Key takeaways
- A load study compares the building's recorded peak demand plus the chargers at their continuous rating with the service rating.
- When service must grow, CPS Energy's Commercial Building Application goes in with a load sheet, sealed site plan, one-line diagram and site plan with easements.
- CPS Energy treats a diversified load of 300 kVA or more as Large Commercial, served from a pad-mounted transformer.
- CPS Energy bills demand from the highest 15 minute kW of the month, with a winter ratchet on the prior summer peak.
- Fleet charging is permitted through the City's BuildSA portal, and the price is set after the free written estimate.
Fleet EV charging in San Antonio starts with one question: can the building's existing service carry the chargers, or does CPS Energy need to supply more power? The answer sets the schedule. A depot that fits inside its current service needs a City permit and an electrician. One that does not needs CPS Energy's commercial application, a utility design and possibly a new transformer before the first vehicle charges. This guide walks a fleet owner through the load study, CPS Energy's process when service has to grow, how CPS Energy structures demand billing, and what NEC Article 625 and the City's BuildSA permit require.
How do you know if the existing service can carry fleet chargers?
A load study answers it. The study takes the building's recorded peak demand, or a load calculation under NEC Article 220 where records are thin, adds the chargers at their continuous rating, and compares the total with the service rating. If the total fits with margin, the chargers can go on the existing service.
Twelve months of demand history is the best input, since it shows the summer peak and the hour it lands. CPS Energy bills commercial demand from a meter that records the highest 15 minute period each month, so that history usually exists. A fleet that charges overnight often fits beside a building whose peak falls in the afternoon, because the two loads do not stack. Where the numbers are close, an energy management system that shares capacity across several chargers can hold the total under the service's limit.
What does NEC Article 625 require for EV chargers?
Article 625 governs electric vehicle power transfer equipment. It treats charging as a continuous load, so the branch circuit and its protection are sized at 125 percent of the charger's rating. It also requires listed equipment, sets disconnect rules for larger chargers, and calls for ground-fault protection on receptacles that serve EV charging.
The article also allows the load on a circuit to be set by an energy management system or by the charger's adjustable setting, rather than the nameplate maximum, which is how many depots fit more chargers on the same feeder. Outdoor pedestals need equipment rated for wet locations and protection from vehicle damage, and the conduit to them is trenched under the parking surface. Texas adopted the 2026 NEC as the state electrical code effective September 1, 2026, and San Antonio adopts the National Electrical Code with its own local amendments in Chapter 10.
State code source: TDLR's 2026 NEC adoption notice.
When does a fleet need more service from CPS Energy?
When the load study shows the chargers would push the building past its service rating. The owner then applies through CPS Energy's Construction and Renovation Web Portal with a Commercial Building Application, and a CPS Energy designer works out how the added load will be served. For a commercial renovation, a designer typically makes contact within two business days.
The application carries the attachments CPS Energy lists in its step by step document: a load sheet, signed and sealed if the design drawings are not yet at 100%; a signed and sealed utility site plan; a meter loop drawing where the Service Standards require one; a signed and sealed one-line diagram; and a site plan with easements identified. An owner authorizes a contractor to register for the project with CPS Energy's Web Authorization Form. CPS Energy also offers a free, optional Utility Preliminary Plan Review meeting before a full application, to flag items that need changing before the request goes in.
On a new commercial service, CPS Energy describes the steps after that: a designer holds a pre-design meeting, and at the end of design CPS Energy provides the final design, a contract and an invoice. The customer installs the infrastructure to CPS Energy's design. For an existing service being upgraded, the Service Standards route the request by size, with separate contacts for services above and below 300 kVA.
Sources: CPS Energy's New Commercial Construction step by step document, its commercial renovation page and its Electric Service Standards.
What is the 300 kVA split?
It is where CPS Energy changes how it serves a commercial customer. CPS Energy designates a diversified load under 300 kVA as Small Commercial, typically served from overhead transformers, and a diversified load of 300 kVA or more as Large Commercial, served from a pad-mounted transformer. A large charging depot can move a site across that line.
Crossing it changes the site work. A pad-mounted transformer needs a slab and a duct bank built by the customer to CPS Energy's design, and CPS Energy inspects both before concrete is poured. Easements may be needed too, and CPS Energy's new commercial construction page says easement review can take up to 3 weeks. Knowing early which side of 300 kVA a fleet lands on keeps the transformer from becoming the last item on the schedule.
Sources: CPS Energy's step by step document and its new commercial construction page.
How does CPS Energy bill demand for a commercial building?
By the highest 15 minute kW reading of the month, with a winter ratchet. On CPS Energy's base commercial rate, General Service PL, billing demand from October through May is the month's demand or 80% of the highest demand set the previous summer, June through September, whichever is greater.
The PL rate has no per-kW demand charge. Instead, billing demand enlarges the block of energy billed at the first price and sets the minimum bill, and a power factor below 85% lagging can raise billing demand. Larger customers fall under Large Lighting and Power, LLP, which bills a per-kW demand charge with separate summer and non-summer prices, a 100 kW billing floor and the same kind of 80% ratchet on the prior summer peak. Extra Large Power, ELP, applies when monthly load is greater than 1,000 kW.
For a fleet, the structure points to charging timing. A depot that charges every vehicle at once at shift change sets a new 15 minute peak, and if that peak lands in summer, the ratchet carries 80% of it through the following winter. Spreading charging across the night with managed chargers keeps the peak down. We describe the structure only; CPS Energy's current rate sheets set the prices.
Sources: CPS Energy's General Service PL rate sheet, its LLP rate sheet, its ELP rate sheet and its rates page.
How is fleet EV charging permitted in San Antonio?
Through the City's BuildSA portal. The Development Services Department requires all commercial applications to be submitted online there, and its electrical permit application carries the BuildSA name. Wattsmith registers with the City before a permit is bought, as the City requires, since trade permits go only to licensed contractors registered with the department.
The application asks whether the job crosses the City's engineer's seal thresholds: equipment over 600 amps at 250 volts or less, or over 400 amps above 250 volts, any system over 600 volts, or a work area on more than one floor or over 5,000 square feet. A large depot often does, and then sealed drawings go with the permit. Underground conduit is inspected before the trench is backfilled, rough-in before walls close, and the final after the chargers are set and tested. Inspections are scheduled in the BuildSA portal or by calling the Development Services Department at 210-207-1111.
Sources: the City's Commercial Project Application Guide, its electrical permit application and its commercial permit process page.
What does a fleet charging estimate from Wattsmith cover?
Everything between the service and the charger. The written estimate names the load study result, any service work, the feeders and panels, the circuits to each charger, the trenching and pedestals, the permit and inspections, and the CPS Energy coordination. The price is set after the free written estimate, once the load study is done.
The owner chooses the charger make and its network service, and we size and wire the circuits to its listing and installation instructions. Wattsmith Electric is a veteran-owned contractor working under Texas electrical contractor license TECL 41806, and fleet depots and workplace charging are part of our commercial work in San Antonio.
See our EV fleet charging services and all of our commercial electrical services. When a larger service needs the City's sign-off, the steps are in the Release to CPS for commercial buildings, and depots with heavy loads are covered in industrial electrical work at Port San Antonio.