Release to CPS: How Commercial Power Is Turned On in San Antonio

November 1, 2026Last updated 6 min readWattsmith Electric · TECL 41806

Key takeaways

  • Release to CPS is the City's approval to CPS Energy to energize a service; for commercial work DSD staff send it by hand after checking the inspections.
  • The City's CPS release checklist (Rev 10/25) names six electrical inspection types, from the concrete encased electrode to Work With CPS.
  • Overcurrent devices rated 1200 amps or more need an arc energy reduction letter on file before any final inspection approval.
  • Without the release, CPS Energy may still set its meters, but in a locked position.
  • CPS Energy asks owners to allow 10 business days from the inspection release to the meter set and energizing.

Release to CPS is the City of San Antonio's name for the moment it tells CPS Energy that a building's electrical service may be energized. On a commercial job nothing about it is automatic. The Development Services Department checks that the right inspections have passed and then sends the approval to CPS Energy by hand. Until that happens, CPS Energy may set its meter but leaves it locked. This guide follows a commercial job from the first electrical inspection to the meter set, using the City's own release checklist and CPS Energy's published steps.

What does Release to CPS mean?

It is the City's approval to CPS Energy to energize a service. Information Bulletin 104a says DSD requires every building to have all permits finalized before giving final approval to CPS Energy to energize the electrical service, with one exception: a TOPS release may be given before a certificate of occupancy or letter of completion.

The City uses a few names for the same step: Release to CPS, Release to CPS Energy, and utility release. CPS Energy has been owned by the City of San Antonio for 75 years, and by its April 2026 quarterly disclosure it is currently the exclusive provider of retail electric service in its service area, because the City and CPS Energy have not opted in to retail competition. Every commercial service in that area passes through this one release. The bulletin also states that in all cases a Texas licensed master electrician registered with the City must be associated with the permit.

Sources: Information Bulletin 104a, CPS Energy's who we are page and its April 2026 quarterly update.

Why is the commercial Release to CPS a manual process?

Because a person checks the file. Information Bulletin 104a describes the commercial Release to CPS as a manual process: DSD staff check that the requirements are met and, if the appropriate inspections have passed, send the approval to CPS Energy by hand. The City's checklist says staff review the required criteria and manually generate the CPS release.

The one commercial exception on the checklist is the temporary meter loop. Its release is systematic: when the Electrical TML inspection is closed as Pass or Conditionally Approved, the release goes out on its own. Every other commercial release waits for staff. On a schedule, that means leaving time between the passed inspection and the day the utility hears about it, and keeping the permit record clean so the reviewer has nothing to send back.

Source: the City's CPS Release Requirements for commercial work, Rev 10/25.

Which inspections does the CPS release checklist list?

The checklist, titled CPS Release Requirements for commercial work and dated revision 10/25, names six electrical inspection types: Concrete Encased Electrode, Foundation/Slab, Rough-in, TOPS, TML, and Work With CPS. For the Work With CPS inspection, its status must read Pass or Conditionally Approved before the release can go forward.

Most of the types match a point in the build. The concrete encased electrode is the grounding electrode in the footing, seen before concrete covers it. Foundation and slab covers raceway set in or under the slab. Rough-in covers wiring in walls and ceilings before they close. TOPS and TML are the temporary power releases explained in our post on temporary power. The checklist does not describe the Work With CPS inspection beyond its name and its pass condition, so we confirm what it covers with DSD on each job.

In what order are commercial electrical inspections called?

DSD's commercial inspection checklist sets the order by stage. Stage 2 covers the concrete encased electrode, slab rough-in and an optional TML inspection. Stage 3 holds the electrical rough-in, alongside frame and the other trade rough-ins. Stage 5 is the final round, which must be approved before the owner can apply for a certificate of occupancy.

The City's code adds the rule behind that order. Section 10-11 says concealed or rough-in inspections are made before covering, before fixtures or appliances are set, and before the framing inspection. Underground inspections are made after trenches are excavated and bedded and the raceways and conductors are installed, but before backfill. Inspections are scheduled for free in the BuildSA customer portal or by calling the Development Services Department at 210-207-1111. A commercial permit stays active for 180 days from issue, and each inspection performed adds another 180 days.

Sources: DSD's commercial inspection checklist, the City's Chapter 10 building-related codes, the electrical permit application and the Commercial Project Application Guide.

What must be on file before the electrical final?

On a service with large overcurrent devices, one letter. DSD Information Bulletin 249 requires an arc energy reduction certification letter for fuses or breakers rated 1200 amps or more, from a qualified testing company, with an engineer's seal or proof of qualifying certification. It must reach DSD before any final inspection approval or certificate of occupancy.

The letter rests on the National Electrical Code's requirement for a written record of the arc energy reduction performance test, given to the authority having jurisdiction, on devices rated 1200 amps or higher once installed. The bulletin, dated February 23, 2026 and revised March 19, 2026, cites NEC 240.67(C) for fuses and 240.87(C) for circuit breakers. The testing company is booked well ahead, because a missing letter holds the final, and the final holds the Release to CPS. Our crews install the arc flash warning labels the code calls for on the gear; the test and its letter come from the testing company.

Source: DSD Information Bulletin 249.

What happens at CPS Energy after the release?

CPS Energy schedules its service crew. Its new commercial construction page says that once CPS Energy receives the inspection release, the owner should allow 10 business days for the crew to install the meter and energize the service. CPS Energy also needs the City's electric meter loop inspection before it can schedule a service and meter crew.

CPS Energy's step by step document is plain that all permits and inspections required by any authority having jurisdiction must be completed and released to CPS Energy before the electric meter is set. If they are not, CPS Energy will still install its infrastructure and meters, but in a locked position until it receives the inspections. The City's utility release page gives the owner's last step: once the inspections have final approval, CPS Energy is notified the property is safe to turn on, and the owner contacts CPS Energy to arrange service.

Earlier steps run on CPS Energy's side in parallel. On a new commercial service, its designer issues a final design, a contract and an invoice, and CPS Energy encourages developers to sign and pay within 5 business days to avoid schedule delays. Its underground crews need about 15 business days, weather permitting. CPS Energy inspects transformer slabs and duct banks itself, before concrete is poured.

Sources: CPS Energy's new commercial construction page, its step by step document and the City's utility release page.

How does Wattsmith keep a Release to CPS on schedule?

By treating the release as part of the electrical scope from the first day. Wattsmith registers with the City before a permit is bought, as the City requires, is added to the building permit as the electrical Licensed Professional, and calls each inspection as its stage is reached, so the record DSD staff review is complete.

Our written estimate names the inspections the job carries and who books the arc energy test where gear is 1200 amps or larger. Where equipment crosses the City's thresholds, such as service equipment over 600 amps at 250 volts or less, or over 400 amps above 250 volts, the electrical plans carry a Texas professional engineer's seal before the permit is issued. Wattsmith Electric is a veteran-owned contractor working under Texas electrical contractor license TECL 41806. The price is set after the free written estimate.

We carry jobs through this as part of commercial tenant build-outs. Power before the finals is covered in temporary power in San Antonio, and plants with large gear in industrial electrical work at Port San Antonio. For all of our work see commercial electrical services.

FAQ

Common questions

Straight answers. If you do not see yours, call us and ask.

Who sends the Release to CPS on a commercial building?

DSD staff. Information Bulletin 104a calls the commercial release a manual process: staff check that the requirements are met and, if the inspections have passed, send the approval to CPS Energy.

Will CPS Energy set a meter before the City releases the building?

It may install its infrastructure and meters, but in a locked position until it receives the required inspections. The meter is energized after the release.

How long after the release does CPS Energy energize the service?

CPS Energy's new commercial construction page says to allow 10 business days from its receipt of the inspection release for the service crew to install the meter and energize.

Related help

Where to go from here

Ready to get it handled?

Flat-rate pricing quoted up front. Licensed and insured. A Wattsmith electrician calls you back within 15 minutes during business hours.

  • Licensed and Insured
  • BBB Accredited
  • Flat-Rate Pricing
  • Background-Checked
Call NowGet a Quote