Key takeaways
- Commercial plans are submitted through the AB+C Portal and reviewed to the 2024 International Building Code; the review clock starts once the invoice is paid.
- The City quotes review times by type: Quick Turnaround 1 business day, Small Projects 5 business days, and 7 to 25 business days depending on the application.
- Austin Energy's ESPA is required by the City to obtain an electric permit, so it belongs in the preparation, not after it.
- Austin lists the 2026 NEC as effective September 1, 2026; the edition that counts is the one the permit is reviewed under.
- A clean set ties the one-line, the load calculation and the panel schedules to each other, so a reviewer can follow every number.
Austin electrical plan review is the part of the City's commercial plan review that looks at the electrical sheets before a permit is issued. The City of Austin Development Services Department runs it through the Austin Build + Connect (AB+C) Portal, reviews commercial construction to the 2024 International Building Code, and handles electrical code questions in their own appointment. This guide covers what the electrical side of a set shows, the review times as the City quotes them, where Austin Energy's paperwork fits, and how to prepare drawings that come back with fewer comments.
What is Austin electrical plan review?
It is the City's check of a commercial project's drawings before construction. The applicant creates an AB+C Portal account and submits a Commercial Plan Review Application through the Commercial Building Permit Web Form. Once the invoice is paid, the City says, the project is distributed for review and the review time starts.
The City's page does not list a separate electrical review discipline, so the electrical sheets travel as part of the commercial set. For electrical questions, the City offers a Commercial Electrical Codes appointment to ask general plan and code questions for compliance with the National Electrical Code. Questions about Austin Energy's Design Criteria go to Austin Energy instead, a split worth keeping in mind: the City reviews the building's wiring, and Austin Energy decides how its own service reaches the building.
Source: the City's commercial plan review page. The permit that follows is covered in how commercial electrical permits work in Austin.
What do the electrical sheets need to show?
Enough for someone who has never seen the building to follow the power from the utility to every load. In practice that means a one-line or riser diagram, a load calculation, panel schedules, power and lighting floor plans, the grounding and bonding, and the available fault current and equipment ratings at the service.
- One-line or riser diagram: service size and voltage, every panel and transformer, feeder sizes and overcurrent protection.
- Load calculation: the existing and new loads worked out under NEC Article 220, with the method named.
- Panel schedules: each circuit, its breaker, its load and the panel totals, matching the one-line.
- Floor plans: receptacles, lighting, equipment connections and circuit numbers.
- Service details: grounding electrode system, short circuit ratings and equipment working space under Article 110.
That list is general practice for commercial electrical drawings, not a City checklist. It also matches what the City's inspectors later look for in the field: the commercial temporary inspection checklist dated October 2026 asks that available fault current be posted under 2026 NEC Article 110.24, that ground fault protection be tested where required under 230.95(E), and that conductors be color coded per the City of Austin Electric Code. Drawings that already show those items make the inspection the same conversation as the review.
Source: the City's commercial temporary inspection checklist, linked from the Building Inspections page.
How long does plan review take in Austin?
The City quotes review times by project type: Quick Turnaround 1 business day, Small Projects 5 business days, New Construction up to 10,000 square feet 7 business days, and, depending on the application type, 7 to 25 business days. The clock starts when the invoice is paid and the project is distributed.
Those are review times, not permit dates. A set that comes back with comments goes through another round, and Austin Energy's design steps run on their own track. Austin Energy says the timeline to energization starts with the submission step and gives no fixed overall timeline, so a schedule that shows the City review and the utility design side by side is more honest than one finish date.
Which projects fall outside Quick Turnaround?
Projects that need complex system upgrades. The City says Quick Turnaround is not for work requiring large new electrical or gas services, and its EV Quick Turnaround excludes any job needing a new service or greater than 400 amps. Those go to the regular review for their application type.
In practice, a tenant finish that reuses the existing panel may fit the faster path, while one that adds a service, a switchboard or a large feeder will not. Knowing which side of that line a project sits on before submission keeps the schedule real. If the work grows mid-design, say because a kitchen or a bank of chargers is added, the review path can change with it.
Charger projects are covered in EV charging for Austin business, and service growth in our guide to a commercial panel upgrade in Austin.
Where does Austin Energy's ESPA fit into plan review?
Early. Austin Energy's Electric Service Planning Application, the ESPA, is needed for its design of power to new developments and for changes to existing services, and Austin Energy says the City's Development Services Department also requires the ESPA to obtain an electric permit. It states the connected load so Austin Energy can size its facilities.
For commercial, multifamily, mixed use and subdivision projects, Austin Energy asks for an AutoCAD drawing of the approved site plan, a riser diagram and an address verification form with the intake request. Services over 350 amps single phase or 225 amps three phase go through Austin Energy Design Intake, and loads over 320 amps continuous must move to CT metering. When the riser diagram in the City set and the one sent to Austin Energy are the same drawing, the two reviews stay in step.
Sources: Austin Energy's Design Criteria, sections 1.4.2.1 to 1.4.2.4 (effective December 12, 2023; Austin Energy notes some processes in it are not up to date), and its construction and renovation page.
Which code edition is the set reviewed under?
The one in force when the permit is reviewed. Austin's Building Technical Codes page lists the 2023 NEC and notes the 2026 edition is effective September 1, 2026, after the City Council approved an ordinance on April 23, 2026 adopting the 2026 NEC, Annex H and local amendments.
TDLR adopted the 2026 NEC as the state electrical code on the same date. We have not seen the final text of Austin's 2026 local amendments, so this guide does not describe them. A designer starting a set now should draw to the 2026 edition and confirm any local amendment with the City in a Commercial Electrical Codes appointment rather than carry over a detail from an older Austin set.
Sources: the City's Building Technical Codes page, the April 23, 2026 council action notes and TDLR's 2026 NEC adoption notice.
When is a stand-alone electrical permit enough?
When the electrical work is not tied to a building permit. The City's stand-alone electrical permit covers that kind of work, and only a registered trade contractor may apply. On a commercial or multifamily property, requesting more than one trade permit may bring the job into plan review.
The trade contractor named on the permit must have an AB+C Portal account, and the City requires a registration with current information before the application is submitted. Wattsmith Electric registers with the City of Austin before a permit is bought, as the City requires. Whichever path a job takes, inspections are scheduled through the AB+C Portal or by phone, and the contractor is the one who books them.
Sources: the City's stand-alone permit page and contractor registration page. The inspection order is in Austin electrical inspections.
How should a set be prepared before submission?
So every number can be traced. The one-line, the load calculation and the panel schedules should agree with each other, sheet by sheet, and with the riser Austin Energy receives. Existing conditions should be verified in the field, not copied from an older drawing, and every sheet should carry its issue date.
A short pre-submission pass catches most comments: confirm the service size and the utility's thresholds, check that each new load appears in the calculation and on a panel, mark spare capacity, show the fault current and ratings at the service, and note the code edition. For tenant work, the landlord's base building drawings and the panel the space is fed from belong in the package too.