Houston Temporary Power: Saw Poles, Cut-Ins and CenterPoint Service

November 1, 2026Last updated 6 min readWattsmith Electric · TECL 41806

Key takeaways

  • A Houston saw pole needs its own electrical permit, and the city's code sets its minimum build: a 60 ampere switch or breaker panel and a grounded receptacle on at least a solid four by four timber.
  • The Temporary Cut-In permit brings temporary service to a building under construction; the city lists it as valid for 180 days.
  • The code separately limits a permit for temporary use, a temporary connection, to 90 calendar days. The two are different things.
  • On commercial projects, temporary utilities come only after all permits are purchased, including the Temporary Cut-In.
  • CenterPoint is paid before it builds temporary facilities, and its 2023 Service Standards keep temporary meter poles out of the utility easement.

Houston temporary power on a construction job comes in two stages and needs two city permits, plus a request to CenterPoint Energy. The saw pole gives the framing crew power on day one. The Temporary Cut-In gives the building itself temporary service so the wiring can be checked before the permanent meter is set. For home builders and commercial builders alike, the order matters, because CenterPoint will not connect anything the city has not approved. This guide walks through each step as the City of Houston and CenterPoint describe it.

What is Houston temporary power on a construction job?

It is power for the site before the permanent service is energized. In Houston it usually starts with a temporary saw pole for the trades, under its own electrical permit, and moves to a Temporary Cut-In, the permit that lets a home or business under construction receive temporary electrical service from CenterPoint.

Both permits are electrical permits, so both are bought by a registered electrical contractor. On a commercial job the trade permits come after the building permit has been sold, and the electrical permit needs a master electrician licensed by the Texas Department of Licensing and Regulation and registered with the city. The city's inspection sequence for commercial work places the temporary cut-in between rough-in and the meter loop and final.

Source: the Houston Permitting Center's Commercial Permitting 101 presentation from BuildExpo 2025.

What does a Houston saw pole need?

A temporary saw pole needs its own electrical permit, applied for by a registered electrical contractor. Section 507 of the Houston code sets the minimum build: weatherproof materials, at least a 60 ampere switch or circuit breaker panel and a grounded receptacle, mounted on at least a solid four by four timber.

The same section says the service conductors are 6 AWG or larger, run in conduit. Those are minimums. A site with more tools running at once, or a larger crew, may need more than one receptacle or a larger panel, and the pole goes where the service drop can reach it and the trades can reach the pole. Building it to the code the first time keeps the inspection from becoming the thing that holds up framing.

Sources: the city's Temporary Saw Pole permit page and Section 507 of the City of Houston Electrical Code administrative provisions.

What is a Temporary Cut-In permit?

A Temporary Cut-In, or TCI, is the Houston electrical permit that lets a home or business receive temporary electrical service, and the city says it is often requested while a building is being built. Plan review and inspection are both listed as required, and the permit page lists a valid period of 180 days.

The cut-in is how a builder gets the building's own wiring energized before the final, so the trades can test circuits, start equipment and finish work that needs power. The temporary cut-in inspection is scheduled when temporary power is needed to check the wiring. Until the building official authorizes it, nothing is connected to the power source, and the city's release is what CenterPoint waits for.

Source: the city's Temporary Cut-In permit page.

How is the 90 day temporary use limit different from the cut-in permit?

They are two separate rules. The Temporary Cut-In permit page lists a valid period of 180 days. Separately, Section 306.2 of the Houston code says no permit for temporary use, meaning a temporary connection the building official authorizes for testing or for a temporary certificate of occupancy, is valid longer than 90 calendar days.

Keep the two apart on the schedule. The 180 days is how long the city lists the cut-in permit as valid. The 90 days is the code's limit on a permit for temporary use of the connection. A project that expects to run on temporary power for a long stretch should plan its dates around both, and confirm with the city how they apply to its permits rather than assume one covers the other.

When can a commercial project get temporary utilities?

Only after all permits are purchased. The Houston Permitting Center's commercial guidance says temporary utilities may be obtained after all permits are bought, and that a Temporary Cut In permit must be purchased. On a commercial job, the building permit is sold first and the trade permits follow it.

That order is the most common cause of a late temporary service. A general contractor who wants power on a set date needs the building permit sold, the electrical permit and the Temporary Cut-In bought, and the inspections lined up behind them. We buy the electrical permits as soon as the building permit allows, and file the CenterPoint side at the same time.

It helps to give the general contractor a short timeline at the start: the date the building permit is expected, the day the electrical and Temporary Cut-In permits can be bought after it, the inspection that has to pass, and the CenterPoint payment and request that run alongside. When one of those dates moves, everyone can see which of the later ones moves with it, and the site does not lose a week waiting on a step nobody was watching.

What does CenterPoint require for temporary service?

CenterPoint's tariff says the customer or the entity asking for temporary service pays CenterPoint before it builds the temporary facilities. Its 2023 Service Standards add that temporary service is installed at the customer's expense, that the customer provides a suitable location for the service drop and meter, and that temporary meter poles may not sit in the utility easement.

The Service Standards copy we could read is the 2023 revision, and a newer revision may exist, so confirm the current wording with CenterPoint before setting a pole near an easement line. CenterPoint also connects only after the proper authority's approval reaches its Permit Desk, so payment and the city release both have to be in place before temporary service goes live.

Sources: CenterPoint's Tariff for Retail Delivery Service, Section 5.7.7, and the 2023 Service Standards, Article 410.

Where can a temporary meter pole go in an underground subdivision?

In CenterPoint's underground residential areas, called URD, the 2023 Service Standards say temporary service for home construction is available only at designated locations next to existing energized transformers or energized secondary junction boxes. The builder or its contractor installs the temporary meter pole there, where CenterPoint allows it.

That means the pole location in a new subdivision is set by where the energized equipment is, not by where the lot's own service will end up. Underground residential subdivisions run through CenterPoint's Joint Trench portal, and larger underground work through its MUG portal. The same 2023 revision caution applies, so the current rule is confirmed with CenterPoint before the poles go in.

How do home builders get ESI IDs from CenterPoint?

CenterPoint asks home builders to request ESI ID numbers online, and multi-unit or apartment builders to email a request for multiple ESI IDs or call a dedicated line. Commercial business owners and commercial builders call CenterPoint to have an ESI ID created, and file an Electric Service Request when CenterPoint construction is needed.

The ESI ID is the number every later step refers to, so it is worth starting early. On new homes we get it moving at rough-in, so the meter is not what holds the closing. For Houston builders we wire new homes from the saw pole and the cut-in to the service entrance and the final. Service calls, repairs and remodels on existing homes stay in the San Antonio area only.

Source: CenterPoint's service connect page. The builder scope is on our Houston new construction electrician page, and the price is set after the free written estimate. Commercial builders who need permanent service next can read about fleet EV charging in Houston for the CenterPoint construction request. For our other Houston work, see the Houston commercial electrician hub, and for our work across Texas, our commercial electrical services.

FAQ

Common questions

Straight answers. If you do not see yours, call us and ask.

Does a saw pole in Houston need a permit?

Yes. A registered electrical contractor applies for an electrical permit for the temporary saw pole, and the city's code sets its minimum build.

How long is a Houston Temporary Cut-In permit valid?

The city's permit page lists a valid period of 180 days. Separately, the code limits a permit for temporary use of a connection to 90 calendar days.

Do you wire new homes for Houston builders?

Yes. For home builders in the Houston area we wire new homes, from temporary power to the final. Service calls, repairs and remodels on existing homes stay in the San Antonio area only.

Ready to get it handled?

Flat-rate pricing quoted up front. Licensed and insured. A Wattsmith electrician calls you back within 15 minutes during business hours.

  • Licensed and Insured
  • BBB Accredited
  • Flat-Rate Pricing
  • Background-Checked
Call NowGet a Quote