Key takeaways
- A lighting audit counts every fixture, its wattage, its hours and its controls, room by room, before any new fixture is chosen.
- Oncor bills most commercial meters on NCP kW, the highest 15-minute demand of the month.
- Most loads over 20 kW carry Oncor's 80% ratchet: the higher of this month's peak or 80% of the highest peak in the prior 11 months.
- A premise that has reached 700 kW is billed transmission on its 4CP kW, set by four summer ERCOT peaks.
- Controls decide when the lights run; the fixtures decide how much they draw while they do.
A lighting retrofit in a Dallas building replaces old fixtures or lamps with LED and, done well, adds controls that decide when the light runs. Offices, warehouses, stores and parking lots each light for different hours and different tasks, so the work starts with a lighting audit, not a catalog. The audit also feeds the electric bill: Oncor bills most commercial meters on their highest 15-minute demand, and lighting that runs through the peak hours sets part of that number. This guide covers the audit, how each building type differs, how Oncor bills demand, which controls matter, and the City of Dallas permit.
What does a lighting audit count?
Every fixture, room by room: its type, its lamp and wattage, how many hours a day it runs, what switches or sensors control it, and what task it lights. The audit also records the ceiling height, the mounting and the circuits, because those decide which replacement fits and whether the wiring can stay.
An audit done properly is a spreadsheet you can read. Each line is a fixture group with its count, its present wattage and the hours it burns. From that the energy each group uses is a multiplication, and the same lines show which fixtures run during the afternoon peak and which only at night. Nobody can work out what a retrofit changes on the bill without these lines, and nobody should guess at them: the hours come from the people who run the building, or from logging the circuits.
The audit also turns up problems a fixture swap would hide. Failing ballasts, overloaded lighting circuits, fixtures fed from the wrong panel and emergency fixtures that no longer hold a charge all show up on the walk. Each one is noted on the same sheet, so the retrofit scope can say plainly which items are part of the job and which are left for a later decision.
How do offices, warehouses, retail and parking differ?
By hours, height and task. Offices light open floors and private rooms for a working day and often sit half empty. Warehouses light tall aisles for shifts that may run all night. Stores light merchandise for long hours with display lighting on top. Parking lots and garages run from dusk to dawn, and garages often run all day.
Those differences change the design. In an office, occupancy sensors and daylight controls near windows do much of the work. In a warehouse, high-bay fixtures with sensors in each aisle let the lights follow the forklifts. Retail cares about color as much as light level, so fixture choice is about how the goods look. Outdoor lots need even light without glare onto neighbors, and a garage needs fixtures that hold up to exhaust and weather. One retrofit design rarely suits all four.
How does Oncor bill demand on a commercial meter?
On kW. A secondary voltage service with demand greater than 10 kW falls on Oncor's Secondary Service Greater Than 10 kW schedule, where NCP kW is the demand supplied during the 15-minute period of maximum use in the billing month. That one peak, not the monthly total, drives the demand part of the delivery charges.
A premise placed on that schedule stays on it until it completes 12 consecutive billing months with no recorded demand greater than 10 kW. Oncor's delivery charges reach the customer through the retail provider, and the Public Utility Commission notes that it regulates the delivery utility's rates but not the retailer's price. So a lighting retrofit moves two things on the bill: the energy the retail provider sells, and the demand Oncor measures.
Sources: Oncor's Tariff for Retail Delivery Service, Sheet 1.3, Section 6.1.1.1.3, and the PUC guide to understanding your bill.
What is the ratchet, and why does it matter for lighting?
The ratchet carries a high peak forward. For most loads over 20 kW, Oncor bills the distribution charge on the higher of this month's NCP kW or 80% of the highest monthly NCP kW in the previous 11 months. One summer afternoon peak can set the floor for the year that follows.
The tariff names an exception: loads whose highest NCP kW in the prior 11 months is over 20 kW and whose annual load factor is 25% or less are billed on the current month. Loads at 20 kW or less are billed on the current month too. For everyone else, lighting that runs at full output through the hottest afternoon adds to the peak that the ratchet then holds. Lower fixture wattage lowers that contribution every hour the lights run, including the hour that sets the peak. We work out the effect from your own interval data and the audit, never from a rule of thumb.
When does 4CP apply to a Dallas building?
When the premise has established an NCP kW of at least 700 kW in any previous billing month. Oncor then bills transmission on its 4CP kW: the average of its 15-minute demand at the moment of ERCOT's system peak in each of June, July, August and September of the previous year.
The 4CP figure is updated each January 1 and stays fixed for the calendar year. That puts weight on four summer moments nobody knows in advance. Large buildings that can see a likely ERCOT peak coming sometimes cut load in those hours, and lighting is one of the easier loads to dim. A retrofit with controls that can take a signal gives a building that option; one without controls does not.
Source: Oncor's Tariff for Retail Delivery Service, the Secondary Service Greater Than 10 kW schedule and Rider TCRF. Our guide to Oncor demand charges and LED retrofits goes further into the billing.
Which controls belong in a lighting retrofit?
The ones that match how the space is used. Occupancy and vacancy sensors turn lights off in empty rooms and aisles. Daylight sensors dim fixtures near windows and skylights. Time schedules handle store hours and parking. Dimming lets a building trim output during a peak without turning anything off.
Controls are where retrofits most often fall short. A fixture swap with the old wall switches left in place runs the new lights for exactly the hours the old ones ran. Sensors need placing where they see people, not shelves, and their timeouts need setting to how the space is used. Parking controls need a photocell or an astronomical clock so they follow the season. We set them up on site and leave a written schedule of what each zone does, so the next person can change it.
Does a lighting retrofit need a Dallas electrical permit?
Electrical work on commercial property in Dallas requires a registered electrical contractor and a permit. When electrical plans are submitted, the city's checklist asks for the floor plan power and lighting layout among its required items. Applications and inspection requests go through DallasNow, with inspections booked at least 24 hours ahead.
The work is held to Chapter 56, the Dallas Electrical Code, which Ordinance 33081 amended to adopt the 2023 National Electrical Code with local amendments, effective May 23, 2025. We register with the City of Dallas before a permit is bought, as the city requires, and schedule the retrofit around business hours so floors stay open while crews move through them in sections.
Sources: the city's Electrical Permit Application Checklist, Chapter 56 as amended by Ordinance 33081 and the DallasNow page.
We do Dallas LED lighting retrofits from the audit through the controls. If chargers are next on the list, our guide to EV charging for Dallas properties covers the same demand rules from the other side. See also the Dallas commercial electrician hub and our commercial electrical services. The price is set after the free written estimate.