How Commercial Electrical Permits Work in Austin, From AB+C to Final

November 1, 2026Last updated 6 min readWattsmith Electric · TECL 41806

Key takeaways

  • Austin Development Services runs permits, plan review and inspections, and every step starts with an account in the Austin Build + Connect (AB+C) Portal.
  • Commercial plans are reviewed to the 2024 International Building Code; review time starts only once the invoice is paid.
  • A stand-alone electrical permit covers electrical work not tied to a building permit, and only a registered trade contractor may apply for one.
  • The contractor books each inspection through AB+C or by phone, and Austin Energy energizes only after the City approves the work.

A commercial electrical permit in Austin moves through the City of Austin Development Services Department and its online system, the Austin Build + Connect Portal, known as AB+C. The same portal carries the plan review application, the trade permit and the inspection requests. This guide follows that path for a property manager, owner or general contractor planning electrical work on a commercial space in Austin, using the City's own pages, so you know which step belongs to the City, which belongs to your electrician, and where Austin Energy comes in at the end.

Who runs commercial electrical permits in Austin?

Austin Development Services runs permits, plan review and inspections for commercial work in the city. Its commercial plan review page asks applicants to create an account in the AB+C Portal, then submit a Commercial Plan Review Application through the Commercial Building Permit Web Form. Austin Energy, a separate City department, handles the power connection afterward.

Two departments of one city therefore share a commercial job. Development Services reviews the drawings, issues the permits and sends inspectors. Austin Energy designs and builds its side of the service and decides when to energize. Keeping those two tracks apart in your schedule is the first step to reading where a job is stuck.

On a tenant space in an existing building the split still holds, only smaller. The City may need nothing more than a trade permit and a few inspections, while Austin Energy may need nothing at all unless the service or the meter changes. The scope of the electrical work decides how many of the steps below apply.

What does commercial plan review check in Austin?

The City says commercial construction projects are reviewed for compliance with the 2024 International Building Code. For electrical questions, applicants can book a Commercial Electrical Codes appointment to ask general plan and code questions about compliance with the National Electrical Code. Questions about Austin Energy's Electrical Design Criteria go to Austin Energy instead.

The page does not describe a separate electrical review discipline, so plan the drawings to answer the reviewer's questions on their own. In general practice a commercial electrical set shows the lighting and power layout, panel schedules for each new or changed panel under NEC Article 408, branch circuits under Article 210, and a load calculation for the service and feeders under Article 220.

  • Lighting and power plans for the space.
  • Panel schedules for every new or changed panel.
  • A load calculation for the service and feeders.
  • A one line or riser diagram where the work changes the service.

How long does Austin commercial plan review take?

The City's page lists review times by application type. Quick Turnaround reviews take 1 business day and Small Projects take 5 business days, and depending on the application type a review can take 7 to 25 business days. The clock starts only once the invoice is paid and the project is distributed for review.

Quick Turnaround has limits that matter for electrical work. The City says it is not for projects that need complex system upgrades, such as large new electrical services. Its EV Quick Turnaround path excludes jobs that need a new service or run over 400 amps. A job that adds a service or a large feeder should plan for a longer review from the start.

The review types and times are on the City's commercial plan review page.

When is a stand-alone electrical permit used?

A stand-alone electrical permit covers electrical work unrelated to a building permit, such as new circuits in an existing suite that needs no other construction. Only a registered trade contractor, or a registered homeowner acting as the trade contractor, may apply, and the contractor named on the permit must have an AB+C account.

The City adds that trade contractor registration with up to date information is required before the application can be submitted. On a commercial or multifamily property, plan review may be needed when more than one trade permit is requested, so a job that touches electrical and mechanical work together may not stay a simple trade permit.

The rules are on the City's stand-alone permit page, and our guide to Austin trade contractor registration covers what the contractor needs in place first.

Who books electrical inspections in Austin?

The contractor does. Austin's Building Inspections page says inspections can be scheduled online through the AB+C Portal or by phone, and that it is up to the contractor to schedule each one. Inspections are usually performed 24 hours after scheduling, though an inspector's workload can push one to the next business day or 48 hours.

The City's commercial electrical inspections flowchart names the stages in order: the 302 Electrical Grounding and 300 Electrical Slab inspections before the foundation, the 301 Electrical Rough once the building is dried in, then the 304 Temporary Electric, a 306 or 307 TCO inspection when occupancy or stocking is needed early, and the 305 Final Electrical. Each stage is booked separately, so a crew should call each one as soon as the area is ready.

The flowchart sets one condition worth planning around. Before the 301 Electrical Rough inspection is requested, the building must be dried in and both the 302 Grounding and 300 Slab inspections must already be approved. The 306 and 307 TCO inspections are needed only to allow occupancy or stocking before the final, so a retailer that wants to stock shelves ahead of opening should put the 307 on the schedule from the start rather than find it late.

The scheduling rules and the checklists for each stage are on the City's Building Inspections page.

When does Austin Energy turn on the power?

Austin Energy energizes a site only after Austin Development Services inspects and approves the project. Its Design Criteria asks to receive notification of a passed electrical inspection from the City, and from all other governing entities, three regular working days before the service can be energized. Build that notice into the schedule.

The last days of a job therefore run in a fixed order: the City's final inspection passes, the City's notification of that passed inspection reaches Austin Energy, and Austin Energy energizes. If the job also needs new or larger service, Austin Energy's own design steps should have started months earlier.

Our guide to Austin Energy new commercial service covers those steps, and Austin Energy's construction and renovation page lists them in its own words.

How should an owner plan around the Austin permit steps?

Plan around the City's gates rather than crew availability. Open the AB+C account early, have the electrical drawings ready with the plan review application, expect review time to start only when the invoice is paid, show each inspection as its own schedule line, and allow three working days between the passed inspection and Austin Energy energizing.

  • Confirm the electrician's City registration and TDLR license before the bid is accepted.
  • Decide early whether the work is a building permit job or a stand-alone electrical permit.
  • Keep Quick Turnaround for jobs with no new service and nothing over 400 amps.
  • Hold drywall and ceilings until the rough inspection has passed.
  • Start any Austin Energy service request well ahead of the final.

Texas requires anyone doing electrical work to be licensed, and electrical contractors must employ a licensed master electrician. Our Texas electrical contractor license is TECL 41806. We register with the City of Austin before a permit is bought, as the City requires, and we work Austin from San Antonio, planning each trip around the inspection the space is ready for.

For suites and storefronts, see our Austin tenant build-out electrician page. The Austin commercial electrician hub lists all our Austin work, our commercial electrical services page covers the rest of Texas, and the code edition the reviewer uses is in our Austin electrical code guide. TDLR's licensing rules are on its electrician FAQ and electrical contractor page. Every job is priced after the free written estimate.

FAQ

Common questions

Straight answers. If you do not see yours, call us and ask.

Can a general contractor pull the electrical permit in Austin?

A stand-alone electrical permit may be applied for only by a registered trade contractor or a registered homeowner acting as one, and the contractor on the permit needs an AB+C account.

How fast are Austin electrical inspections?

The City says inspections are usually performed 24 hours after scheduling, but an inspector's workload can delay one to the next business day or 48 hours.

When does plan review time start in Austin?

The City says the review time starts once the invoice is paid and the project is distributed for review.

Ready to get it handled?

Flat-rate pricing quoted up front. Licensed and insured. A Wattsmith electrician calls you back within 15 minutes during business hours.

  • Licensed and Insured
  • BBB Accredited
  • Flat-Rate Pricing
  • Background-Checked
Call NowGet a Quote