EV Charging for Fort Worth Businesses: Workplace and Customer Chargers

November 1, 2026Last updated 6 min readWattsmith Electric · TECL 41806

Key takeaways

  • Siting comes first: chargers go where drivers park and where the conduit run back to the panel stays short.
  • A load study on the existing service tells you how many chargers fit before Oncor has to build anything.
  • When the service must grow, the project starts with Oncor's online new construction request and its load form.
  • Oncor bills demand on the 15-minute peak of the month, so managed charging that caps the total protects the bill.
  • NEC Article 625 and a Fort Worth electrical permit to the 2026 NEC govern the install; buried conduit is inspected before backfill.

EV charging for a Fort Worth business usually means chargers for the people who park there: employees during the workday, or customers while they shop, eat or wait. That is a different design problem from a fleet depot. The cars come and go on their own schedule, the chargers sit in a public lot, and the power arrives in the middle of the business day, when the building is already busy. This guide covers where the chargers go, how a load study sets the count, when Oncor must grow the service, how demand billing works, and the code and permit rules.

Who uses workplace and customer chargers, and why does it matter?

Employees park for a full shift, so a slower charger reaches most cars by the end of the day. Customers park for an hour or less, so a customer charger has to deliver more in less time. Who parks, and for how long, sets the charger type before anything else is decided.

Most workplace stations are Level 2 chargers on 208 or 240 volt circuits, each sharing a modest amount of power across a long stay. A retail or restaurant lot may add a faster charger near the door so a short visit is worth plugging in for. Mixed sites are common: a row of Level 2 stations in the employee section and one or two higher output units by the entrance. Each choice moves the load on the building's service, so the plan starts with who will use the chargers and when.

Where should chargers go in a business parking lot?

Where drivers already park and where the run back to the electrical room stays short. Every foot of trench and conduit between the panel and the charger adds work, so the closest practical spaces to the service usually win. Lighting, cord reach, traffic flow and protection from vehicles finish the choice.

We walk the lot with a site plan and mark three things: the panel or switchboard that will feed the chargers, the spaces that make sense for drivers, and the path between them. A path across finished asphalt means saw cutting and patching; a path through a landscaped strip may not. Bollards or wheel stops keep bumpers off the pedestals. Planning conduit for future spaces while the trench is open costs little now and saves digging the same lot twice when the business adds chargers later.

What does a load study show before chargers are added?

How much room the existing service has left. We record the demand the building actually draws over a stretch of normal business days, add the chargers being considered, and check the service, the switchboard and the feeders against the total. The study turns the charger count from a guess into a number.

Timing is the hard part for workplace charging. A fleet charges at night when an office is quiet. Employee cars plug in at the start of the shift, which is when the lights, the air conditioning and the equipment are all coming up. The study looks at those morning and afternoon hours closely, using the load calculation methods in NEC Article 220 alongside the recorded demand. If the margin is thin, managed charging can keep the total under it.

When does Oncor have to grow the service for EV charging?

When the chargers need more than the existing service can give, even with managed charging. Oncor says a project that needs its construction, such as new poles, wire or transformers, starts with an online request. Its Commercial and Industrial Load Requirements form has a box for adding load to an electrically energized service.

After the request, Oncor assigns a Project Manager, who makes contact within two business days, and the requester follows the project in Oncor's Construction Portal. The load form asks for the contractor details, the service dates requested, the voltage and the loads, along with a site plan showing the proposed transformer and meter locations. Utility equipment can take months to arrive, so the Oncor request goes in as soon as the study shows it is needed. Most Fort Worth addresses are served by Oncor; some edge areas are co-op territory, where the co-op handles service growth under its own rules.

Sources: Oncor's new construction page, its Commercial and Industrial Load Requirements form, and the PUC's FAQ on municipal utilities and co-ops.

How does Oncor demand billing affect a business that adds chargers?

Chargers can raise the building's monthly peak, and the peak drives part of the delivery bill. On Oncor's Secondary Service Greater Than 10 kW schedule, the NCP kW is the demand supplied during the 15-minute period of maximum use in the billing month. Chargers running at the building's busiest hour add straight onto that peak.

Two more rules stretch a high month forward. For most loads over 20 kW, the distribution charge is billed on the higher of the current month's peak or 80% of the highest peak in the previous 11 months. A premise that has reached 700 kW is billed transmission on its 4CP kW, set by its demand at ERCOT's four summer system peaks of the previous year. Oncor's charges reach the business through its retail provider, and the PUC regulates the delivery rates, not the retailer's price.

Sources: Oncor's Tariff for Retail Delivery Service, Section 6.1.1.1.3, and the PUC's guide to understanding your bill.

What does managed charging do for workplace chargers?

It sets a ceiling on the power all the chargers draw together and shares it among the cars plugged in. When the building is busy, each car charges more slowly; when the building quiets down, they speed up. Drivers still leave with a useful charge, and the building's peak barely moves.

For an employee lot the trade is easy, because cars sit for hours and few drivers need a full battery by noon. The ceiling can follow the building's own load, rising when the air conditioning cycles off, or follow a schedule that backs off on summer afternoons. Networked chargers also let the business decide who may use them and whether drivers pay, which is a business decision made in the charger software, not in the wiring.

Which code and permit rules apply in Fort Worth?

NEC Article 625 governs the charging equipment, and a City of Fort Worth electrical permit covers the work. Article 625 treats charging as a continuous load, so circuits are sized at 125 percent of the charger rating, unless a listed load management system sets a lower limit the circuits are sized to.

The permit is applied for through Accela Citizen Access; where the job also needs a building permit, the city issues that one first. Fort Worth enforces the 2026 NEC on work started from September 1, 2026. Conduit buried across the lot is inspected as 205, Electrical Underground, after the trench is bedded and before backfill, and power to new equipment comes after the city's final and release. Oncor's tariff says it does not connect until the proper authority approves the installation.

Sources: the city's permits page, commercial permits page, What Inspections Do I Need? guide and building and energy codes page. The same trench work comes up in our guide to a parking lot LED retrofit in Fort Worth.

We build workplace and customer charging under Fort Worth EV charging. Charging for vehicle fleets is in our separate guide to fleet EV charging in Fort Worth on Oncor. See also the Fort Worth commercial electrician hub and our commercial electrical services. The price of a charging project is set after the free written estimate.

FAQ

Common questions

Straight answers. If you do not see yours, call us and ask.

Do workplace chargers need a new Oncor service?

Not always. A load study shows whether the existing service has room, and managed charging can keep the total under it. When it does not, the project starts with Oncor's online new construction request.

Will chargers raise our Oncor demand charges?

They can, if they run during the building's busiest 15 minutes of the month. Managed charging that caps the total keeps the peak close to where it was.

Is buried charger conduit inspected in Fort Worth?

Yes. Underground conduit is inspection 205, Electrical Underground, called after the trench is bedded and the conduit is in, before backfill.

Related help

Where to go from here

Ready to get it handled?

Flat-rate pricing quoted up front. Licensed and insured. A Wattsmith electrician calls you back within 15 minutes during business hours.

  • Licensed and Insured
  • BBB Accredited
  • Flat-Rate Pricing
  • Background-Checked
Call NowGet a Quote