Key takeaways
- A load study sets the building's measured demand against its service, so the room left for chargers is known before design.
- AEP's guide says the customer must notify the company before altering service entrance equipment.
- On AEP Texas's secondary schedule over 10 kW, billing demand is the highest 15-minute kW of the month.
- The 80% ratchet hits the distribution charge on primary service, and only certain riders on secondary service.
- A premises that has reached 700 kW is billed transmission on its 4CP kW, set by the summer ERCOT peaks.
Fleet EV charging in Corpus Christi begins with a measurement, not a charger catalog. The building's electrical service has a limit, the fleet has a nightly energy need, and the gap between them decides whether the chargers fit on today's service or need new service from AEP Texas. The same numbers decide how the delivery side of the power bill moves once the vehicles plug in. This guide covers the load study, AEP Texas's service requests, how its tariff bills demand, managed charging, NEC Article 625 and the City of Corpus Christi permit.
What does a load study show before fleet chargers go in?
It shows how much of the existing service the building already uses and how much is left. We record the building's actual demand over a period that covers its busy and quiet hours, add the chargers the fleet needs, and check the service, panels and feeders against the total.
The fleet's side of the study is just as concrete. It counts the vehicles, the distance each covers in a shift, the battery each carries and the hours each one sits at the yard. A route truck parked all night can charge slowly on a small circuit, while a vehicle that turns around in two hours needs a faster charger and a heavier feed. Those answers set the number and size of the chargers, and they keep the project from buying capacity it will never draw.
When does a charging depot need new service from AEP Texas?
When the chargers need more than the existing service can deliver. AEP Texas's Builders and Contractors page takes requests for temporary or permanent service through online forms, and its guide says the customer must notify the company before altering service entrance equipment, so facilities of proper capacity can be provided.
A depot on a new site uses the Permanent Service for a New Business form, which asks for the customer, the site address, driving directions, a mailing address, a phone number and details of the project. AEP's guide says it is written for homes and small commercial buildings, and that on larger commercial or industrial jobs the engineer, architect or electrical contractor contacts the company for detailed service requirements. A depot with several fast chargers is likely to sit in that second group, so the talk with AEP Texas starts early.
Sources: AEP Texas's Builders and Contractors page, its new business service form, and AEP's Guide for Electric Service and Meter Installations (2026).
What does AEP Texas need in a construction service request?
Six items, by its tariff: the customer contact name and phone number, the ESI ID if one exists, the service address with directions and access notes, the construction service wanted, and the requested date. AEP Texas says it will contact the named person within two business days to arrange the work.
The tariff is just as direct about time: AEP Texas will make reasonable provisions for construction service but does not guarantee its timeliness. For a fleet with vehicles arriving on a delivery date, that sentence is the reason to file the request when the load study is done, not when the chargers ship. New lines and transformers are utility work on the utility's schedule, and the depot's opening date should sit behind them.
Source: AEP Texas's Tariff for Retail Delivery Service, Section 5.3.2.
How does AEP Texas bill demand for a fleet depot?
A depot served at secondary voltage with demand over 10 kW falls under AEP Texas's non-residential schedule for that service. On it, AEP Texas bills delivery per kW of billing demand, which is the kW supplied during the 15-minute period of maximum use in the month. One busy quarter hour sets it.
AEP Texas bills in kW, and its delivery charges reach the business through the retail electric provider it chose: the tariff says the company bills the selected competitive retailer for delivery service, and the retailer's invoice carries those charges. For a fleet manager the point is plain. Chargers that all start at once when the trucks return set the month's billing demand, whatever the depot draws the rest of the time.
Sources: AEP Texas's Tariff for Retail Delivery Service, Sections 5.8.1 and 6.1.1.1.3, and the PUC's guide to choosing an electric plan.
Does the 80 percent ratchet apply to a fleet depot?
It depends on the service voltage. On secondary service over 10 kW, AEP Texas applies an 80% ratchet only to certain riders, not to the distribution charge. On primary voltage service, the distribution charge itself is billed on the higher of the month's demand or 80% of the highest demand in the previous 11 months.
The riders the secondary ratchet touches are named in the tariff as TC, NDC, SRC and ADFIT. On either voltage, a single month with every charger running flat out can carry forward into the bills that follow it. A large depot that takes primary service, with its own transformer, is worth designing with that ratchet in view from the first drawing.
Why do summer afternoon peaks matter to a large depot?
Because of 4CP billing. A premises that has reached 700 kW in any earlier month is billed transmission on its 4CP kW: its average demand at the ERCOT system's monthly 15-minute peaks in June, July, August and September of the previous year. Charging during those peaks raises the next year's figure.
Most fleets charge at night, after routes end, which keeps them clear of those afternoon peaks by habit. A depot that also tops up vehicles during the day, or runs a second shift, needs its controls set so charging stays light on summer afternoons. The 700 kW line is also a reason to plan the whole depot rather than only its first phase, because later phases can carry the premises across it.
How does managed charging keep the peak down?
Managed charging is a control system that divides a set amount of power among the chargers, so the depot never draws more than the limit chosen for it. Vehicles that leave first or need the most energy charge first, and the rest wait their turn. The fleet still leaves charged, and the peak stays flat.
On an AEP Texas bill a flat peak lowers the 15-minute billing demand, leaves less to carry forward under any ratchet that applies, and at large sites keeps the 4CP figure down. The NEC lets branch circuits and feeders be sized to the setting of a listed load management system, so managed charging can also keep a project on its existing service instead of a new one.
Which NEC article covers fleet charging equipment?
Article 625 of the National Electrical Code, which covers electric vehicle power transfer equipment. It treats EV charging as a continuous load, so circuits and overcurrent protection are sized at 125 percent of the charger's rating unless a listed load management system sets the limit. It also covers disconnects and personnel protection.
Which edition applies is settled with the City. Corpus Christi's codes page still lists the 2020 NEC with local amendments effective August 1, 2023, while TDLR made the 2026 NEC the state electrical code from September 1, 2026. We found no City page on how it handles that change, so we confirm the edition with the plan reviewer before drawings are final. One local amendment matters in a yard: the City generally allows only nonmetallic conduit underground, with an exception in its motor fuel dispensing rules.
Sources: the City's construction codes page, its code ordinance with local amendments, and TDLR's September 1, 2026 rule adoption.
What permits does a fleet charging project need in Corpus Christi?
A City electrical permit, applied for in the Dynamic Portal. When the project includes building work, the electrical permit is a child permit issued only after the master building permit is approved and paid. The City's commercial checklist asks electrical plans for a one-line diagram, a power plan and panel schedules.
New service is energized after the City's service release, and AEP Texas connects only after the proper authority approves the installation. Where Nueces Electric Cooperative is the provider, the co-op's own service and billing rules apply instead; the City says AEP Texas serves the majority of Corpus Christi, not all of it. The price of a charging project is set after the free written estimate.
We build these depots as Corpus Christi EV fleet charging. The release step is in our guide to the Corpus Christi service release. See also Corpus Christi commercial and industrial electrical work and our commercial electrical services. Sources: the City's building permits page, its commercial permit checklist, DSD-2001, and its recovering from disasters page.