Key takeaways
- Standby power is sized from the loads that must keep running, listed and measured, not from the size of the building.
- NEC Article 700 covers emergency systems, 701 legally required standby and 702 optional standby, and each sets its own wiring rules.
- Austin Energy exempts standby systems that do not run in parallel with its grid beyond brief transfer; parallel systems follow its interconnection procedure.
- Parallel systems from 50 kW to under 1 MW need an automatic sync-check relay or an open transition transfer switch.
- The price is set at the free site visit, from the loads, the transfer switch, the fuel and the pad.
Standby power for an Austin business means a generator, or another on-site source, that takes over the loads that must keep running when Austin Energy's supply is lost, and hands them back when it returns. The work is in the sizing and the installation: listing the loads, choosing the NEC article the system falls under, picking the transfer switch, deciding whether it ever runs in parallel with the grid, and building it under a City of Austin permit. The storm record that makes the case for standby in Austin has its own guide; this one is about the system itself.
For the outages behind it, see Winter Storm Mara and standby power in Austin.
What does standby power cover for an Austin business?
Whatever the business decides must not stop: refrigeration, servers and network gear, security, a production line, a pump, life safety equipment, or the whole building. The generator, its transfer switch and the wiring between them are sized around that list, so writing the list is the first step of any standby project.
Austin Energy's report on the February 2021 winter storms makes the stakes plain for large sites: it says customers are responsible for managing the risks of any on-site hazardous materials during outages and for meeting their regulatory obligations, and that during those storms Austin Energy and the City were called on to find fuel for backup generators or restore power to specific customers. A standby plan that answers for its own fuel and its own loads keeps a business off that list.
Source: Austin Energy's February 2021 Winter Storms After-Action Report, section on large commercial and industrial customers.
Which NEC article applies to the standby system?
It depends on why the power is needed. Article 700 covers emergency systems required for life safety, such as egress lighting. Article 701 covers legally required standby, where a code or authority demands it. Article 702 covers optional standby, chosen by the owner to protect the business, which is where most commercial generators sit.
The article matters because each sets its own rules for transfer time, wiring separation, signs and testing. An emergency system's wiring is kept apart from other circuits and must transfer quickly; optional standby has more freedom in how loads are chosen and shed. One generator can serve more than one class, with separate transfer switches, so the load list should mark which article each load falls under before anything is sized.
How is a standby generator sized for an Austin business?
From the loads, measured or calculated. Each load on the list is given its running power and its starting power, since motors and compressors draw far more for a moment when they start. The total, with the starting sequence planned, sets the generator size; demand data from the utility meter helps check the result.
Two choices change the answer a great deal. A whole-building system must carry everything the building could draw at once, worked out under NEC Article 220. A partial system carries only the chosen loads, which are moved to a separate panel fed through the transfer switch. Load shedding, where the controls drop lower-priority loads to protect the generator, can let a smaller unit serve safely. Room for growth is chosen on purpose: a generator sized to the inch today may be too small after the next tenant change.
- List every load that must run, and mark its NEC article.
- Record running and starting power for each, from nameplates or measurement.
- Plan the starting sequence so large motors do not start together.
- Decide whole-building or partial, and which loads can be shed.
- Add chosen spare capacity, then select the generator and the fuel.
What kind of transfer switch does the job need?
One rated for the load, the fault current and the article it serves. Most commercial standby uses an automatic transfer switch that senses the outage, starts the generator and moves the load. Open transition switches break from the grid before connecting the generator; closed transition switches overlap the two briefly, which brings in Austin Energy's rules.
Service-entrance rated transfer switches can combine the service disconnect and the transfer function in one enclosure, which saves space in a crowded electrical room. Bypass isolation switches let the switch itself be serviced without dropping the load, a feature hospitals and data rooms often want. The choice also decides how the generator's grounding and neutral are arranged, which has to match the rest of the system.
When does Austin Energy need to review a standby system?
When the generator runs in parallel with Austin Energy's grid. Austin Energy's interconnection guide says emergency and standby systems under NEC Articles 700 to 702 that do not run in parallel, other than brief transfer, need not follow its interconnection procedure. Parallel operation longer than about 1 second must, and any closed transition switching needs synchronizing controls.
The guide adds that parallel systems not on the Downtown Network, rated at least 50 kW to less than 1 MW, must also have an automatic sync-check relay, where the generator is synchronous or self-commutated, or an open transition transfer switch. Austin Energy's Design Criteria says each request to interconnect customer-owned generation must be reviewed and approved individually. For most optional standby systems, an open transition switch keeps the job outside the interconnection procedure altogether.
Sources: Austin Energy's Distribution System Interconnection Guide (revision 14.0, November 12, 2024) and its Design Criteria (effective December 12, 2023; Austin Energy notes some processes in it are not up to date).
What does the installation job involve?
A pad or support for the generator, the fuel supply, conduit and feeders to the transfer switch, the switch itself, the separate panel for chosen loads if the system is partial, controls and alarms, grounding, and a full load test. Each step is in the written scope, along with which trade carries it.
Placement comes first: clearances from openings and property lines, access for maintenance and fuel delivery, protection from vehicles, and drainage. A natural gas unit needs a gas line sized for its full load, which is a licensed plumber's work; a diesel unit needs a tank and a plan for refueling in a long outage. The concrete pad is often the general contractor's. The electrical work then ties it together, and the start-up proves the transfer, the load and the return to utility power before the owner takes it over.
Which permits and inspections apply in Austin?
The electrical work goes in under a City of Austin electric permit, either with the building project or as a stand-alone electrical permit, which only a registered trade contractor may apply for. The inspections follow the City's commercial sequence, booked through the AB+C Portal, ending with the 305 Final.
The City's commercial temporary inspection checklist dated October 2026 cites 2026 NEC articles, and Austin lists the 2026 edition as effective September 1, 2026, the same date TDLR adopted it for the state. Wattsmith Electric registers with the City of Austin before a permit is bought, as the City requires. The price is set at the free site visit, after we have seen the loads, the electrical room and where the generator can stand.
Sources: the City's stand-alone permit page, the commercial electrical inspections flowchart, the Building Inspections page and TDLR's 2026 NEC adoption notice. A generator often comes with service work, covered in our guide to a commercial panel upgrade in Austin, and it belongs on the schedule in what a commercial electrician handles in Austin.
See our Austin commercial generator installation page, the Austin commercial electrician hub and our commercial electrical services.