Key takeaways
- Workplace, customer and fleet chargers have different use patterns, and the pattern sets how much capacity the site needs.
- A load study measures the existing service against the new charging load before anything is ordered.
- When the service has to grow, CenterPoint construction goes through its online Electric Service Request.
- Since September 1, 2026, Houston reviews permit applications to the 2026 NEC, and only a licensed, registered contractor can obtain the permit.
Commercial EV charger installation in Houston is an electrical service question before it is an equipment question. The chargers themselves are the easy part to choose. What decides the project is whether the building's service can carry them, whether CenterPoint Energy has to build, and how the new load lands on the demand line of the bill. This guide walks a Houston property owner, facility manager or fleet manager through those questions in the order they come up, with the official pages behind each Houston and CenterPoint step.
Which kind of commercial EV charger does your site need?
It depends on who parks and for how long. Workplace chargers serve cars parked through a shift, customer chargers serve short visits, and fleet chargers serve company vehicles that return on a schedule. Long dwell times suit Level 2 chargers, while short visits and tight fleet turnarounds may call for DC fast charging.
- Workplace: many cars, long dwell, often Level 2 shared across spaces.
- Customer: short visits, so charging speed matters more per space.
- Fleet: known vehicles, known return times and a known daily energy need.
Fleet sites are the easiest to plan because the energy each vehicle needs per day is known. Workplace and customer sites are planned from expected use, so they benefit most from a design that can add chargers later without reopening the service.
Our post on fleet EV charging in Houston goes deeper on fleet depots.
How does a load study decide what the service can carry?
A load study compares the building's existing demand with the capacity of its service and feeders, then adds the proposed chargers. The existing demand comes from a year of utility demand data or from a calculation under NEC Article 220. What remains is the room the chargers can use without a service change.
The study also looks past the main service. A distribution panel near the parking area may have less room than the service as a whole, and the feeder to it may need replacing even when the service does not. Doing the study before chargers are ordered keeps the equipment choice tied to what the building can actually deliver.
Interval data from the meter is the most useful input, because it shows when in the day the building already peaks. A building that peaks in the afternoon may have plenty of room overnight, which suits fleet charging, while a workplace site charges during the very hours the building is busiest. The study records both the size and the timing of the room left.
The study ends with a short written result: the existing peak, the capacity of the service and the panel that will feed the chargers, the charging load proposed, and whether that load fits as is, fits with managed charging, or needs a service change. That result is what the drawings, the permit application and any CenterPoint request are built on.
When must CenterPoint build for new chargers?
When the load study shows the service or the utility transformer must grow, CenterPoint has to do construction. CenterPoint says projects that need its construction, such as poles, wire or transformers, go through its online Electric Service Request, and a local service consultant reaches out within two business days.
CenterPoint's tariff lists what each construction request must include: a contact name and phone number, the ESI ID if one exists, the service address with directions and access notes, the construction requested, and the requested date. It also says CenterPoint does not guarantee the timeliness of starting or finishing construction, so the request should go in as soon as the study confirms it is needed.
CenterPoint's steps are on its service connect page, the ESR sits in its portal center, and the request rules are in its Tariff for Retail Delivery Service.
What does NEC Article 625 require?
NEC Article 625 covers electric vehicle power transfer equipment and its wiring. It treats EV charging as a continuous load when sizing branch circuits and feeders, sets rules for disconnecting means, ground-fault protection for personnel and equipment listing, and allows an energy management system to limit the total load the chargers draw.
The continuous load rule is why a charger circuit is sized larger than the charger's nameplate current alone would suggest. The energy management allowance is what makes managed charging part of the design rather than an afterthought, because the system's setting becomes the load the service has to carry.
Does a Houston EV charger installation need a city permit?
Yes, the electrical work is permitted. Houston's code says only a licensed and registered electrical contractor may obtain an electrical permit, applied for in iPermits. Since September 1, 2026, the city reviews permit applications submitted on or after that date to the 2026 National Electrical Code, which Texas adopted.
On a commercial site, the city inspects the work before it is covered and again at the final, and nothing is connected until the building official approves it. Where CenterPoint must connect new service, it waits for that approval at its Permit Desk. We register with the City of Houston before any Houston permit is bought, as the city requires.
The city's notice on the 2026 National Electrical Code and TDLR's 2026 NEC adoption set the edition. The permit rules are in the City of Houston Electrical Code.
How do chargers affect CenterPoint demand charges?
Most commercial accounts on secondary service over 10 kVA are billed per Billing kVA, which is the kVA supplied in the 15 minute period of maximum use in the month. Chargers that run during the building's busiest window add straight to that peak, even if they run only a short time.
For accounts over 700 kVA, transmission is billed on 4CP, the average demand at ERCOT's monthly peaks in June through September of the previous year. Fleet charging on summer afternoons can reach into that figure. Charging after the building's own peak, and outside those summer peak windows, keeps the chargers from setting either one.
What is managed charging, and when does it help?
Managed charging uses software or a load management system to cap the total power the chargers draw, share it between vehicles, or shift charging to hours when the building's own load is low. It helps whenever the service is close to full or the account is billed on its monthly peak.
For a fleet, managed charging can mean staggering start times after vehicles return. For a workplace, it can mean sharing a set amount of power across all spaces in use. In both cases the managed limit, set in the design, becomes the number the load study and the service are built around.
Why lay conduit for chargers you have not bought?
Trenching and coring are the parts of a charger project that disturb the site most. Laying spare conduit to future charger spaces while the ground is open, and leaving room in the panel, lets later chargers go in without cutting the parking lot again. Conduit laid in an open trench is far less work than a second dig.
The future spaces should be on the drawings and in the load study as well, even if the chargers are years away, so the service and the managed charging limit are chosen with them in mind. That keeps the first phase from boxing in the second. Each phase is priced at the free written estimate.
See our Houston EV and fleet charging, the Houston commercial electrician hub and our commercial electrical services. The demand rules here also shape commercial LED retrofit payback.