Skip to content
Wattsmith Electric

Commercial

Standby Generator Sizing for Houston Business: Starting From the Loads That Must Run

November 1, 2026Last updated 6 min readWattsmith Electric · TECL 41806

Key takeaways

  • Sizing starts from the loads that must run in an outage, listed with their running and starting demand.
  • Large motors such as chillers, pumps and compressors often set the size because of the current they draw when they start.
  • The NEC article that applies, 700, 701 or 702, depends on why the load must run, and it shapes the transfer switch and wiring.
  • CenterPoint has a Transfer Switch portal, Houston issues the electrical permit only to a licensed, registered contractor, and the price is set at the free site visit.

Standby generator sizing for a business is a list before it is a number. The size of the unit follows from what must keep running when the grid is down, how those loads start, and which part of the building the transfer switch carries. A Houston business has had recent reasons to make that list carefully. This guide explains how a commercial standby unit is sized from the loads up, what the transfer switch and the National Electrical Code decide, and where CenterPoint Energy and the city come in.

Why do Houston businesses size standby power around long outages?

Because recent outages lasted days for many. Hurricane Beryl came ashore near Matagorda on July 8, 2024, and CenterPoint reported more than 2.26 million customers out at the peak. Earlier that year, the May 16 derecho drove a swath of 100+ mph winds through the Houston metro, NWS reported.

CenterPoint had restored more than 770,000 customers, about 85% of those affected, by May 20, 2024, four days after the derecho. Winter Storm Uri in February 2021 was a different kind of event: ERCOT said that at its worst the storm took out 48.6% of the generation available to its grid. A line down and a statewide shortfall both end the same way at the meter, so a standby plan is sized for hours of running, not minutes.

The sources are the NWS Hurricane Beryl summary, CenterPoint's Beryl update, the NWS May 2024 climate summary, CenterPoint's derecho restoration update and ERCOT's Uri statement to Congress.

How do you list the loads that must run?

Walk the building with the people who run it and sort every load into must run, should run and can wait. For each must run load, record its running demand from the nameplate or measured current, and whether it is a motor. That list, not the size of the main service, sets the generator.

  • Life safety: egress lighting, fire alarm and any legally required systems.
  • Business critical: servers, refrigeration, point of sale, process equipment.
  • Building systems: pumps, some cooling, controls and security.
  • Comfort and convenience: loads that can wait until the grid returns.

A whole building unit and a partial one are both legitimate choices. Carrying only the must run list keeps the unit and the transfer switch smaller, while carrying everything removes the need to choose during an outage. The list makes that trade visible before any equipment is selected.

Running time belongs on the list as well. A unit sized for the must run loads also needs fuel for as long as the outage might last, and a long event changes the choice between natural gas and stored diesel or propane. How long each load must run, and how it will be fueled, is decided alongside the size.

Measured data improves the list. A year of demand readings from the utility bills, or a short period of logging on the panels the generator will carry, shows what those loads really draw at the busiest times. Nameplates tend to overstate running load, so measured figures keep the unit from being sized larger than the building needs.

Why does motor starting drive the size?

A motor draws several times its running current for a moment as it starts. A generator that carries the running load comfortably can still sag in voltage when a large chiller, pump or compressor starts, which can drop other loads off. So the largest motor, and how motors start together, often sets the size.

There are ways to manage it. Soft starters and variable frequency drives cut the starting current, and a transfer scheme can bring loads on in steps rather than all at once. Each choice changes the calculation, so the sizing and the starting plan are worked out together, using the manufacturer's sizing method for the unit under consideration.

What does the transfer switch decide?

The transfer switch decides which part of the building the generator carries and how it changes over. Placed at the service, it carries the whole building. Placed on a separate panel, it carries only the loads moved onto that panel. Its rating and its location follow directly from the load list.

Automatic switches start the generator and transfer on their own when utility power fails, then return when it is restored. Some sites use more than one switch so life safety and business loads change over separately. Whatever the arrangement, the switch is what keeps generator power from backfeeding the utility lines, which matters for the crews restoring them.

How do NEC Articles 700, 701 and 702 change the sizing?

The National Electrical Code sorts standby power by why it must run. Article 700 covers emergency systems for life safety, Article 701 covers legally required standby systems, and Article 702 covers optional standby, which protects the business rather than the occupants. The article that applies shapes wiring, switching and how loads are separated.

Emergency loads under Article 700 are kept separate from other wiring and must be carried first, so the generator is sized to pick them up quickly before anything else. Optional standby under Article 702 gives the owner more choice over what is carried. Many business sites have a mix, which is why the load list records why each load must run.

What does CenterPoint's Transfer Switch portal handle?

CenterPoint's portal center lists a Transfer Switch Portal for creating and viewing transfer switch requests, alongside its Electric Service Request portal for new or modified service. Where a standby installation involves CenterPoint, the contractor files through those portals, and CenterPoint connects changed installations only after the city's approval reaches its Permit Desk.

The portals are listed on CenterPoint's portal center, and the Permit Desk rule is on its service connect page.

Who permits a commercial standby installation in Houston?

The City of Houston does. Its code says only a licensed and registered electrical contractor may obtain an electrical permit, applied for in iPermits, and permit applications submitted on or after September 1, 2026 are reviewed to the 2026 NEC. Nothing is connected to power until the building official approves it.

Concealed wiring is inspected before it is covered, and a final inspection follows completion. On a commercial standby job the generator pad, the conduit to the transfer switch and the switch itself are all part of that inspected work. We register with the City of Houston before any Houston permit is bought, as the city requires.

The permit rules are in the City of Houston Electrical Code, and the edition is in the city's notice on the 2026 National Electrical Code.

How is the price for a standby system set?

The price is set at the free site visit. The load list, the motor starting plan, the transfer switch location, the generator placement and the fuel source all change the work, so the price comes from the visit and the written estimate that follows, not from a table of sizes.

Bring a year of utility bills and any equipment lists to the visit. The bills show the building's real demand peaks, which helps check the load list, and the equipment lists save time finding nameplates. If you plan to add load later, say so then, so the unit and switch can be chosen with room for it.

See our Houston commercial standby generators, the Houston commercial electrician hub and our commercial electrical services. A commercial electrical contractor in Houston should pass the checks in that post before you sign.

FAQ

Common questions

Straight answers. If you do not see yours, call us and ask.

Should a business generator be sized to the main service?

Not necessarily. Sizing starts from the loads that must run in an outage and how their motors start. A partial system that carries only those loads is a common choice.

Which NEC article applies to a business standby generator?

It depends on why the load must run: Article 700 for emergency life safety systems, Article 701 for legally required standby, and Article 702 for optional standby.

How do I get a price for a standby generator in Houston?

The price is set at the free site visit, from the load list, the transfer switch location, the generator placement and the fuel source.

Ready to get it handled?

Flat-rate pricing quoted up front. Licensed and insured. A Wattsmith electrician calls you back within 15 minutes during business hours.

  • Licensed and Insured
  • BBB Accredited
  • Flat-Rate Pricing
  • Background-Checked
Call NowGet a Quote