CenterPoint Demand Charges and LED Retrofits for Houston Buildings

November 1, 2026Last updated 6 min readWattsmith Electric · TECL 41806

Key takeaways

  • A business on secondary service with a peak over 10 kVA pays CenterPoint's distribution charge per billing kVA, the most power used in any 15 minute period of the month.
  • Over 700 kVA, CenterPoint bills transmission on 4CP: the business's demand at ERCOT's monthly peaks in June through September of the year before.
  • The 80% ratchet applies to primary voltage service, not to the secondary schedule most buildings are on.
  • CenterPoint's delivery charges reach you through your retail electric provider's bill.
  • Lighting that is on through the peak is part of the number, so an LED retrofit lowers both the energy used and the demand billed.

A CenterPoint demand charge is the part of a Houston business's electric bill set by its busiest fifteen minutes, not by how much energy it used over the month. Property managers often see it as a line that moves for no clear reason. It follows a few rules in CenterPoint's tariff, and once those rules are clear, it is easier to see what lighting has to do with it and why an LED retrofit can lower it. This guide explains the rules in plain words, without rates, and shows how to read the demand line on a bill before and after a retrofit.

What is a CenterPoint demand charge?

It is a delivery charge based on the highest rate at which a business drew power during the month, rather than the total energy it used. CenterPoint's tariff charges distribution per billing kVA on its schedule for non-residential secondary service over 10 kVA, so a short peak can set the charge for the month.

Two buildings can use the same energy in a month and pay different demand charges. One that spreads its use evenly across the day has a low peak. One that starts every rooftop unit, every light and a kitchen line at the same moment has a high one. The energy part of the bill counts the total. The demand part looks only at the busiest stretch.

How does CenterPoint measure demand for a business?

CenterPoint measures the kVA supplied during the 15 minute period of maximum use in the billing month, which the tariff calls the NCP kVA. On the secondary service schedule for loads over 10 kVA, the billing kVA for the distribution charge is that month's NCP kVA. One busy quarter hour sets it.

The unit is kVA, not kW. Kilowatts measure the power that does work. Kilovolt amperes measure all the current the wires carry, including current that moves back and forth without doing useful work. Equipment with a poor power factor, such as older fixtures on magnetic ballasts and some motors, draws more kVA for the same work. That is one more reason lighting matters to a demand charge billed in kVA.

The schedule is Sheet 6.3, Section 6.1.1.1.3, in CenterPoint's Tariff for Retail Delivery Service. We do not quote its rates here; your bill shows the ones that apply to you.

What changes for a business with a peak over 700 kVA?

Once a business has set an NCP demand over 700 kVA in any previous billing month, CenterPoint bills transmission on the 4CP method. The 4CP kVA is the average of its 15 minute demands at the times of ERCOT's monthly system peaks in June, July, August and September of the previous calendar year.

That means four summer afternoons last year can set part of this year's bill. The business does not know in advance which fifteen minutes ERCOT's peak will land on, but it knows they fall on hot summer afternoons when the whole grid is busiest. Any load the building does not run at those times, lighting included, lowers the 4CP number for the year that follows.

Does the 80% demand ratchet apply to my building?

Only if the building is served at primary voltage. CenterPoint's primary service schedule bills the higher of this month's peak or 80% of the highest peak in the previous 11 months, with loads at or under 20 kVA excepted. The secondary schedule most commercial buildings are on carries no ratchet in its text.

Primary service is for customers served directly from feeder lines of at least 12,470 volts but less than 60,000 volts, which usually means a plant or a large campus with its own transformers. For those customers, one high month can set the floor for most of a year, so a lower lighting load helps for many months at once. For a building on secondary service, the demand charge follows each month's own peak.

Why do CenterPoint charges show up on a retail provider's bill?

In the Houston market, CenterPoint owns the wires and delivers the power, while the business buys its electricity from a retail electric provider. CenterPoint's tariff charges its delivery service to that provider, which the tariff calls the Competitive Retailer, and the provider passes those charges through on the bill the business receives.

So the bill has two kinds of charges. The provider's own energy charges depend on the contract the business signed. The delivery charges follow CenterPoint's tariff, whichever provider sends the bill. Changing providers can change the energy price, but the demand side of the delivery charge moves only when the building's own peak moves.

How does lighting load sit in the 15 minute peak?

Lighting is usually on for the whole business day, so it is on during the busiest quarter hour no matter when that falls. Unlike a compressor that cycles, a warehouse full of high bays or an office of troffers adds its full load to every 15 minute period while the lights are on.

That makes lighting one of the steadiest parts of a building's peak. Cooling swings with the weather, and kitchen or process loads swing with the schedule, but lighting sits underneath all of them. In a warehouse with high ceilings and long hours, it can be a large share of the base. In an office, it adds to the cooling load as well, since older fixtures turn much of their power into heat that the air conditioning then removes.

How does an LED retrofit lower both energy and demand?

An LED fixture gives the same or better light with fewer watts than the fixture it replaces. Fewer watts for the hours the lights run lowers the energy charge. Fewer watts during the busiest quarter hour lowers the peak, and with it the billing kVA, the 4CP number and, on primary service, the ratchet.

Controls add to it. Occupancy sensors turn off lights in rooms no one is using, and daylight sensors dim fixtures near windows and skylights. Those cut energy most of all, and they can lower the peak when the busiest stretch falls on a bright afternoon. Less heat from the fixtures also means less work for the cooling system at the same hour. We do not promise a percentage, because the result depends on what else runs during your peak, and the bill shows that.

We replace fixtures or convert them to LED, rework switching and controls, and fix the wiring old fixtures hide, as described on our Houston LED lighting retrofit page. The price is set after the free written estimate.

How do you read the demand line on a commercial bill?

Find the delivery section of the bill, where the provider passes through CenterPoint's charges, and look for a demand figure in kVA or kW next to the energy figure in kWh. That demand figure is the month's peak. Compare it across two or three recent bills before a retrofit, then the same months after.

  • Write down the demand figure and the energy figure from at least three recent bills.
  • Note the season of each, since summer cooling raises the peak whatever the lighting does.
  • If the building is over 700 kVA, look for a separate transmission line based on 4CP.
  • After the retrofit, compare the same months, not just the next one, so the weather is a fair match.
  • Ask your provider for interval data if the bill does not show enough to see when the peak happens.

Fleet chargers are the other load that can move a demand charge, covered in our guide to fleet EV charging in Houston. For our other Houston work, see the Houston commercial electrician hub, and for our work across Texas, our commercial electrical services.

FAQ

Common questions

Straight answers. If you do not see yours, call us and ask.

Will an LED retrofit lower my CenterPoint demand charge?

It lowers the lighting share of your peak demand. How much that moves the charge depends on what else runs at your busiest fifteen minutes, which the bill's demand line shows.

Does the 80% ratchet apply to every Houston business?

No. In CenterPoint's tariff the 80% ratchet is on the primary service schedule. The secondary service schedule for loads over 10 kVA bills each month's own peak.

Why is my demand charge on my retail provider's bill?

CenterPoint charges its delivery service to your retail electric provider, which passes those charges through on the bill you receive.

Related help

Where to go from here

Ready to get it handled?

Flat-rate pricing quoted up front. Licensed and insured. A Wattsmith electrician calls you back within 15 minutes during business hours.

  • Licensed and Insured
  • BBB Accredited
  • Flat-Rate Pricing
  • Background-Checked
Call NowGet a Quote