Key takeaways
- Austin Energy is a City of Austin department and is not part of retail deregulation, so the business works with Austin Energy for both its power and its connection.
- Austin Energy's steps run from an approved site plan, through an AB+C intake request and the ESPA, to design, the City permit, the City inspection and energizing.
- Services over 350 amps single phase or 225 amps three phase go through Austin Energy Design Intake.
- Austin Energy gives no fixed timeline and asks for notice of the City's passed inspection three working days before it energizes.
New commercial electric service in Austin means working with Austin Energy and Austin Development Services at the same time. Austin Energy designs and builds the utility side and sets the meter. Development Services permits and inspects the building side. Austin Energy will not energize until the City has inspected and approved the work. This guide walks through Austin Energy's own steps for a new commercial service or an upgrade, using its construction and renovation page and its Design Criteria, so an owner or builder knows what to submit, in what order, and what each step waits on.
Who supplies power to a business in Austin?
Austin Energy does. It is a department of the City of Austin and an ERCOT member, and it says it is not participating in retail deregulation. A business in its service area cannot pick a retail electric provider, so Austin Energy is both the utility that builds the service and the one that bills for power.
That keeps the list of parties short. On a new commercial service, every step is between the owner, the owner's electrician and engineer, Austin Energy and the City of Austin. There is no third company selling the energy to bring into the conversation.
Austin Energy's service area covers about 437 square miles, mostly in Travis County with the rest in Williamson County, and only about half of it lies inside Austin city limits. A site near the edge of town may or may not be on Austin Energy, so confirm the utility for the exact address before planning the service.
Austin Energy describes its place in the market on its statewide electric grid page.
What are Austin Energy's steps for new commercial service?
Austin Energy lists the steps in order: have the site plan approved by Austin Development Services, submit an intake request in the AB+C Portal, receive approval of the Electric Service Planning Application, work through design with Austin Energy, finish the customer's civil work and metering equipment, get the City electric permit, pass City inspection, then energize.
- Site plan approved by Austin Development Services.
- Intake request submitted through the AB+C Portal.
- ESPA approved, with a stamped copy sent to the customer.
- Design completed with Austin Energy Design.
- Customer civil work and metering equipment in place.
- City electric permit and all other required permits obtained.
- City inspection and approval, then the customer applies for service.
- Austin Energy energizes the location.
The full list is on Austin Energy's construction and renovation page.
What goes into the Austin Energy intake request?
Austin Energy's page asks for an ESPA for every address, an AutoCAD file of the site plan, a riser diagram and an address verification report, plus added items for some project types, such as layouts for Downtown Network projects and a Commercial Electric Permitting Application for multi-metered commercial projects. Incomplete packages slow the review.
The Design Criteria says the same in its own words for apartments, commercial, multifamily, mixed use and subdivisions: submit an AutoCAD drawing of the approved site plan, a riser diagram and the 911 address verification form. The site plan has to be approved first, which is why the City's site plan step sits at the top of Austin Energy's list.
Why does the ESPA matter so much?
The ESPA, the Electric Service Planning Application, is needed twice. Austin Energy needs it to design power for a new development or a changed service, and Development Services needs it to issue an electric permit. It must state the total undiversified connected load for each equipment item or load category so Austin Energy can size its facilities.
That load figure is the electrician's work. In general practice it comes from the same load calculation the permit drawings carry, built under NEC Article 220 from the lighting, receptacles, HVAC, motors, kitchen or process equipment and any planned EV chargers. Getting it right the first time keeps the ESPA from going back for changes, and it lets Austin Energy size the transformer and service conductors once.
Which services go through Austin Energy Design Intake?
Austin Energy's Design Criteria sends services over 350 amps single phase or 225 amps three phase outside the network area, every Downtown Network project, and anything needing an Austin Energy design through Design Intake. Smaller service-only jobs take a simpler ESPA review, but a load over 320 amps continuous must move to CT metering and Design Intake.
Most new commercial buildings and many tenant spaces with new service fall on the Design Intake side, because three phase service above 225 amps is common for retail, restaurant, office and light industrial buildings. Knowing which side of the line the job falls on early tells you how much design work Austin Energy has to do before anything is built.
What must happen before Austin Energy connects the service?
The Design Criteria lists five conditions before Austin Energy schedules a new connection: an approved ESPA from Austin Energy Design, a City electric permit and all required permits, all work done to Austin Energy's design and metering requirements, all required inspections passed, and an account set up with Austin Energy.
Two more rules sit inside those steps. Before buying or installing any service equipment, the customer must get approval from Austin Energy's Distribution Metering Operation. And for CT rated, or instrument rated, services, Austin Energy must inspect before any meter is set, and its CT inspection must pass before the contractor calls for the City's 305 final inspection.
The connection rules are in Austin Energy's Design Criteria, and the CT inspection order is in its instrument rated metering guidelines.
How long does Austin Energy new commercial service take?
Austin Energy gives no fixed timeline. It says the project timeline to energization starts with the submission step, and it warns that metering equipment should be ordered as soon as possible or supply chain delays may slow the project. The Design Criteria also asks for three working days' notice of the passed City inspection.
The Design Criteria in use is the edition effective December 12, 2023, and Austin Energy's own page notes that some processes described in it are not up to date. Where a step matters to the schedule, we confirm it with Austin Energy Design on the job rather than relying on the manual alone.
On the customer side, switchgear, panelboards and meter equipment can be the slowest items to arrive, which is why Austin Energy's warning about ordering metering equipment early is worth taking literally. We place those orders once Distribution Metering has approved the equipment, so nothing bought early has to be sent back because it does not match Austin Energy's requirements.
What can an owner do to keep the service on schedule?
Start Austin Energy's track at the same time as the City's. Get the site plan approved, submit the intake request with a complete package, have the electrician's load calculation ready for the ESPA, ask Distribution Metering to approve the service equipment before it is ordered, and order the metering equipment early.
- Gather the AutoCAD site plan, riser diagram and address verification before the intake request.
- State the connected load for each equipment item on the ESPA.
- Get Distribution Metering approval before buying switchgear or meter equipment.
- On CT services, call Austin Energy's CT inspection before the City's 305 final.
- Allow three working days between the passed inspection and energizing.
We size, install and inspect the customer side of new services and upgrades; see our Austin service upgrades and switchgear page. The City side is in our guide to how commercial electrical permits work in Austin, and the Austin commercial electrician hub and our commercial electrical services page list the rest of our work. Every job is priced after the free written estimate.