Fleet EV Charging in Houston: The Service, CenterPoint and the Code

November 1, 2026Last updated 6 min readWattsmith Electric · TECL 41806

Key takeaways

  • Fleet EV charging starts with a load study of the existing service and panels, before any charger is chosen.
  • When the service has to grow and CenterPoint must add poles, wire or a transformer, the job goes through an online Electric Service Request, and CenterPoint does not guarantee construction timelines.
  • CenterPoint bills commercial distribution on the busiest 15 minutes of the month, so managed or staggered charging keeps a fleet from setting a new peak.
  • Chargers are built to NEC Article 625, and Houston reviews permit applications submitted on or after September 1, 2026 under the 2026 NEC.
  • Conduit run now for the chargers you will add later costs less disruption than trenching the lot twice.

Fleet EV charging at a Houston depot, warehouse or office garage is an electrical service question before it is a charger question. A row of trucks plugged in at the end of a shift can draw more than the building's other loads combined. Whether that fits depends on the service already there, the panels it feeds, and what CenterPoint Energy has to build if it does not. This guide covers the load study, CenterPoint's construction requests, how charging hours meet the demand charge, NEC Article 625, the City of Houston permit, and the conduit worth running now for chargers you will add later.

What does fleet EV charging need from a building's service?

It needs spare capacity at the service and in the panel that feeds the chargers, for as many hours as the fleet charges. Each charger is a continuous load, so the service has to carry it for hours alongside everything else that runs at the same time, with the margin the code requires.

The vehicles decide how much. A truck that drives a short route and sits overnight can charge slowly over many hours. A vehicle that turns around between shifts needs a faster charger and more power in a shorter window. The daily miles, the hours parked and the number of vehicles set the total, and that total is what the service has to carry.

How is a load study done against the existing service?

We start with the service size, the main and the panels, then measure or read what the building already draws at its busiest times. The gap between that peak and what the service can safely carry is the room left for chargers. If the gap is too small, the plan needs a larger service or managed charging.

The building's own records help. A year of electric bills shows the monthly peak demand, and interval data from the retail provider shows when in the day it happens. We walk the panels to see where a charger circuit can come from and how far it has to travel to the parking. The result is a short written plan: how many chargers fit today, how many fit with managed charging, and what it takes to go beyond that.

  • Service size, main rating and the panels that could feed chargers.
  • The building's existing peak demand, from bills, interval data or measurement.
  • Vehicle count, daily miles and the hours each vehicle is parked.
  • The distance from the panel to the parking, and the route conduit can take.
  • How many chargers the fleet may add in the next few years.

When does CenterPoint need to build for fleet chargers?

When the chargers need more service than the site has and CenterPoint has to add poles, wire or a transformer, the project goes through CenterPoint's online Electric Service Request. A commercial business owner or builder calls CenterPoint for an ESI ID if the service is new, and files the request for the construction.

CenterPoint's tariff lists what every construction request must include: a contact name and phone number, the ESI ID if one exists, the service address with directions and access instructions, the construction asked for, and the date wanted. CenterPoint says it will contact the person named within two business days. The tariff also says it does not guarantee when construction starts or finishes, so a fleet with a delivery date for its vehicles files early.

CenterPoint does not connect the new service until it receives notice that the proper authority has approved the installation. In Houston that is the city's inspection and release, so the city permit and the CenterPoint request move side by side.

Sources: CenterPoint's service connect page and its Tariff for Retail Delivery Service, Sections 5.3.2 and 5.4.2.

How do fleet chargers affect CenterPoint demand charges?

A business on CenterPoint's secondary service schedule over 10 kVA pays distribution per billing kVA, set by its busiest 15 minutes of the month. A row of chargers that all start when the trucks return can set a new peak in one quarter hour, and that peak sets the charge for the month.

Larger sites have a second effect. Once a business has set a demand over 700 kVA, CenterPoint bills transmission on 4CP, its demand at the times of ERCOT's monthly system peaks in June through September of the previous year. Those peaks fall on summer afternoons. A fleet that charges in the afternoon in summer can raise that number for the whole of the following year.

The same rules are explained in more detail in our guide to CenterPoint demand charges and LED retrofits. We do not quote tariff rates; your bill shows the ones that apply to you.

What is managed or staggered charging?

Managed charging uses the chargers' own controls or a site energy management system to cap how much power the fleet draws at once and to share it among the vehicles. Staggered charging is the simpler form: chargers start on a schedule, in groups, so they do not all start when the shift ends.

Both do two things. They keep the fleet from setting a new demand peak, and they can let more chargers share a service that could not carry them all at full power. The NEC lets the load calculation use the limit a listed energy management system enforces, so a managed system can sometimes avoid a service upgrade. The trade is time: each vehicle charges more slowly, which works when the fleet is parked for long hours and less well when vehicles turn around fast.

What does NEC Article 625 require for fleet chargers?

Article 625 of the National Electrical Code covers electric vehicle charging equipment. It treats charging as a continuous load, so circuits are sized at 125 percent of the charger's rating, and it calls for each charger to be on its own branch circuit, with listed equipment and the disconnecting means the article sets.

Outdoor fleet lots add their own needs. Chargers and their circuits must be rated for the location, cords must be protected from being run over, and bollards or wheel stops keep trucks from backing into the equipment. Ground fault protection for personnel is built into listed chargers, and the article sets the rules for where and how it applies. The inspector checks the installation against the edition of the code the permit was reviewed under.

Does fleet charging need a City of Houston permit?

Yes. Charger circuits are electrical work under a City of Houston permit, applied for in the iPermits portal and issued only to registered master electricians. Houston reviews permit applications submitted on or after September 1, 2026 against the 2026 National Electrical Code, the edition Texas adopted on that date.

Houston's code says only a licensed and registered electrical contractor may obtain an electrical permit. Underground conduit and other wiring meant to be concealed is inspected before it is covered, and nothing is connected to power until the building official approves it. On a fleet lot, that usually means a ditch inspection for the conduit to the parking before the trench is closed.

Sources: the Houston Permitting Center's 2026 National Electrical Code notice and the City of Houston Electrical Code administrative provisions.

Why should conduit be planned for later chargers?

Because the trench and the panel space are the hard part, and they are cheapest to add once. Running empty conduit to future charger spots while the lot is open, and leaving room in the panel or switchboard, means the next chargers go in without cutting the paving or rebuilding the service again.

We plan the conduit from the fleet's own forecast: how many vehicles in the next few years and where they park. Pull strings go in the empty runs, the ends are capped and marked, and the plan is kept with the permit records so the next crew knows what is there. A site that adds chargers in stages also gets a new load study at each stage, against the demand the earlier chargers have added.

The full scope is on our Houston EV and fleet charging page, and the price is set after the free written estimate. For our other Houston work, see the Houston commercial electrician hub, and for our work across Texas, our commercial electrical services.

FAQ

Common questions

Straight answers. If you do not see yours, call us and ask.

Do Houston fleet chargers need a city permit?

Yes. Charger circuits are electrical work under a City of Houston permit, applied for in iPermits and issued only to registered master electricians.

Will fleet chargers raise my CenterPoint demand charge?

They can, if they run during your busiest 15 minutes of the month. Managed or staggered charging keeps them off that peak.

How long does CenterPoint take to build new service for chargers?

CenterPoint says it contacts the requester within two business days of a construction request, but its tariff does not guarantee when construction starts or finishes. File the request early.

Related help

Where to go from here

Ready to get it handled?

Flat-rate pricing quoted up front. Licensed and insured. A Wattsmith electrician calls you back within 15 minutes during business hours.

  • Licensed and Insured
  • BBB Accredited
  • Flat-Rate Pricing
  • Background-Checked
Call NowGet a Quote