is from early in the event, as of that release. It is not the final peak, which ERCOT's later reports describe in their own terms.
ERCOT also told Congress why it ordered the cuts: if it had not stopped a blackout, power could have been out for 90% of Texans for weeks. Controlled outages were the tool that kept the grid running at all. For a business, that means the outage was ordered from the top of the system and rotated through circuits in turns, and the turns did not follow anyone's opening hours.
Source: ERCOT's news release of February 15, 2021.
Why is a statewide generation shortfall different from a local line down?
A line down is a local fault that a crew can find and fix, and power returns when the repair is done. A generation shortfall is a shortage of supply across the whole grid. No crew on your street can end it early, and the outage lasts until the grid has enough generation to serve the load again.
The two also look different from inside the building. After a hurricane, CenterPoint's crews restore lines feeder by feeder, so a business can watch the trucks move closer. During a grid emergency, the wires are intact and the power can come and go as rotating outages move across the system. Equipment that restarts on its own after each cut can be worn down by repeated starts, and staff cannot plan around an outage nobody can schedule.
Hurricane Beryl, which came ashore near Matagorda on July 8, 2024, is the other kind. CenterPoint reported more than 2.26 million customers out at its peak, from damage to its own lines. A standby system built for Houston has to handle both: a long outage from storm damage in summer and repeated or extended outages from a supply shortfall in winter.
What does a grid emergency mean for generator fuel at a Houston business?
It means fuel is the first question to settle. A natural gas generator depends on steady gas supply and pressure at the meter for as long as it runs. A diesel or propane generator carries its own fuel, so the questions are how many hours the tank holds at the planned load and how it gets refilled.
For a gas unit, the gas service has to be sized for the generator running at the same time as the building's own gas loads, such as heat and water heating. That is a question for the gas utility and the plumber, and the written estimate says which parts are ours and which are theirs. For a tank, the run time at the tested load decides how long the business can wait for a delivery, and icy roads are when that delivery is hardest to get.
Neither choice is right for every building. A restaurant with a large gas service may choose gas. A site that cannot risk a gas pressure drop may choose a tank and a refill contract. The load list below changes the answer too, because a shorter list burns less fuel and lasts longer on the same supply.
Which loads should stay on during a winter grid emergency?
Keep the loads that prevent damage first: freeze protection on pipes, heat for the rooms where water lines run, power for fire sprinkler and alarm equipment, and the controls of a gas heating system. Then add what keeps the business open, such as phones, servers, refrigeration and enough lighting to move safely.
Winter changes the list in two ways. Electric resistance heat is one of the largest loads a building can carry, so a generator rarely heats a whole building that way. It usually keeps one zone warm, or runs the blowers and controls of a gas system that makes its own heat. And the cost of losing a load changes: a cooler may hold in a cold building, while a burst pipe above a ceiling can close a business for weeks.
- Heat trace and freeze protection on exposed pipes.
- Heat for the rooms that hold water lines and the sprinkler riser.
- Fire alarm, security and access control power.
- Phones, network equipment and servers.
- Refrigeration that would not hold through a long outage.
- Lighting for safe movement and a working restroom.
How is a commercial standby system built for a winter outage?
It is built the same way as any standby system: a generator, an automatic transfer switch, and wiring that separates the chosen loads. For winter, the generator needs a cold weather package such as a block heater and battery warmer, and the transfer switch must handle repeated outages without damaging the loads it carries.
Most business generators are optional standby under NEC Article 702, which leaves the owner to choose what the generator carries. Systems required for life safety fall under Article 700, and standby required by a government agency falls under Article 701, each with its own transfer time and testing rules. The work goes in under a City of Houston electrical permit, which only a licensed and registered electrical contractor may obtain, and nothing is connected to power until the building official approves it.
CenterPoint keeps a Transfer Switch portal in its portal center for these requests. The full scope is on our Houston commercial standby generators page, and the price is set at the free site visit.
When should a standby system be tested for winter?
Test it in the fall, before the first freeze, under the building's real load. A start with no load proves the engine runs. A test through the transfer switch proves the system carries the winter list, transfers back cleanly when utility power returns, and starts again if the outage repeats a few minutes later.
- Check the block heater, the battery and its charger, since cold is hardest on both.
- Confirm gas pressure at the generator, or the fuel level and a refill plan for the tank.
- Run the system under load and walk the winter list to confirm each load came on.
- Test a second transfer soon after the first, the way a rotating outage would ask it to.
- Write down the results and the run time the fuel supply gives at that load.
The summer side of the same plan is in our guide to hurricane standby power for Houston businesses. For our other Houston work, see the Houston commercial electrician hub, and for our work across Texas, our commercial electrical services.