Key takeaways
- Temporary power starts with AEP Texas's Temporary Service form, which requests an ESI ID for service during construction.
- AEP Texas's tariff has the requester pay before it builds temporary delivery facilities.
- The City's 22,000 amp fault current minimum for service equipment excludes temporary construction loops.
- For permanent service, AEP Texas issues a 9-digit number, may hold a site meeting, and sends a design package.
- The meter is energized after AEP Texas receives the electrical inspection and deposits; the City's electrical permit follows the building permit.
AEP Texas temporary power on a new home starts with a number, not a pole. The builder asks AEP Texas for an ESI ID for power during construction, and that number follows the temporary service from the request to the meter. The permanent service then runs on its own track: a request, a site meeting, a design package, and a meter energized only after the City's inspection. This guide follows AEP Texas's temporary service form, its tariff and its new-home steps, then the City of Corpus Christi's new-home submission, for builders putting up homes in the city.
How does AEP Texas temporary power start?
With AEP Texas's Temporary Service form, which exists to request an ESI ID for electrical service during construction. The form asks for the site address, directions to the site, a customer contact name and details about the construction request. The ESI ID it produces identifies the temporary service from then on.
The request starts a clock rather than ending one. AEP Texas's tariff gives the company two business days to reach the person named on a construction request, and it makes no promise about how quickly the work itself gets done. On a production schedule, the temporary request goes in when the lot is ready to clear, so the pole has power before the foundation crew needs it.
Sources: AEP Texas's Temporary Service form, its Builders and Contractors page, and its Tariff for Retail Delivery Service, Section 5.3.
Who pays for AEP Texas temporary facilities?
The customer, or whoever asks for the service, and in advance. AEP Texas's tariff says the requester pays the company before it builds temporary delivery system facilities, under the tariff's Chapter 6. The amount is set by AEP Texas for each site, and it comes with the arrangements for that job.
The pole follows AEP's guide. It says the company has specific requirements for temporary service and should be consulted for each case, and that the structural requirements for a temporary service used in construction are shown in its figures M.S._F001 and M.S._F003. We build the pole and the meter loop to the figures in the edition AEP Texas links today, and check with AEP Texas when a lot calls for something those figures do not show.
Sources: AEP Texas's Tariff for Retail Delivery Service, Section 5.7.7, and AEP's Guide for Electric Service and Meter Installations (2026), Section 4.6.
What does the City's code say about temporary construction loops?
One thing, and it is an exception. Corpus Christi's amendment to NEC 230.70 requires all electrical service entrance equipment to carry fault current protection of at least 22,000 amps, except temporary construction loops. It is the only City text we found that names temporary power at all.
We found no City page or form for a separate temporary power permit, and no list of temporary pole rules, so we do not describe one. On a home build the temporary loop is planned with the electrical permit and the AEP Texas request, and we confirm with the City how it wants the temporary service handled before the pole is set. The permanent service equipment, unlike the loop, must meet the 22,000 amp minimum.
Source: the City's code ordinance with local amendments, Section 230.70(D).
How does AEP Texas set up permanent service for a new home?
The builder requests it on AEP Texas's new-home form, or by phone, giving a project contact, the 911 site address and the type of service. AEP Texas says the requester receives a 9-digit number and, if needed, a technician site visit is scheduled. That number is the job's reference with AEP.
For the site meeting, AEP Texas asks the builder to bring the date the site will be ready, a site plan showing features such as the driveway, the planned meter location, and load information, including square footage and heating and cooling kW. Getting the meter location right at this meeting saves moving it later, because the design that follows is drawn to it.
Source: AEP Texas's new home service page.
What is in AEP Texas's design package?
After the site visit, the AEP Texas technician sends a design package with the easement requirements, a construction drawing and an estimated cost, if there is one. The builder reviews it, settles any easement, and meets the other requirements before AEP Texas builds. Changes to layout or scope after this point delay the job.
AEP Texas lists the other things that slow new service: requests for multiple estimates, information that is wrong or late, permitting, and third-party easements. It also says the time of year, weather and storm restoration work can greatly affect its timeline, and it gives no number of days. On this coast, storm season belongs on the schedule as a real risk to the meter date.
When does AEP Texas energize the new home's meter?
Once it receives the electrical inspection and the security deposits, and the other requirements are complete. AEP Texas says the meter is energized at that point. Its tariff carries the same rule in general form: no interconnection until the company is notified that the proper authority approved the electrical installation.
In Corpus Christi that approval comes from the City. AEP Texas's Corpus Christi entry says a City inspection is required inside city limits where no meter existed before, and the City calls its approval a service release, sent by a City inspector to the power provider. Each new home also needs a retail electric provider before power is used: AEP's guide says Texas Choice is applied for through a retail provider, as far ahead of the service date as possible.
Sources: AEP Texas's new home service page, its Permit and Inspection Requirements page, and the City's Informational Bulletin 019. The full step is in our guide to the Corpus Christi service release.
What does AEP's guide require of a new home's service?
For AEP West, which includes AEP Texas, the guide says residential service entrance conductors and equipment should be rated at least 200 amps, and it does not permit 100-amp meter sockets. It sets a 36 inch burial depth for Texas and requires a surge protective device on every service supplying dwelling units.
The surge rule follows NEC 2020 Article 230.67, which AEP cites, and the guide applies it when service equipment is replaced as well as on new work. The guide is written for all of AEP's operating companies and borrows some text from other states, so we use only the lines it states for Texas or AEP West, and check anything else with AEP Texas.
Source: AEP's Guide for Electric Service and Meter Installations (2026), Sections 4.11 and 9.2.
What does the City need for a new-home electrical permit?
A complete new-home submission, then a separate electrical permit. The City lists the building permit application, site and floor plans, an engineer-sealed foundation plan, an energy compliance certificate and the TDI windstorm WPI-1 form. The electrical permit application is filed after the building permit is issued, by a contractor registered with the City.
The checklist, Form DSD-1002, says the contractor's registration must be valid and current with the City, and its drawings list includes electrical plans. It names the 2021 IRC and the 2020 NEC, and the City's ordinance deletes the IRC's electrical part, so homes follow the National Electrical Code. Texas adopted the 2026 NEC statewide from September 1, 2026, and the City has not posted how it handles that, so we confirm the edition at plan review. We register with the City before a permit is bought, as it requires. When a home is done, the City issues the certificate of occupancy as the final step.
Sources: the City's new residential buildings page, its new residential checklist, DSD-1002, its Informational Bulletin 018, and TDLR's September 1, 2026 rule adoption.
Do you wire new homes for Corpus Christi builders?
Yes. For home builders in Corpus Christi we wire new homes, from the temporary loop through rough-in and trim-out to the final inspection and the permanent meter. We start the AEP Texas permanent request early, so the meter does not hold the closing. Service calls, repairs and remodels on existing homes stay in the San Antonio area only.
See Corpus Christi new construction electrician, Corpus Christi commercial and industrial electrical work, and our commercial electrical services. The price for wiring a plan is set after the free written estimate.