Fleet EV Charging in Fort Worth: Oncor Service, Demand and Permits

November 1, 2026Last updated 7 min readWattsmith Electric · TECL 41806

Key takeaways

  • Start with a load study: what the existing service already carries, and what is left for chargers.
  • When the project needs new poles, wire or transformers, it starts with Oncor's online new construction request and its Construction Portal.
  • Oncor bills demand on the 15-minute peak of the month, and most loads over 20 kW carry an 80% ratchet for 11 months.
  • A premise that has reached 700 kW is billed transmission on its 4CP kW, set by the four summer ERCOT peaks.
  • Managed charging, NEC Article 625 and a Fort Worth electrical permit to the 2026 NEC shape the design.

Fleet EV charging in Fort Worth starts with a question about the building you already have: how much more can its electrical service carry? The answer decides whether chargers fit on the existing service, whether Oncor has to build new poles, wire or a transformer, and how the delivery charges on the bill will move once the trucks plug in at night. This guide covers the load study, Oncor's new construction request, how Oncor bills demand, what managed charging changes, the NEC article that governs the equipment, and the City of Fort Worth permit.

What is a load study for fleet EV charging?

It is a measurement of what the existing service already carries, set against what it can carry, so the room left for chargers is a number and not a guess. We read the demand the building actually draws over time, add the chargers the fleet needs, and see whether the service, the panels and the feeders hold.

The study looks at the hours that matter. A warehouse busy by day and quiet at night may have room after the shift ends that it does not have at noon, and that is when a fleet usually charges. The study also counts the vehicles, the miles each covers in a day and the hours it sits at the depot. Those three numbers decide how many chargers are needed and how large each one is, and they keep the design from buying capacity the fleet will not use.

When does a fleet charging project need Oncor construction?

When the chargers need more than the existing service can give. Oncor says a project that needs its construction, such as new poles, wire or transformers, starts with an online request. Its commercial load form has a box for adding load to an electrically energized service, beside the one for new load.

After the request, Oncor asks the requester to create a Construction Portal account with the same email, to follow the project's status. A Project Manager is assigned and makes contact within two business days. When the site is ready, the Project Manager provides an ESI ID, the customer chooses a retail provider, and the meter is set on the start date chosen with that provider. Equipment such as transformers can take months to arrive, so the Oncor request belongs at the start of the project, not after the chargers are ordered.

Sources: Oncor's new construction page, its commercial new service request, and its Commercial and Industrial Load Requirements form.

What does Oncor's Project Manager need from the customer?

Plans and load figures. Oncor's Customer Checklist asks for civil and electrical plans, including the plat, site plan, riser diagram and panel schedule, plus one electrical load form for each voltage and phase type. Its load form asks for a site plan showing the proposed transformer, meter and other Oncor equipment locations.

The checklist also lists what must happen before Oncor can schedule construction: contracts received, payments received, original easement documents signed and received, the customer's civil work approved by an Oncor inspector, and the site within about 3 inches of final grade. The load form says an easement for on-site Oncor facilities is needed, by final plat or by a separate instrument. A fleet depot on leased land should raise the easement with the landlord early.

Source: Oncor's Customer Checklist.

How does Oncor bill demand for a fleet depot?

Most depots fall on Oncor's Secondary Service Greater Than 10 kW schedule. On it, the NCP kW is the demand supplied during the 15-minute period of maximum use in the billing month. A premise on that schedule stays there until it completes 12 consecutive billing months with no recorded demand greater than 10 kW.

Oncor's charges reach the customer through the retail provider. The tariff bills delivery charges to the competitive retailer serving the customer, and the Public Utility Commission regulates the delivery utility's rates but not the retailer's price. A fleet manager reading the bill will see the delivery charges inside the retailer's invoice, and the demand that drives them is set at the meter by the depot's own peak.

Sources: Oncor's Tariff for Retail Delivery Service, Section 6.1.1.1.3, and the PUC's guide to understanding your bill.

Why does the 80% ratchet matter for fleet charging?

Because one high month can set the bill for a year. For most loads over 20 kW, Oncor bills the distribution charge on the higher of this month's NCP kW or 80% of the highest NCP kW in the previous 11 months. Loads whose annual load factor is 25% or less are billed on the current month instead.

A second rule applies to the largest sites. A premise that has reached an NCP kW of at least 700 kW in any earlier billing month is billed transmission on its 4CP kW: the average of its demand during ERCOT's 15-minute system peaks in June, July, August and September of the previous year. That figure is updated every January 1 and stays fixed for the year. A depot charging at the moment of a summer afternoon peak carries that into the next year's bill.

What is managed charging?

Managed charging is a control system that shares a set amount of power among the chargers, so the depot never draws more than the limit chosen for it. Vehicles that need the most charge get it first, and the rest charge later in the night. The depot's peak stays flat while every truck still leaves full.

On an Oncor bill that flat peak is the point. The 15-minute NCP kW, the 80% ratchet and, at larger sites, the 4CP kW all reward a depot that does not spike. The NEC also allows the branch circuits and feeder to be sized to the setting of a listed load management system, which can keep a project on the existing service. Keeping the chargers off during summer afternoon peaks is a schedule written into the controls.

Which NEC article covers fleet EV charging equipment?

Article 625 of the National Electrical Code covers electric vehicle power transfer equipment, including the chargers, their circuits and their disconnects. It treats charging as a continuous load, so the branch circuit and overcurrent protection are sized at 125 percent of the charger's rating, unless a listed load management system sets a lower limit.

The article also covers where equipment may go, the disconnect for larger chargers, and the ground-fault protection personnel need around vehicles and cords. Charger maker instructions set the rest, such as clearances, mounting and conductor sizes. Fort Worth enforces the 2026 NEC on work started from September 1, 2026, so a project begun now is built to that edition of Article 625.

What permits does a fleet charging project need in Fort Worth?

A City of Fort Worth electrical permit, applied for through Accela Citizen Access. If the project also needs a building permit, the city issues it before the trade permit. The city's commercial plans list asks electrical plans to show transformer, disconnect, meter and panel locations and one-line diagrams.

The work is inspected before it is covered and again at the final, and power comes on after the city's electrical release. Oncor's tariff says it will not connect until the proper authority approves the installation. Most of Dallas and Fort Worth is served by Oncor; some edge areas are co-op territory, where the co-op's own service and billing rules apply. The price of a charging project is set at the free site visit.

We build these depots as Fort Worth EV fleet charging and Dallas EV fleet charging. The permit steps are in our guide to how commercial electrical permits work in Fort Worth. See also the Fort Worth commercial electrician hub and our commercial electrical services. Sources: the city's commercial building plans page and building and energy codes page.

FAQ

Common questions

Straight answers. If you do not see yours, call us and ask.

Does a fleet charging depot need a new Oncor service?

Not always. A load study shows whether the existing service has room. When it needs new poles, wire or a transformer, the project starts with Oncor's online new construction request.

What is the 80% ratchet on an Oncor bill?

For most loads over 20 kW, the distribution charge is billed on the higher of this month's peak or 80% of the highest peak in the previous 11 months.

Which NEC article covers EV chargers?

Article 625. It treats charging as a continuous load and allows circuits to be sized to a listed load management system's setting.

Related help

Where to go from here

Ready to get it handled?

Flat-rate pricing quoted up front. Licensed and insured. A Wattsmith electrician calls you back within 15 minutes during business hours.

  • Licensed and Insured
  • BBB Accredited
  • Flat-Rate Pricing
  • Background-Checked
Call NowGet a Quote