Key takeaways
- A commercial panel upgrade starts with a load study under NEC Article 220, not with the size of the panel on the wall.
- Services over 350 amps single phase or 225 amps three phase, or over 320 amps continuous, go through Austin Energy Design Intake.
- Austin Energy's Distribution Metering group must approve service equipment before it is bought or installed, and it asks that metering equipment be ordered early.
- For CT services, Austin Energy's CT inspection must pass before the City's 305 final is called.
- The shutdown is planned with the owner and Austin Energy in writing; the price is set after the free written estimate.
A commercial panel upgrade in Austin ranges from replacing one worn or full panelboard to changing the whole service, with new switchgear, new feeders and a new meter that Austin Energy has to design and approve. Which one a building needs depends on its load, not on the age of the gear alone. This guide covers how that size is worked out, where Austin Energy's thresholds and metering approval come in, which City of Austin permits and inspections apply, and how the shutdown is planned so the business loses as little time as possible.
What is a commercial panel upgrade?
Any change that gives a building more capacity or safer distribution: a larger or added panelboard, a new switchboard, larger feeders, or a bigger service from Austin Energy. A like-for-like panel swap stays on the building side; an increase in service size brings in Austin Energy's design, metering and inspection steps as well.
The words get used loosely, so it helps to name the level. Adding a subpanel for a new tenant area is distribution work. Replacing a main distribution panel with a larger one, without changing the utility service, is equipment work under NEC Article 408. Raising the service ampacity changes the service conductors, the service equipment under Article 230 and often the meter, and that is where the utility becomes a partner in the job rather than a bystander.
When does a business need a commercial panel upgrade?
When the existing equipment can no longer carry the load safely, has no room for the circuits the business needs, or has reached the end of its service life. New kitchens, chargers, process equipment and HVAC are the usual triggers, along with breakers that trip under normal use or panels with no spare spaces.
Condition counts as much as capacity. Signs worth a closer look include heat or discoloration at breakers and lugs, corrosion, damaged enclosures, missing covers, and equipment for which replacement parts are no longer made. A tenant change is a good moment to look, because the space is open and a permit is already in motion. So is a change of use, when a building that was storage becomes a shop floor or an office becomes a lab.
How is the new panel or service sized?
From a load study. The electrician reads the existing service, the panel schedules and, where available, a year of demand data, adds the planned loads, and works the total under NEC Article 220. The result sets the service size, the panel ratings and the feeder sizes, with spare capacity chosen on purpose.
Austin Energy needs its own version of the same numbers. Its ESPA asks the customer to state the total undiversified connected load for each equipment item or load category, so it can size its transformer and service lines. The study also checks the available fault current at the service, because new equipment must be rated for it, and the City's commercial checklists dated October 2026 ask that available fault current be posted under 2026 NEC Article 110.24. Planning for growth now, with spare breaker spaces and conduit, often causes less disruption than a second upgrade later.
When does Austin Energy have to design the service?
When the service crosses its thresholds. Services over 350 amps single phase or 225 amps three phase outside the Downtown Network, every Downtown Network project, and anything needing an Austin Energy design go through Design Intake. Austin Energy adds that a load over 320 amps continuous must move to CT metering and through that process.
For a commercial upgrade, Austin Energy lists the steps in order: a site plan approved by Austin Development Services, an intake request in the AB+C Portal, ESPA approval, a design with Austin Energy, the customer's civil work and metering equipment, a City electric permit, City inspection and approval, an application for service, and energizing. Austin Energy schedules the connection only after the ESPA is approved, the City permit is obtained, the work matches its design, the inspections are passed and an account is set up.
Sources: Austin Energy's construction and renovation page and its Design Criteria, sections 1.4.2.1 to 1.4.2.4 (effective December 12, 2023; Austin Energy notes some processes in it are not up to date). New service from the start is covered in Austin Energy new commercial service.
Why does the metering equipment get ordered early?
Because it can hold up the whole job. Austin Energy asks that metering equipment be ordered as soon as possible or supply chain delays may slow the project, and its Distribution Metering group must approve service equipment before the customer buys or installs any of it. Approval first, then the order, then the wait.
On a CT service the metering adds its own inspection. Austin Energy requires every transformer-rated service to be inspected before a meter is set, and its guideline says the CT inspection must be called in and passed before the City's 305 final inspection is requested. Lining those up on the schedule, rather than discovering them at the end, is most of what keeps an upgrade on time.
Source: Austin Energy's metering guidelines for instrument rated installations. Austin Energy gives no fixed overall timeline; its construction and renovation page says the timeline to energization starts with submission.
What permits and inspections does the upgrade need in Austin?
A City of Austin electric permit and the commercial electrical inspections that apply to the job. The City's commercial flowchart runs from grounding and slab inspections, through 301 Rough once the building is dried in, to 304 Temporary and the 305 Final, with 306 or 307 TCO inspections only when occupancy or stocking needs one.
An upgrade inside an existing building usually skips the slab stage, but the service and grounding are still checked. The City's temporary inspection checklist asks that the 302 Grounding inspection be passed and, where required, that Austin Energy has completed a CT inspection and approved the meter equipment; its final checklist asks that service equipment be suitable for the use and identified as such under 2026 NEC Article 230.66. Inspections are booked through the AB+C Portal and are usually performed within 24 hours of scheduling, the City says, though an inspector's workload can push one to the next business day or 48 hours.
Sources: the City's commercial electrical inspections flowchart, the commercial temporary inspection checklist, the commercial final inspection checklist and the Building Inspections page. What the drawings need is in Austin electrical plan review.
How is the shutdown planned?
In writing, with the owner and Austin Energy, before the day. The plan names the date and hours, which loads go dark, what stays up on temporary power or a generator, who disconnects and reconnects the utility side, and the order in which circuits come back. After the City's passed inspection, Austin Energy wants three working days' notice before energizing.
Most of the work happens before the outage: new gear set beside the old where space allows, feeders pulled and terminated, circuits labeled and tested. The cutover is then a short, rehearsed sequence. For a business that cannot close, a temporary service or a rented generator can carry the critical loads, and that choice belongs in the estimate. New arc flash warning labels under NEC 110.16 go on the new gear; we install the labels, and any arc flash study behind them is engineering work for a qualified engineer.
This guide is about commercial buildings. Wattsmith wires new homes for builders in Austin, and does not upgrade panels in existing ones there. Service calls, repairs and remodels on existing homes stay in the San Antonio area only.
See our Austin commercial service upgrades and switchgear page. If the upgrade is paired with backup power, see standby power for Austin business. For the rest of our work in the city, see the Austin commercial electrician hub and our commercial electrical services. The price is set after the free written estimate.