Key takeaways
- Oncor's toolkit asks for one ESI ID for the temporary pole and one for the permanent meter.
- The customer provides the temporary pole: at least 4 by 4 inches by 16 feet unspliced, marked with the address in 3 inch numbers.
- Oncor holds the meter order up to 20 work days for the city inspection, and connects only after the city approves.
- Dallas lets the electrical permit ride on the master permit and offers same-day RSVP review for qualifying new homes.
- In Fort Worth, umbrella permit fees are waived under a valid new construction building permit.
Oncor temporary power on a new home runs on two numbers and one rule. The numbers are ESI IDs, one for the temporary pole and one for the permanent meter. The rule is that Oncor connects nothing the city has not approved. A builder who has both ESI IDs moving early and books each inspection in step with the retail provider keeps the meter from holding up framing or the closing. This guide follows Oncor's Home Builders Toolkit and Electric Service Guidelines, then the permits Dallas and Fort Worth issue for new homes.
How does Oncor temporary power work on a new home?
Oncor's Home Builders Toolkit starts with two ESI IDs, the premise numbers, one for the temporary pole and one for the permanent meter. The builder calls the retail electric provider with the pole's ESI ID, timed with the electrical inspection request, and Oncor holds the order up to 20 work days for the city inspection.
Once Oncor receives the city inspection, it works to set the meter on the requested date. Its Electric Service Guidelines say temporary service for construction starts with a call to Oncor, and that a retail electric provider must be chosen before a temporary meter is installed and energized. Oncor's tariff adds that temporary delivery facilities are paid for before Oncor builds them. The toolkit is undated and some of its links point to older Oncor addresses, so we check each step against the current guidelines.
Sources: Oncor's Home Builders Toolkit, its Electric Service Guidelines, February 2025, Section 600.01, and its Tariff for Retail Delivery Service, Section 5.7.7.
What does Oncor require of the temporary pole?
The customer provides and installs it. Oncor's guidelines call for a pole at least 4 by 4 inches by 16 feet unspliced, or a treated pole with a 5 inch minimum diameter at the top, tall enough for the service drop to meet clearance, 12 feet minimum. The pole carries the address in numbers at least 3 inches high.
Oncor owns and installs the service drop conductors, the service grips and the connectors. Everything below the drop is the builder's electrician's work: the pole, the meter base, the panel and the receptacles the trades plug into. Oncor's guidelines are revised from time to time and say the customer is responsible for using the latest revision, so the pole is built to the current book. The February 2025 edition applies to construction started on or after that month.
What does Oncor check before setting the temporary meter?
The toolkit gives a short checklist. Street signs are present, the address is clearly marked and in plain sight, and the handhole is not covered or damaged. For underground service there is enough flex conduit to reach into the transformer or handhole, and for overhead service the service entrance conductors are at least 24 inches long.
The handhole line is the one that costs time. Oncor's toolkit warns that a damaged or buried handhole or pedestal can cause service delays for up to six weeks. On a lot where the grading crew has been through, the handhole can end up under dirt or crushed by a machine. Checking it before the meter is ordered, and reporting damage to Oncor's new construction line when it is found, is faster than waiting.
When does Oncor set the permanent meter?
After the city approves the home's electrical installation. The toolkit heads this step "Green Tag": the builder calls the retail provider with the permanent ESI ID, following the checklist, and Oncor says every attempt will be made to install underground service in 7 to 10 business days. Dallas and Fort Worth call that approval a release.
The rule behind it is in both Oncor documents. Its tariff and its guidelines say Oncor will not interconnect until it receives notice that the proper authority approved the customer's installation, and that Oncor does not inspect the customer's wiring itself. The city's final inspection is the step the meter waits for, so it goes on the schedule before the retail provider call, not after it.
Source: Oncor's Tariff for Retail Delivery Service, Section 5.4.2.
What is Oncor's standard for new residential service that needs construction?
Oncor's tariff says new residential delivery service that needs construction, such as a line extension, is completed within 90 days of the Facility Extension Agreement, or a period both sides agree to, after the requester has made payment arrangements. The clock starts at the agreement, not at the first phone call.
Oncor's new service request site routes residential, subdivision, multi-family and commercial projects, with the New Construction Management Center as backup. For a subdivision, Oncor's load form asks for a copy of the plat and water and sewer prints, and an easement for on-site Oncor facilities by final plat or separate instrument. Most of Dallas and Fort Worth is served by Oncor; some edge areas are co-op territory, where the co-op's own steps apply.
Sources: Oncor's business and new service page and its Residential Subdivision load form.
What does Dallas require for a new home's electrical permit?
Dallas's new one and two family checklist says permits are issued only to a registered contractor, an Energy Code Certificate goes to the electrical inspector before final, and builders contact Oncor before any work near overhead lines. Where electrical plans were in the master permit set, no further electrical plan submittal is needed.
Dallas also runs the Rapid Single-Family VIP program, RSVP, an expedited plan review built to issue new single-family and duplex permits the same day the project is reviewed. The city says it is open to any registered developer, homeowner, architect, engineer or contractor, for an hourly review fee the city sets. The electrical permit can be paid for on the master permit, while the wiring itself goes to a registered electrical contractor.
Sources: the City of Dallas New Construction for One and Two Family Dwellings checklist, its Electrical Permit Application Checklist, and its RSVP program FAQ.
How do Fort Worth residential and umbrella permits work?
Fort Worth's residential building permits cover one and two family detached homes, and applicants must be registered building contractors. Electrical service work needs its own electrical permit. The city's Electrical Permit Application says umbrella permit fees are waived with a valid new construction building permit, and it lists the temporary pole as a permit item.
The city's stated first review standard for a complete residential permit is 7 business days. The numbered electrical inspections then follow the house as it goes up, from underground and slab before cover to rough-in before the walls close, and the city releases power after the electrical final.
The full order is in our guide to the Fort Worth electrical inspections sequence. Sources: the city's residential permits page, its Electrical Permit Application, and its review timeframes page.
Do you wire new homes for DFW builders?
Yes. For home builders in Dallas and Fort Worth we wire new homes, from the temporary pole to the final and the permanent meter. We get the permanent ESI ID moving at rough-in, so the meter is not what holds the closing. Service calls, repairs and remodels on existing homes stay in the San Antonio area only.
See Fort Worth new construction electrician and Dallas new construction electrician, the Fort Worth commercial electrician hub, and our commercial electrical services. The price for wiring a plan is set at the free site visit.