Key takeaways
- Start with plans and load calculations; Houston's code asks for them with the permit application and may require an engineer's seal.
- The electrical permit can be bought only after the building permit is sold, so the build-out schedule hangs on the general contractor's permit.
- Drywall and ceiling grid wait on the wall cover and ceiling cover inspections.
- File the CenterPoint request early; CenterPoint connects only after the city's utility release, and the meter follows.
A tenant build-out in Houston has a fixed electrical path: plans, plan review, the building permit, the electrical permit, cover inspections, the final, the city's utility release and the CenterPoint meter. Miss a step and the suite waits, often with drywall up that has to come back down. This checklist breaks the electrical side of a Houston build-out into stages, for offices, medical suites, restaurants and retail bays, so a property manager, tenant or general contractor can see what has to be done before each stage can start. The city and CenterPoint steps come from their own pages.
What should be ready before a tenant build-out goes to plan review?
Electrical plans, panel schedules and load calculations should be ready before the set goes up through ProjectDox. Houston's code asks for plans, calculations and diagrams with each permit application, and the building official may require them prepared by a master electrician of record or sealed by a Texas professional engineer. Electrical is its own review discipline.
- The tenant's equipment list, with the electrical rating of each piece.
- Lighting and power plans for the suite.
- Panel schedules for the suite panel and any changes upstream.
- Load calculations showing the existing service and feeder can carry the new load.
- Any dedicated circuits the tenant's equipment needs, shown on the plans.
- An engineer lined up if the building official asks for a sealed set.
The load calculation is the item most worth doing first. If the building's existing service or the feeder to the suite cannot carry the tenant's load, the project picks up a service change and a CenterPoint request, and both are better known before the lease terms are final than after.
The plan rules are in Section 302.2 of the City of Houston Electrical Code, and the review process is in the Permitting Center's Commercial Permitting 101 presentation.
Which permits come first on a Houston build-out?
The building permit comes first. On a commercial job, licensed contractors can buy trade permits only after the building permit has been sold, so the electrical permit waits on the general contractor's permit. The electrical contractor's master electrician, licensed by TDLR and registered with the City of Houston, then buys it in iPermits.
- Building permit sold to the general contractor.
- Electrical permit bought by the registered master electrician.
- Temporary Cut-In permit added if the suite needs temporary power, bought after all other permits.
- The electrical contractor's city registration confirmed current before the permit is bought.
The full order is in how commercial electrical permits work in Houston.
What should be checked before drywall goes up?
Every wire, box and conduit that will be inside a wall must pass the wall cover inspection before drywall is hung. Houston's code says no wiring meant to be concealed may be concealed until it is inspected and approved. If any conduit runs under a slab or in a trench, the ditch or slab cover inspection comes even earlier.
- Ditch or slab cover inspection passed for any underground or in-slab conduit.
- Boxes set at the heights on the plans, with the right count per wall.
- Home runs and circuit numbers matching the panel schedule.
- Dedicated equipment circuits in place where the equipment will sit.
- Wall cover inspection called as soon as the area is ready, and passed before drywall.
Houston's code says the Electrical Inspections Section shall endeavor to inspect within three working days of a request. Build those days into the schedule between electrical rough and drywall, and have the electrical contractor call the inspection the day the area is ready.
What should be checked before the ceiling grid closes?
Everything above the ceiling: lighting circuits, emergency lighting and exit sign circuits, junction boxes, low voltage pathways and any equipment feeds that run overhead. The ceiling cover inspection must pass before the tiles go in. Inspectors look up through an open grid, so keep it open until the inspection is signed off.
- Fixture whips and lighting circuits complete and supported.
- Emergency lighting and exit signs on the circuits the plans show.
- Junction boxes accessible and covered.
- Ceiling cover inspection passed before tiles are set.
The city's Electrical Inspections page lists the ditch or slab cover, wall cover and ceiling cover inspections by name.
What changes for a medical suite?
Medical and dental suites usually carry more dedicated circuits, more receptacles per room and more equipment with specific electrical needs than a plain office, so the equipment list and the load calculation matter more. The plans should show every piece of medical equipment and the circuit that feeds it before the set goes to review.
Houston has a great many of these spaces. The Texas Medical Center describes itself as the largest medical complex in the world, with 54 million developed square feet, and clinics and medical offices fill buildings well beyond it. Equipment vendors often supply their own electrical requirements; get those sheets early, because a late change to an imaging or sterilization circuit can reopen plans that already passed review.
The figures are from TMC's own about page.
What changes for restaurants and retail bays?
Restaurants bring cooking, refrigeration and hood equipment, each with its own circuit and often its own disconnect, so the kitchen equipment schedule drives the electrical plans. Retail bays bring display lighting, signage and point of sale circuits. In both, the service size is the first thing to check, because these loads add up quickly.
- Restaurants: equipment schedule with the rating of every appliance, circuits for the hood and walk-in, and receptacles placed where the equipment will stand.
- Retail: display and track lighting, exterior sign circuit, point of sale and security circuits.
- Both: a check of the existing service and the suite meter before the lease is signed.
When should the CenterPoint meter request go in?
Early, if the suite needs its own meter or a service change. A commercial owner calls CenterPoint to have an ESI ID created and files an Electric Service Request if CenterPoint must build. CenterPoint does not guarantee construction timelines, and meters are usually set 3 to 5 business days from the requested date.
CenterPoint's tariff lists what each construction request carries: a contact name and phone number, the ESI ID if one exists, the address with directions and access, the work requested and the date wanted. Put it in while the walls are still open, not after the final.
CenterPoint's steps are in our guide to CenterPoint new commercial electric service and on CenterPoint's service connect page.
What has to happen at the final?
The final inspection is scheduled after all work is complete, and the code says nothing may be connected to power until the building official authorizes it. Electrical Inspections then performs the utility release, and CenterPoint connects only after that approval reaches its Permit Desk. Panel directories, labels and devices should all be finished first.
- Devices, covers and fixtures installed throughout.
- Panel directory filled in to match the circuits.
- Arc flash warning labels on the panels, as NEC 110.16 calls for.
- Final inspection called and passed.
- Utility release sent and the CenterPoint meter requested date confirmed.