EV Charging for Dallas Properties: Offices, Retail and Multifamily

November 1, 2026Last updated 6 min readWattsmith Electric · TECL 41806

Key takeaways

  • A load study comes first: what the service already carries, and what is left for chargers.
  • Dallas's Chapter 56 amendments require load calculations when loads are added, and chargers are added load.
  • When service must grow and Oncor has to build, the project starts with Oncor's online new construction request and its Construction Portal.
  • NEC Article 625 covers the charging equipment and its wiring.
  • Managed charging spreads the load so the chargers do not set a new 15-minute peak.

EV charging at a Dallas property starts with the electrical service, not the charger catalog. An office garage, a shopping center lot and an apartment community each need different numbers of ports, charge for different hours and sit on services with different room to spare. The first step is a load study that shows what the service can carry. If it is not enough, Oncor may have to build more, and that changes the schedule. This guide covers each property type, the load study, Oncor's new construction request, NEC Article 625, managed charging and demand, and the City of Dallas permit under Chapter 56.

What does EV charging look like at offices, retail and multifamily?

Each property charges on its own clock. Office chargers fill during the working day while cars sit for hours. Retail chargers serve short visits, so speed matters more than port count. Multifamily chargers run overnight, when residents come home, and need fair sharing among many parked cars on one service.

Those patterns decide the equipment. An office can often meet its need with slower chargers spread over many spaces, because each car has all day. A store or restaurant that wants drivers to stop may choose fewer, faster units near the door. A multifamily property usually needs a plan for growth: conduit to more spaces than get chargers on day one, so later ports are a wiring job rather than a trench through the parking lot. The property type also shapes who pays for charging and how access is controlled, which the charger software handles.

Why does a load study come first?

Because chargers are continuous loads, and the service has a limit. A load study measures what the building actually draws over time, sets it against what the service and panels can carry, and shows how many chargers fit. Dallas's Chapter 56 amendments also require calculations when loads are added.

The city's letter to contractors lists that amendment, numbered 13 and tied to NEC Article 220, among the items that bear special attention. In practice the study uses a year of demand data where the meter has it, or a recording period where it does not, and follows the method Article 220 sets out. The result is a number: the capacity left after the building's own peak. Chargers that fit inside it go in on the existing service; chargers that do not need either managed charging or more service.

Sources: the city's letter to contractors on the 2023 NEC and Chapter 56 as amended by Ordinance 33081.

When does the service need to grow, and how does Oncor handle it?

When the chargers need more than the study shows is left. Oncor says a project that needs its construction, such as new poles, wire or transformers, starts with an online request. Its commercial load form has a box for adding load to an electrically energized service, alongside the one for new load.

After the request, Oncor asks the requester to create a Construction Portal account with the same email, to track the project. A Project Manager is assigned and makes contact within two business days. The load form asks for the contractors, service dates, meters and amps, voltage and the loads, and a site plan showing where the transformer, meter and other Oncor equipment will go. Transformers and other equipment can take months to arrive, so the request goes in as soon as the study says the service must grow.

Sources: Oncor's new construction page, its commercial new service request and its Commercial and Industrial Load Requirements form.

What does Oncor need before it can build?

Plans, payment and easements. Oncor's Customer Checklist asks for civil and electrical plans, including the site plan, riser diagram and panel schedule, and one load form for each voltage and phase type. It cannot schedule construction until contracts and payments are received and the original easement documents are signed.

The checklist adds that the customer's civil work must be approved by an Oncor inspector and the site brought within about 3 inches of final grade. For an existing parking lot that may mean trenching and conduit work before Oncor arrives. A property on leased land should raise the easement with the owner early, because Oncor needs it recorded by plat or by separate instrument. When a new meter is involved, Oncor provides an ESI ID and the customer chooses a retail provider before the meter is set.

Source: Oncor's Customer Checklist.

What does NEC Article 625 cover?

The electric vehicle charging equipment and the wiring that serves it. Article 625 sets how the equipment is listed, how its branch circuits are sized as continuous loads, where disconnects go, how cords and connectors are protected, and when ventilation matters indoors. It is the article the plan reviewer and the inspector read the charger design against.

Article 625 also allows an energy management system to limit what the chargers draw, and the load calculation can then use that limit instead of the full nameplate of every charger. That is the code side of managed charging. For parking structures, the location of the equipment, its protection from vehicles and the routing of conduit through a garage all go into the drawings the city reviews.

Outdoors, the work is mostly underground. Conduit runs from the panel or a new distribution point to each charger pedestal, under paving or along curbs, and the trench route is planned to avoid other utilities and to leave room for later ports. Each pedestal needs a base, protection from bumpers where cars pull in, and clear space for cords so they do not lie across a walkway.

How does managed charging affect Oncor demand?

It keeps the chargers from setting a new peak. Oncor bills most commercial meters on NCP kW, the demand during the 15-minute period of maximum use in the month. Managed charging shares a fixed limit among the cars plugged in, so ten chargers can run on the power of a few.

The peak carries forward. For most loads over 20 kW, Oncor bills the distribution charge on the higher of this month's peak or 80% of the highest peak in the prior 11 months. A premise that has reached 700 kW is billed transmission on its 4CP kW, set by its demand during four summer ERCOT peaks. At an office, chargers filling at midday add to the building's own afternoon peak; managed charging can hold them back in those hours. At multifamily, overnight charging falls when the building is quiet, which is often why the service has room for it.

Source: Oncor's Tariff for Retail Delivery Service, the Secondary Service Greater Than 10 kW schedule and Rider TCRF.

What permit does EV charging need in Dallas?

A City of Dallas electrical permit. Electrical work on commercial property needs a registered electrical contractor and a permit, applied for through DallasNow. The work is held to Chapter 56, which Ordinance 33081 amended to adopt the 2023 National Electrical Code with local amendments, effective May 23, 2025.

Commercial electrical plan review checks the one-line diagram, the load calculations, conductor sizing, overcurrent protection and grounding. Inspections are booked through DallasNow at least 24 hours ahead, and Oncor connects new service only after it hears the city approved the installation. We register with the City of Dallas before a permit is bought, as the city requires.

Sources: the city's Electrical Permit Application Checklist and the 2025 to 2026 Development Guide. The permit steps are in our guide to how commercial electrical permits work in Dallas.

We install Dallas EV and fleet charging. If the lighting is due too, our guide to lighting retrofits for Dallas buildings shows how both loads meet on the same demand bill. See also the Dallas commercial electrician hub and our commercial electrical services. The price is set after the free written estimate.

FAQ

Common questions

Straight answers. If you do not see yours, call us and ask.

Do EV chargers need a load calculation in Dallas?

Yes. Dallas's Chapter 56 amendments require calculations when loads are added, and the city's letter to contractors lists that item among those that bear special attention.

What happens if the existing service is too small for the chargers?

Either managed charging keeps the chargers inside what is left, or the service grows. If Oncor has to build, the project starts with its online new construction request.

What does EV charging installation cost at a Dallas property?

It depends on the load study, the number and type of chargers, the trenching and whether Oncor must build. The price is set after the free written estimate.

Related help

Where to go from here

Ready to get it handled?