Key takeaways
- Home Builder Loops serve single and duplex homes; Temporary Power Loops serve triplexes, fourplexes and commercial or multifamily work. Each needs a City permit and inspection first.
- Austin Energy provides temporary construction power for 24 months, and its charges for the temporary facilities are paid before installation.
- Since October 2026, Austin Energy no longer requires the BSPA with residential permit applications.
- Austin Energy sets the service point the day after the electric permit becomes active, and inspects the service conduit with the trench open.
- The residential 304 Temporary inspection is the City's Request for Permanent Power, conditional on inspector approval.
Austin Energy temporary power for a new home starts with a meter loop the City has permitted and inspected. Austin Energy calls the loops for single and duplex homes Home Builder Loops and the loops for larger work Temporary Power Loops, and each one needs its own City permit and inspection before it is connected. This guide follows a builder's lot from plan review to permanent power, in the words Austin Energy and the City of Austin use for each step. In Austin we wire new homes for home builders only. Service calls, repairs and remodels on existing homes stay in the San Antonio area only.
What is the difference between an HBL and a TPL?
What the loop is used for. Austin Energy's Design Criteria says Home Builder Loops are single-phase construction loops used only for building work on a single or duplex family residence. Temporary Power Loops are single-phase or three-phase, for triplex and quadruplex residences and commercial or multifamily projects. Every meter loop needs a meter can of at least 200 amps.
Both kinds still need a City of Austin permit and an inspection by the City's Building Inspections division before use. A TPL, whether new or used, requires a new permit and a new inspection, and every TPL needs a separate address identifier. The Design Criteria adds that an application for temporary service must also be made to Austin Energy for either type, so the loop is on two lists: the City's and the utility's.
Larger temporary services, over 350 amps single-phase or 225 amps three-phase or in the Downtown Network, are requested with an ESPA through the Austin Energy Additional Services Design Intake in the AB+C Portal. Most single lots never reach that size.
Sources: Austin Energy's Design Criteria, section 1.7.1.4, and its construction and renovation page.
How long does Austin Energy provide temporary power?
Up to 24 months. Austin Energy's Design Criteria says it provides temporary construction power to job sites for 24 months for the sole purpose of construction, and that all temporary construction power is disconnected when the permanent meter is installed. The loop powers the build, and it comes out when the house goes onto its permanent meter.
The same section says the customer pays for the labor to install and remove the temporary facilities, along with the other costs of providing temporary power and any non-reusable materials, before temporary power is installed. A builder who knows that schedules the loop request once the permit is in hand, so the payment and the installation are not waiting on each other.
How long does residential plan review take in Austin?
The City's Residential Plan Review page lists 10 business days for new construction and additions. It reviews new single-family, duplex and two-family houses to Land Development Code Chapter 25-2, the 2024 International Residential Code and the Chapter 25-12 local amendments. Most stand-alone trade permits can be requested directly in the AB+C Portal.
The electrical permit follows the plans. We take it out under our City registration, which the City requires of every trade contractor and which must be updated each year. Wattsmith registers with the City before a permit is bought, as the City requires, and works under Texas electrical contractor license TECL 41806.
Sources: the City's Residential Plan Review page and its contractor registration page.
What changed with the BSPA in October 2026?
Austin Energy stopped asking for it. The City's Residential Plan Review page lists, under its October 2026 process changes, that Austin Energy will no longer require the Building Service Planning Application when residential permit applications are submitted. Austin Energy's 2023 Design Criteria still describes the BSPA, so the newer City page is the one to follow.
Austin Energy itself notes that some processes described in its Design Criteria are not up to date. Where the manual and a newer City or Austin Energy page disagree, we follow the newer page and confirm with Austin Energy on the job. The October change removes one form from the residential submission, not the ESPA: on service-only jobs, Austin Energy still approves the ESPA, and it is still attached to the electric permit.
Where does the ESPA fit on a new home?
On service-only jobs, which sit outside the Downtown Network, need under 350 amps single-phase or 225 amps three-phase, and have Austin Energy facilities in place, the completed ESPA goes to Austin Energy's Development Assistance Support review team. Once approved, it is attached to the electric permit during the application.
After that, Austin Energy's steps run in order: the City inspects and approves the work, the customer applies for service and sets up billing with Austin Energy, and Austin Energy energizes the location. The Design Criteria says the same in its own words: once the equipment passes electrical inspection and all permits are closed out, the customer may apply for temporary or permanent service.
When does Austin Energy mark the service point?
The day after the electric permit becomes active. Austin Energy's spot location and conduit inspection page says the request for a spot location is generated automatically then, and that it does not perform the spot location until an active permit exists. The underground service conduit is inspected with the trench still exposed.
Two inspectors see conduit on a new home. Austin Energy inspects the service conduit it will pull its conductors through, and the City's Building Inspections division inspects the load side conduit. We leave the trench open until both have signed off, because a backfilled trench that has not been inspected is dug up again.
Source: Austin Energy's Spot Location and Conduit Inspection page.
What is the 304 Request for Permanent Power?
It is the residential 304 Temporary inspection. The City's residential checklist, dated October 9, 2026, titles it Request for Permanent Power, conditional on inspector approval. It needs the grounding inspection passed, a final inspection also requested or a reason for temporary power approved, and the metering equipment and location approved by the utility.
The checklist also asks that a surge-protective device be installed, citing 2026 IRC 3606.5 and 2026 NEC 230.67. The City books inspections through the AB+C Portal or by phone, and says they are usually performed 24 hours after scheduling, sometimes the next business day or 48 hours out when inspectors are busy. A builder planning a closing date works back from that window.
On a subdivision the same order repeats on every lot: permit, loop inspection, spot location, conduit inspection, rough-in, the 304 request and the final. We track each lot's permit and inspection status for the builder's superintendent, so a lot ready for permanent power is not left waiting on a request nobody made.
Sources: the City's residential Electrical Temporary Inspection Checklist and its Building Inspections page. The commercial inspections are a longer sequence, set out in the Austin electrical inspection sequence.
Does Wattsmith wire new homes in Austin?
Yes, for home builders only. We wire new homes from the temporary loop through rough-in, trim-out and the permanent service, and we carry the permits and inspections that go with them. The price of each plan is set after the free written estimate. Service calls, repairs and remodels on existing homes stay in the San Antonio area only.
Builders can see the work on our Austin new construction electrician page. For our commercial work in the city see the Austin commercial electrician hub, and for all of Texas our commercial electrical services.