Key takeaways
- The City's flowchart runs 302 Grounding and 300 Slab before the foundation, 301 Rough once the building is dried in, then 304 Temporary, any 306 or 307 TCO, and the 305 Final.
- The 301 Rough may be requested only after the 302 and 300 inspections are approved and the building is dried in.
- The commercial 304 Temporary checklist cites the 2026 NEC and asks for Austin Energy's CT inspection and meter equipment approval where required.
- On CT-metered services, Austin Energy's CT inspection must pass before the City's 305 Final is called.
- Inspections are booked through the AB+C Portal or by phone and are usually done 24 hours after scheduling.
An Austin electrical inspection is booked at each point where commercial work is about to be covered or put under power, and the City numbers every one. The sequence runs from the 302 Grounding and 300 Slab inspections before the foundation is poured, through the 301 Rough once the building is dried in, to the 304 Temporary, any 306 or 307 TCO, and the 305 Final. This guide walks that order as the City of Austin's commercial flowchart and its October 2026 checklists set it out, and shows where Austin Energy's own inspection of CT-metered services fits into it.
What are the Austin commercial electrical inspections, in order?
The City's flowchart groups them in three stages. Before the foundation come 302 Electrical Grounding and 300 Electrical Slab. The rough stage is 301 Electrical Rough. The final stage holds 304 Temporary Electric, a 306 or 307 TCO when the building must be used early, and 305 Final Electrical.
- 302 Electrical Grounding: pre-foundation stage.
- 300 Electrical Slab: pre-foundation stage.
- 301 Electrical Rough: once the building is dried in and 302 and 300 are approved.
- 304 Temporary Electric: verifies the electric work is suitable, compliant and safe.
- 306 Electrical TCO Occupancy or 307 Electrical TCO Stocking: only when needed.
- 305 Final Electrical: final verification that all work is complete.
The City's Building Inspections page posts a checklist for each of them: Grounding, Slab, Rough, Temporary, TCO and Final, plus a Multifamily Dwelling Permanent Power checklist. The inspector works from those checklists, so they are also what we walk the job against before the request goes in.
Sources: the City's Commercial Electrical Inspections flowchart and its Building Inspections page.
What do the 302 Grounding and 300 Slab inspections cover?
The work the concrete is about to hide. The flowchart places both at the pre-foundation stage, ahead of the pour. In practice the grounding inspection sees the electrode and bonding work set before concrete, and the slab inspection sees conduit and boxes laid in or under the slab. Both must be approved before rough-in can be called.
Before calling either one, we check every stub-up against the drawings, cap the open conduit ends so concrete cannot get in, and make sure the grounding conductors are where the inspector can see them. After the pour, a misplaced stub-up means cutting the slab, so this is the inspection where a careful layout pays off most.
When can the 301 Rough inspection be requested?
Only after two conditions are met. The flowchart notes that before a 301 Electrical Rough request, the building must be dried in, and both the 302 Grounding and 300 Slab inspections must be approved. Rough-in is seen with walls and ceilings still open, so every box, conductor and support is in view.
Dried in means the roof and exterior openings keep weather out, so the wiring under inspection is not sitting in rain. On a tenant build-out inside a finished shell there is no new foundation, and the sequence usually starts at rough. Rough is the last point at which wiring can be seen and corrected without opening finished walls, which is why the drywall crew is scheduled behind it, not beside it.
What does the 304 Temporary inspection ask for?
The commercial 304 checklist, dated October 9, 2026, starts with the 302 Grounding inspection passed. Where required, Austin Energy must have completed a CT inspection and approved the meter equipment. Conductors must be color coded per the City of Austin Electric Code, and the checklist cites the 2026 NEC and the 2026 City code.
Two other lines show the checklist's focus. Available fault current must be posted, under 2026 NEC 110.24, and ground-fault protection of equipment must have been tested where required, under 230.95(E). The flowchart says the 304 is required to verify that all electric work is suitable, compliant and safe, so it is a real inspection, not a formality on the way to the final.
Source: the City's commercial Electrical Temporary Inspection Checklist. The 2026 NEC is the state code from September 1, 2026, by TDLR's rule adoption.
Where does Austin Energy's CT inspection fit?
Before the City's final. Austin Energy's metering guidelines say all transformer-rated services must be inspected before any meter is set, and that instrument-rated or CT-rated inspections must be called in and passed before the contractor calls for a 305 from the City. The CT inspection is scheduled with Austin Energy's Distribution Metering Operations dispatch.
Austin Energy's Design Criteria also says service equipment must be approved by its Distribution Metering Operation unit before it is bought or installed. On a CT job we put that approval at the front of the schedule and book the CT inspection ahead of the final, so neither inspection waits on the other. The metering guide carries no date, so we confirm its steps with Distribution Metering on each job.
Sources: Austin Energy's Metering Guidelines for Instrument Rated Metering and its Design Criteria.
What are the 306 and 307 TCO inspections?
They let a building be used before its final. The flowchart says a 306 Electrical TCO Occupancy or 307 Electrical TCO Stocking inspection is only required to allow occupancy or stocking of the structure. The City's TCO checklist, dated October 9, 2026, treats them as two inspections, each with its own conditions.
For 306 Occupancy, the checklist asks that all life-safety equipment and luminaires be installed, connected and functioning. For 307 Stocking, it asks that the electrical rough-in inspections are complete. A retailer that wants shelves filled before opening day plans a 307; a tenant that needs staff working in the space early plans a 306.
Source: the City's commercial Electrical TCO Inspection Checklist.
What does the 305 Final check?
That all the work is complete. The flowchart calls the 305 Final Electrical the final verification that work is finished. The October 6, 2026 Final checklist has its own section for a temporary loop and items such as service equipment that is suitable for the use and identified as such, under 2026 NEC 230.66.
Before the final we label every panel directory, test ground-fault devices, and install the arc flash warning labels the code calls for under 110.16 on equipment likely to be worked on while energized. We install those labels; we do not perform arc flash studies, which are an engineer's work.
Source: the City's commercial Electrical Final Inspection Checklist.
How are Austin electrical inspections booked, and how soon do they happen?
Through the AB+C Portal or by phone, and booking is the contractor's job. The City says inspections are usually performed 24 hours after scheduling, but an inspector's workload can push a scheduled inspection to the next business day or 48 hours out. Trades that follow an inspection are planned with that window in mind.
Once the City's inspection passes, Austin Energy's Design Criteria says it should receive notification of the passed electrical inspection three regular working days before the service can be energized. The permit itself comes first: the City requires trade contractors to register with Building and Trade Contractor Services, and Wattsmith registers with the City before a permit is bought, as the City requires.
Sources: the City's contractor registration page and stand-alone permit page. We run this sequence on Austin tenant build-outs. New homes follow a residential version, covered in Austin Energy temporary power for home builders. See also the Austin commercial electrician hub and our commercial electrical services. The price of the work is set after the free written estimate.