Fleet EV Charging in Austin: Load, Service and Austin Energy

November 1, 2026Last updated 5 min readWattsmith Electric · TECL 41806

Key takeaways

  • A fleet charging load is sized from each vehicle's daily energy and its dwell time at the depot, not from the charger catalog.
  • Services over 350 amps single-phase or 225 amps three-phase go through Austin Energy Design Intake, and loads over 320 amps continuous move to CT metering.
  • The ESPA must list the total undiversified connected load so Austin Energy can size its facilities; the City needs the ESPA to issue the electric permit.
  • Austin Energy bills commercial demand on the 15-minute interval of greatest use, adjusted when power factor is under 90 percent.
  • Austin Energy schedules the connection only after ESPA approval, the City permit, completed work, passed inspections and an account.

Fleet EV charging in Austin starts with a load study and ends with Austin Energy energizing a service big enough for the chargers. Between those two points sit an Electric Service Planning Application when the service changes, a City of Austin electric permit, and a demand bill that climbs with every charger running at the same moment. This guide covers how a depot charging job is sized, when Austin Energy's design intake applies, how its commercial demand charge is built, and which part of the National Electrical Code the chargers are installed under.

How is a fleet charging load sized?

From the fleet's duty cycle, not the charger catalog. A load study lists each vehicle, the energy it uses on a shift, the hours it sits at the depot, and the charger power that refills it within that window. The total, with any managed charging applied, is the new load the service has to carry.

The existing service is measured the same way. A recording meter on the main service over a normal operating period shows what the building already draws and when, and an NEC Article 220 calculation sets that against the service rating. Depot charging usually lands at night, when the rest of the building is quiet, which the recording shows plainly. The study also plans for growth: conduit and pull boxes for the chargers the fleet will add later are far easier to place now than after the paving is finished.

When does Austin Energy's design intake apply?

When the service grows past set sizes. Austin Energy's Design Criteria sends services over 350 amps single-phase or 225 amps three-phase outside the Downtown Network, every Downtown Network project, and any job needing an Austin Energy design through Design Intake. Smaller service-only jobs take a simpler ESPA review instead.

One more line matters for chargers. The Design Criteria notes that if the load is more than 320 amps continuous, the service must be upgraded to instrument-rated CT service and go through the Design Intake process. A row of chargers running through the night is continuous load almost by definition, so that threshold comes up early in depot work. The intake request is made in the City's AB+C Portal with an ESPA for every address, an AutoCAD site plan, a riser diagram and an address verification report.

Sources: Austin Energy's Design Criteria, sections 1.4.2.1 to 1.4.2.4, and its construction and renovation page.

What does the ESPA ask for on a charging project?

The connected load. Austin Energy's Design Criteria says the ESPA must state the total undiversified connected demand load for each equipment item or load category, so Austin Energy can size its service facilities. The City of Austin's Development Services Department also requires the ESPA before it issues the electric permit.

On a charging job the chargers are listed at full rating, even when the software will hold them lower, because the form asks for undiversified load. Austin Energy also requires approval of the service equipment by its Distribution Metering Operation unit before the equipment is purchased. It gives no fixed timeline, says the timeline to energization starts at submission, and tells customers to order metering equipment as soon as possible because supply chain delays can slow a project. We submit the ESPA and the metering approval at the start, not after the drawings are final.

How does Austin Energy bill demand at a charging depot?

On the busiest 15 minutes of the month. Austin Energy's FY2027 tariff bills commercial demand as the metered kilowatts in the 15-minute interval of greatest use in the billing month, adjusted when power factor in that interval falls below 90 percent. The rate class comes from the average of June through September demand.

Secondary-voltage commercial customers fall into three classes by that summer average: under 10 kW, which carries no demand charge, 10 kW to under 300 kW, and 300 kW and up. Austin Energy is a department of the City and is not part of retail deregulation, so a business in its territory buys its power from Austin Energy under this tariff. For a depot, the shape matters more than the size. A whole fleet plugged in at once when it returns sets one peak; the same energy spread across the night sets a much lower one. We describe the structure only; the tariff sets the rates.

Sources: the City of Austin FY2027 Electric Tariff and Austin Energy's statewide grid page. The demand structure for lighting and other loads is covered in Austin Energy demand charges and LED retrofits.

Can managed charging keep the service smaller?

Often it can. A load management system caps the total power the chargers draw at one time and shares it among the vehicles plugged in. The National Electrical Code lets an energy management system set the load used in the calculation, which can keep a project under the size that triggers new service equipment.

The trade is time. Capped chargers take longer to fill each vehicle, so the duty cycle in the load study decides how low the cap can go before trucks leave short of charge. Managed charging also flattens the 15-minute peak the tariff bills on. The ESPA still lists the full undiversified load, and Austin Energy sizes its side from that.

Which code and permit apply to fleet chargers in Austin?

The City of Austin lists the 2026 National Electrical Code as effective September 1, 2026, the date TDLR made it the state electrical code. Chargers are installed under NEC Article 625, and the work needs a City of Austin electric permit, applied for in the AB+C Portal by a registered trade contractor.

Article 625 treats charging as a continuous load, so the circuits and overcurrent protection are sized above the charger's rating, and it sets rules for disconnects and for equipment outdoors. The City's EV Quick Turnaround review excludes jobs needing a new service or over 400 amps, so a depot of any size takes standard review. On a commercial property, plan review may also be needed when more than one trade permit is requested. Wattsmith registers with the City before a permit is bought, as the City requires.

Sources: the City's Building Technical Codes page, its commercial plan review page, its stand-alone permit page and TDLR's 2026 NEC adoption.

What happens between the permit and energizing?

Austin Energy's Design Criteria lists five things before it schedules the connection: an approved ESPA, a City electric permit and other required permits, work completed to Austin Energy's design and metering requirements, all required inspections passed, and service applied for with an account set up. The City's inspections come before Austin Energy energizes.

On a CT-metered service, Austin Energy's own CT inspection must pass before the City's 305 Final is called, and Austin Energy wants notice of the City's passed electrical inspection three regular working days before it energizes. Booking the CT inspection ahead of the final keeps the two from waiting on each other.

Each City inspection is set out in our guide to Austin electrical inspections. We build depot and workplace charging as Austin commercial EV charger installation, and customer and workplace chargers are covered in EV charging for Austin business. See also the Austin commercial electrician hub and our commercial electrical services. The price of the work is set after the free written estimate. Source for the CT step: Austin Energy's instrument rated metering guidelines.

FAQ

Common questions

Straight answers. If you do not see yours, call us and ask.

Does a fleet charging depot in Austin need an ESPA?

When the electric service is new or changes, yes. Austin Energy requires the ESPA for its design, and the City's Development Services Department requires it to issue the electric permit.

How does Austin Energy measure demand for a charging depot?

As the metered kilowatts in the 15-minute interval of greatest use in the billing month, adjusted when power factor in that interval is below 90 percent.

Which NEC article covers EV chargers?

Article 625 of the National Electrical Code. The City of Austin lists the 2026 edition as effective September 1, 2026, the same date it became the Texas state code.

Ready to get it handled?

Flat-rate pricing quoted up front. Licensed and insured. A Wattsmith electrician calls you back within 15 minutes during business hours.

  • Licensed and Insured
  • BBB Accredited
  • Flat-Rate Pricing
  • Background-Checked
Call NowGet a Quote