CPS Energy New Commercial Service: The Portal, the Application and the Timeline

November 1, 2026Last updated 7 min readWattsmith Electric · TECL 41806

Key takeaways

  • CPS Energy is owned by the City of San Antonio and is the only retail electric provider in its service area.
  • New service starts with registration on the Construction and Renovation Web Portal and a Commercial Building Application with its signed and sealed attachments.
  • CPS Energy splits commercial customers at 300 kVA of diversified load: Small Commercial below, Large Commercial with a pad-mounted transformer at or above.
  • CPS Energy states its own timelines, including payment within 5 business days and 10 business days from the City's release to meter set.
  • Without the City's Release to CPS, the meter is set in a locked position.

New commercial electric service in San Antonio comes from CPS Energy, and the request runs on its own track beside the City permit. CPS Energy has a web portal, an application with required drawings, a design step, a contract and invoice, and its own inspections before the meter is set. This guide walks through CPS Energy new commercial service in the order CPS Energy publishes it, so a developer or owner knows which paperwork is due when and what the stated timelines are.

Who provides commercial electric service in San Antonio?

CPS Energy. It is owned by the City of San Antonio, and its April 2026 disclosure says it is the exclusive provider of retail electric service in its service area, because the City and CPS Energy have not opted in to retail competition. A San Antonio business does not shop for a retail provider.

CPS Energy describes itself as the nation's largest public power, natural gas and electric company. For a construction project the practical point is simpler: one utility designs the service, sets the meter and energizes it, and it follows its own published standards alongside the City's code.

See CPS Energy's who we are page and its quarterly update for the quarter ending April 30, 2026.

Where do you apply for CPS Energy new commercial service?

On CPS Energy's Construction and Renovation Web Portal. CPS Energy says to register there, then complete a Commercial Building Application, or download and email its Commercial Development Application. It says registrations are typically processed within 24 to 48 hours, and a contractor registering for the owner needs a Web Authorization Form.

The portal is also where the project is tracked, from temporary construction power through permanent service. CPS Energy lists Customer Design and Delivery at 210-353-4050 as the contact. Before a full application, CPS Energy offers a free, optional Utility Preliminary Plan Review meeting, which it says helps find items to fix before the complete work request is submitted.

The steps are in CPS Energy's New Commercial Construction step by step document.

What attachments does the Commercial Building Application need?

CPS Energy lists a load sheet, signed and sealed if design drawings are not yet at 100 percent; a signed and sealed electric and gas utility site plan; a signed and sealed meter loop drawing where the Electric Service Standards require one; a signed and sealed one-line diagram; and a site plan with easements identified.

  • Load sheet, sealed if the drawings are not final.
  • Electric and gas utility site plan, signed and sealed.
  • Electric meter loop drawing, signed and sealed when Section 90.3.2 of the Service Standards requires it.
  • Electric one-line diagram, signed and sealed.
  • Site plan with easements identified.
  • A Motor Load Form, which CPS Energy provides when the project has motors of 100 hp or larger.
  • A Distributed Generation Form, if it applies.

The load sheet is where the electrical design and the utility design meet. It is worked out from the connected loads and the design team's demand figures, and it sets the size of what CPS Energy designs. A load sheet that changes late usually means the utility design changes too.

What is the difference between Small and Large Commercial?

CPS Energy draws the line at 300 kVA of diversified load. Below 300 kVA it designates the customer Small Commercial and typically serves it with overhead transformers. At 300 kVA or more it classifies the customer Large Commercial and serves it with a pad-mounted transformer, which brings a transformer slab and duct bank into the site work.

The split carries over to existing buildings. CPS Energy's Electric Service Standards give separate contacts for upgrades on existing services above and below 300 kVA, so an expansion that pushes a building past the line changes who at CPS Energy handles it. For a renovation, CPS Energy says a designer will typically make contact within two business days, and invoices not paid within 90 calendar days are voided.

The renovation steps are on CPS Energy's commercial renovation page.

What happens after CPS Energy receives the application?

Once Customer Engineering has every required document, CPS Energy assigns a designer, who schedules a pre-design meeting. The meter layout is reviewed by its Electric Services and Metering Standards group. At the end of design, CPS Energy provides the final design, a contract and an invoice, and the customer installs the infrastructure to that design.

On a commercial job that infrastructure work is real site work: conduit, duct banks and transformer pads built to CPS Energy's sketch. CPS Energy inspects its own underground work before concrete is poured, for both the slab and the duct bank, and the inspection line is 210-353-3373. A pour before that inspection is a pour that may have to come out.

The pre-design meeting is the best time to settle the questions that move the schedule: where the transformer or meter sits, which easements the design needs, and whether the load sheet still matches the drawings. Bringing the electrical contractor to that meeting means the person who will build the infrastructure hears the designer's requirements first hand, instead of reading them later off a sketch.

How long does CPS Energy take to set a commercial meter?

CPS Energy's new commercial construction page gives its own timelines. It encourages developers to sign the contract and pay within 5 business days. It says easement review can take up to 3 weeks, its underground crews need about 15 business days, weather permitting, and it asks for 10 business days from the inspection release to meter set.

  • Contract and payment: within 5 business days, as CPS Energy encourages.
  • Easements: up to 3 weeks.
  • Underground crews: about 15 business days, weather permitting.
  • Meter set and energize: 10 business days after CPS Energy receives the inspection release.

The figures are from CPS Energy's new commercial construction page. Build them into the schedule early, because the last one starts only after the City's release.

Why would CPS Energy set a meter locked?

Because the City has not released the service yet. CPS Energy says every permit and inspection required by the authority having jurisdiction must be completed and released to CPS Energy before the meter is set. Without it, CPS Energy will still install the infrastructure and meters, but in a locked position until the inspections arrive.

In San Antonio that release is the City's Release to CPS. CPS Energy also says it must receive the electric meter loop inspection from the City before it can schedule a service crew. After final approval, DSD notifies CPS Energy that the property is safe to energize, and the owner then arranges service with CPS Energy. A locked meter is not a failure; it is the meter waiting on paperwork, and the 10 business day clock starts when the release arrives.

The City side of that step is in our guide to how commercial electrical permits work in San Antonio, and DSD explains it on its utility release page.

What are CPS Energy's Electric Service Standards?

They are CPS Energy's rule book for services and meter installations, published in a 2021 edition written for electrical contractors, architects and engineers. CPS Energy says the standards supplement the City of San Antonio electrical code, the National Electrical Code and the National Electrical Safety Code. The City code incorporates them for all electric services and meter installations.

That makes the Service Standards part of the inspection, not only the utility's preference. Meter loop construction, metering equipment and service layout all have to meet them. We read the drawings against the Service Standards before a bid, and every job starts with a free written estimate based on the drawings and the scope. Our license is TECL 41806.

Read the Electric Service Standards (2021 edition), and see our tenant build-out electrical work and commercial electrical services.

FAQ

Common questions

Straight answers. If you do not see yours, call us and ask.

Can a business in San Antonio choose a different electric provider?

Not within CPS Energy's service area. CPS Energy says it is the exclusive retail electric provider there because the City and CPS Energy have not opted in to retail competition.

Is the CPS Energy preliminary plan review required?

No. CPS Energy calls its Utility Preliminary Plan Review free and optional, offered before the complete application to catch items that need to change.

Who sends the inspection release to CPS Energy?

The City. In San Antonio, DSD staff check that the required inspections passed and send the Release to CPS. CPS Energy then schedules the meter set.

Related help

Where to go from here

Ready to get it handled?

Flat-rate pricing quoted up front. Licensed and insured. A Wattsmith electrician calls you back within 15 minutes during business hours.

  • Licensed and Insured
  • BBB Accredited
  • Flat-Rate Pricing
  • Background-Checked
Call NowGet a Quote