Key takeaways
- A written bid names the drawings it was priced from, by sheet and date, so a later revision is visible as a change.
- Commercial electrical work in Dallas needs a registered electrical contractor and a permit, applied for and inspected through DallasNow.
- Oncor connects only after the city approves the installation, so the bid should say who files the Oncor request and the load form.
- Exclusions are part of the scope: what the bid leaves out is as important as what it includes.
- Change orders are priced in writing and approved before the added work starts.
An electrical contractor bid for a Dallas commercial job should tell you what will be built, from which drawings, under which permit, and what is left out. The total is one line of it. When commercial electrical contractors bid the same space, the bids you can compare side by side are the ones that list the same items: the scope, the drawing set, the permit and inspections in DallasNow, the Oncor coordination, the exclusions, the schedule and the way a change is priced. This guide walks through each item so a bid from any electrical contractor in Dallas can be read line by line.
What should a written electrical contractor bid list?
It should list the work in plain terms: the service and distribution equipment, the branch circuits, the lighting, the devices and any specialty systems, each tied to the drawings it came from. It should also name the permit, the inspections, the utility coordination, what is excluded, the schedule and how changes are handled.
A one-page number with the word "electrical" above it is not a bid in this sense, because nobody can check what it covers. A useful bid follows the drawing set sheet by sheet, so an owner, a general contractor or a property manager can hold it up against the plans and see that every panel, feeder and fixture group was counted. When two bids differ, that layout shows where: one priced the site lighting, the other left it out.
Which drawings should the bid be based on?
The bid should name the exact drawing set it was priced from, by sheet number and issue date. Dallas plan review checks one-line diagrams, load calculations, conductor sizing, overcurrent protection and grounding against the NEC, so those sheets carry most of the electrical scope and belong on the bid's list.
The city's electrical permit checklist says submitted electrical plans must include a diagram of the service, conductor and pipe sizes, the grounding electrode system, service overcurrent protection, the location and number of services, and the floor plan power and lighting layout. Where electrical plans were already in the master permit set, no further plan submittal is needed. Either way, a bid that names its sheets makes any later revision easy to spot, because the new sheet date does not match the one the price was built on.
Sources: the City of Dallas Electrical Permit Application Checklist and the 2025 to 2026 Development Guide, page 36, electrical reviews.
How should the bid handle the Dallas permit and inspections?
It should say who pulls the electrical permit and who schedules the inspections. Dallas says electrical work on commercial property requires a registered electrical contractor and a permit. All applications go through DallasNow, the city's land management system launched May 5, 2025, and inspections are scheduled there at least 24 hours ahead.
The city's automated permitting reads the contractor registration file and will not issue a permit to a contractor who is not registered, whose registration has expired or whose insurance has lapsed. That makes registration a bid item, not a formality. Wattsmith Electric registers with the City of Dallas before a permit is bought, as the city requires. The city's development guide also says approved plans must be on site for inspections, and the bid should say who keeps the set there.
The code matters too. Ordinance 33081 amended Chapter 56, the Dallas Electrical Code, to adopt the 2023 National Electrical Code with local amendments, effective May 23, 2025. A bid priced to a different edition than the one the permit office reviews under is priced to the wrong rules.
Sources: Chapter 56 as amended by Ordinance 33081, the city's contractor registration requirements and the DallasNow page. The steps are in our guide to how commercial electrical permits work in Dallas.
Where does Oncor coordination fit in the bid?
Wherever the job touches the utility. Oncor says a project that needs its construction, such as new poles, wire or transformers, starts with an online request, and its commercial load form asks for service dates, meters, voltage and loads. The bid should say who files those, who meets Oncor on site, and who waits for the release.
Oncor will not connect until it is told the proper authority approved the installation. In Dallas that approval is a release: for temporary power, the electrical contractor files a Request for Temporary Utilities, the electrical room must be dried in, the panel or room must lock, and the service must pass inspection before anything is energized. Chapter 56 adds that only Oncor employees may connect Oncor's conductors to the customer's service entrance conductors. Oncor equipment can take months to arrive, so a bid that adds service should show the Oncor request near the start of the schedule.
Sources: Oncor's new construction page, its Commercial and Industrial Load Requirements form, the city's temporary utility release form and Oncor's Tariff for Retail Delivery Service, Section 5.4.2.
What belongs in the exclusions?
Everything the price does not cover that someone might assume it does. Common exclusions are trenching and concrete, roof penetrations, fire alarm, low voltage cabling, utility charges, equipment supplied by others and work behind finished walls nobody has opened. Each one is a line, so the owner knows which trade or which party carries it.
Exclusions are not a way to make a bid look lower. They draw the line between trades. If the general contractor's concrete crew pours the generator pad, the electrical bid says so; if the owner buys the light fixtures, the bid says it installs fixtures supplied by others. When two bids carry different exclusions, adding the excluded items back is the only fair way to compare them.
How should the schedule be written?
As a sequence of steps with the outside waits named, not a single finish date. The Dallas development guide sets an initial review performance goal of 15 days for electrical plans, inspections are booked a day ahead, and Oncor work has its own timeline. A bid that shows these separately shows where time can slip.
The guide does not say whether those 15 days are business or calendar days, and a set that comes back with comments goes through another round. Rough-in, cover and final inspections each depend on the work before them, and any temporary power waits on its own release. Writing the schedule as steps lets the general contractor line up the other trades around the electrical milestones instead of around a date that was never tied to the permit.
How are change orders handled in a good bid?
In writing, priced before the added work starts. The bid should say that any change to the scope, the drawings or the schedule gets a written change order with its price and its effect on time, and that the crew does not start the added work until someone with authority has approved it.
Changes come from revised sheets, owner requests, conditions found behind walls and inspector comments. A bid that names its drawing set makes the first kind easy to price, because the revision is plain. For the rest, the bid can say how the price will be worked out: the labor and material the change adds, less anything it removes. The figure itself is set in writing each time, never after the fact.
Who should hold the license behind the bid?
A Texas electrical contractor licensed by TDLR. The state says anyone who performs electrical work in Texas must be licensed, and an electrical contractor must employ a licensed master electrician. A state license is valid anywhere in Texas, and Dallas adds its own contractor registration on top of it.
You can check this yourself before signing. TDLR's license search shows whether a contractor's license is current, and the contractor can show the Dallas registration and a certificate of insurance. Chapter 56 also requires a qualified electrician of the proper classification on site, supervising permitted work. Wattsmith Electric is a veteran-owned Texas electrical contractor, license TECL 41806, based in San Antonio.
Check a license with TDLR's license search. Sources: the TDLR electricians FAQ and TDLR's electrical contractor license page.
We bid Dallas tenant build-outs this way. If the space needs standby power, our guide to commercial generator installation in Dallas covers that scope. For the rest of our work in the city, see the Dallas commercial electrician hub and our commercial electrical services. The price is set after the free written estimate.