Hurricane Standby Power for Houston Businesses: What Beryl Taught

November 1, 2026Last updated 7 min readWattsmith Electric · TECL 41806

Key takeaways

  • CenterPoint reported more than 2.26 million customers out at Beryl's peak in July 2024, two months after a derecho drove winds over 100 mph through the Houston metro.
  • A commercial standby system is a generator, an automatic transfer switch and the wiring that separates the loads you keep from the ones you drop.
  • Most business generators are optional standby under NEC Article 702; life safety systems fall under Article 700 and legally required standby under Article 701.
  • CenterPoint keeps a Transfer Switch portal for these requests, and the work goes in under a City of Houston electrical permit.
  • Test the system under load in late spring, before the storm season, not on the morning the power fails.

Hurricane standby power is a plan a Houston business makes before the storm, not during it. Hurricane Beryl in July 2024, and the derecho two months before it, left large parts of the metro without power for days. The businesses that kept running had a generator, a transfer switch and a short list of loads already wired to stay on. This guide covers what those two storms showed, how a commercial standby system is put together, which part of the National Electrical Code it falls under, and what CenterPoint Energy and the City of Houston ask for before it goes in.

What did Hurricane Beryl show Houston businesses about power?

Beryl showed that a Category 1 hurricane can cut power across the whole metro at once. It came ashore near Matagorda at 4 am on July 8, 2024, and CenterPoint reported more than 2.26 million customers out at the storm's peak. A business with no power of its own waited in that line with everyone else.

The National Weather Service office for Houston and Galveston counts the same event by people rather than by meters. Its impact summary says outages peaked at around 2.7 million people, with over a million people still without power four days after the storm. The highest gust it recorded was 84 mph at Hobby Airport. The two sources count different things, so their numbers are read side by side, never added or swapped.

Restoration at that scale takes outside crews. CenterPoint said it mobilized about 11,500 frontline resources for Beryl, bringing in about 10,000 from other utilities to add to its own 1,500. Even with that many crews, a utility works first on the lines that bring back the most customers, and a single building at the end of a damaged feeder can wait longer than most.

Sources: the National Weather Service Hurricane Beryl page, CenterPoint's July 8, 2024 update on Beryl, and the NWS Beryl impact narratives.

Why does the May 2024 derecho matter for storm planning?

The derecho matters because it was not a hurricane and still put much of the metro in the dark. On May 16, 2024 the National Weather Service tracked a swath of winds over 100 mph down through the Houston metro. A line of storms gives far less warning than a hurricane, so there were no days to prepare.

CenterPoint's releases show how restoration went. It said more than 630,000 impacted customers were restored in the 72 hours after the storm, and by May 20 it had restored more than 770,000 customers, about 85% of those affected. Most were back within days. Some were not, and for a restaurant with a full walk-in cooler or a clinic with a full schedule, that remainder is the risk. Two storms in one season, from two kinds of weather, are why standby power in Houston is planned for the whole year and not only for hurricanes.

Sources: the NWS May 2024 regional climate summary, and CenterPoint's restoration updates of May 19 and May 20, 2024.

What is a commercial standby system?

A commercial standby system is a permanently installed generator, an automatic transfer switch that moves the chosen loads from the utility to the generator when power fails, and the wiring that separates those loads from the rest of the building. When utility power returns, the switch transfers back and the generator cools down and stops.

Each part has its own job. The generator is sized to the loads that must run, not to the whole building, and runs on natural gas or on fuel from a tank. The transfer switch watches the utility supply, starts the generator when it drops, and connects the chosen loads once the generator is ready. Load separation is the part owners tend to overlook: the circuits that stay on move to their own panel, or the switch is placed so it carries only them. That keeps a generator sized for a cooler and a server room from being asked to start every rooftop unit on the roof.

  • Generator, sized from the list of loads you choose.
  • Automatic transfer switch, rated for the loads it carries.
  • A standby panel or load shedding, so only the chosen circuits move to the generator.
  • Labels at the service and the switch that show where standby power comes from.
  • Gas service or a fuel tank, with the estimate saying which parts go to a plumber or a concrete contractor.

We install the whole system under a city permit, as described on our Houston commercial standby generators page.

How do you choose which loads stay on during a hurricane outage?

Start with what costs the most to lose: refrigeration, servers and phones, security and alarm power, enough lighting to move safely, and a restroom. Write the list room by room, then add only what the business needs to keep serving customers. The generator is sized from that list, not from the size of the building's service.

A walk through the building turns the list into circuits. We find each load in the panels, note what it draws, and mark what can be grouped. Some loads look small and are not: a walk-in cooler's compressor pulls a large current for a moment when it starts, and the generator has to carry that start. Others look essential and can wait, such as a second rooftop unit when one keeps the core of the building usable.

The list also decides how the system is built. A short list usually means a separate standby panel fed through the transfer switch. A list that covers most of the building can mean a transfer switch at the service, with load shedding that drops the large loads the generator cannot carry. Either way the choice is written into the estimate, so everyone knows what will run and what will not.

Which NEC article covers a business generator: 700, 701 or 702?

It depends on why the power is needed. Article 700 covers emergency systems required for life safety, such as egress lighting. Article 701 covers legally required standby, which a government agency requires. Article 702 covers optional standby, which the owner chooses to protect the business. Most business generators fall under Article 702.

The difference shows up in how the system is built. An emergency system under Article 700 must restore power within 10 seconds, keeps its wiring apart from other circuits, and carries its own testing and record rules. Legally required standby under Article 701 has a 60 second limit and rules of its own. Optional standby under Article 702 leaves the owner the most room to decide what the generator carries, as long as the generator can handle the load the transfer equipment connects to it.

One building can have more than one. A medical office might have life safety lighting under Article 700 and a separate optional system under Article 702 for its refrigerators and records. Keeping each in its own branch is part of the design, and when the building's use calls for Article 700 or 701, the engineer and the inspector settle which rules apply.

What does CenterPoint need before a standby system goes in?

CenterPoint keeps a Transfer Switch portal in its online portal center, where transfer switch requests are created and viewed. The transfer switch is what keeps a generator from sending power back onto CenterPoint's lines, so that request belongs in the plan before the switch is set, not after the generator arrives.

When the job also changes the service itself, such as a new main to make room for the transfer switch, the portal center also carries the Electric Service Request for new or modified service. CenterPoint connects only after the proper authority's approval reaches its Permit Desk, so the city inspection and release come before any change at the meter.

CenterPoint's portal center lists the Transfer Switch portal beside the ESR, Joint Trench and MUG portals, and its service connect page describes the Permit Desk.

Is a city permit required for a commercial standby system in Houston?

Yes. The generator, the transfer switch and the wiring are electrical work under a City of Houston electrical permit, and Houston's code says only a licensed and registered electrical contractor may obtain one. Nothing is connected to a source of power until the building official approves it and the city sends its release.

Houston's code asks for plans and calculations with the application, and the building official may require them sealed by a Texas professional engineer or may waive them when review is not needed. Wiring meant to be concealed is inspected before it is covered, and a final inspection follows when the installation is complete. We book those inspections as the work reaches each stage, so the permit does not hold up the day the generator starts.

The rules are in the City of Houston Electrical Code administrative provisions, Sections 302, 305 and 306.

When should a standby system be tested before storm season?

Test it in late spring, before hurricane season and in the same months the derecho arrived. A test under load, with the transfer switch actually moving the building to the generator, shows what a start with no load cannot: whether the unit carries the list it was sized for and whether the switch transfers back cleanly.

  • Run the generator under the building's real load through the transfer switch, and time the transfer.
  • Check the battery, the charger, fluids, filters and the exercise schedule.
  • Confirm gas pressure or the fuel level, and how long the tank lasts at the tested load.
  • Walk the list of standby loads and confirm each one came on.
  • Record the results, as Article 700 requires for emergency systems and as good practice for every other kind.

A yearly spring visit can go into a Houston maintenance agreement. The cold weather side of the same planning is in our guide to winter storm backup power for Houston businesses. For the rest of our Houston work, see the Houston commercial electrician hub, and for everything we do across Texas, our commercial electrical services. The price of a standby system is set at the free site visit.

FAQ

Common questions

Straight answers. If you do not see yours, call us and ask.

How many CenterPoint customers lost power in Hurricane Beryl?

CenterPoint reported more than 2.26 million customers out at the storm's peak on July 8, 2024. The National Weather Service counts people rather than customers, and its own summary gives a separate figure.

Which NEC article covers a business generator?

Most are optional standby under Article 702. A system required for life safety falls under Article 700, and one a government agency requires falls under Article 701.

What does a commercial standby system cost in Houston?

The price is set at the free site visit, from the loads you choose, the transfer switch and the gas or fuel supply, and you get it in writing.

Related help

Where to go from here

Ready to get it handled?

Flat-rate pricing quoted up front. Licensed and insured. A Wattsmith electrician calls you back within 15 minutes during business hours.

  • Licensed and Insured
  • BBB Accredited
  • Flat-Rate Pricing
  • Background-Checked
Call NowGet a Quote